Attachment 0027 TE 5.2-03 -- USAG-RIA Chiller Heat Exchanger Evaluation.pdf

PDF 105 KB Posted

Attached to
RIA HVAC Services Federal contract opportunity
Solicitation number
W519TC-24-R-2015
Issued by
Department of the Army Materiel Command Contracting Command Rock Island Arsenal

About this file

This document is a Technical Exhibit outlining the requirements for conducting non-destructive eddy current testing on chiller heat exchangers at the Rock Island Arsenal (RIA). The key details are:

The testing must be performed by a qualified technician with a minimum of 10 years of specific experience in eddy current testing on absorption, Centrivac, and RHTB chillers. The technician must be certified to Level 3 proficiency per ASNT standards. The testing equipment must meet specific requirements for frequency selection, probe design, and calibration using standard test samples. Any tubes exhibiting defects exceeding defined thresholds for wall penetration, bulging, cracking, or restrictions must be rejected. The final report must include details on the chillers tested, equipment used, technician qualifications, and a summary of findings and recommendations. The report must be submitted to the Contracting Officer's Representative (COR) for approval two weeks prior to the end of the performance period.

View the file

Other files for this federal contract opportunity

Other files attached to RIA HVAC Services, newest first.
File Type Posted
W519TC-24-R-2015 Amendment 0003.pdf PDF
W519TC-24-R-2015 Amendment 0002.pdf PDF
Attachment 0041 Site Visit Sign In.pdf PDF
W519TC-24-R-2015 Amendment 0001.pdf PDF
Attachment 0040 Labor and Material Summary DMOs 25MAR2024.pdf PDF
Attachment 0001 ROCK ISLAND ARSENAL - MECHANICAL PWS -- 02APR2024.pdf PDF
Attachment 0004 Price Matrix 26MAR2024.xlsx XLSX spreadsheet
Attachment 0001 ROCK ISLAND ARSENAL - MECHANICAL PWS -- 20 MAR 2024.pdf PDF
Attachment 0002 Instructions to Offerors.pdf PDF
Attachment 0004 Price Matrix.xlsx XLSX spreadsheet
Attachment 0016 TE 1.10-01 -- Refrigeration Removal Certifications.pdf PDF
Attachment 0029 TE 5.2-05 -- Chilled Water Services.pdf PDF
Attachment 0035 TE 5.8-01 -- USAG-RIA Operation of Major Comfort Boiler Plants_20240301.pdf PDF
Attachment 0036 TE 6.0-01 -- USAG-RIA HVAC&R Contract Deliverables.pdf PDF
Attachment 0006 SCA Wage Determination 26DEC2023.pdf PDF
B08 Attachment 0009 VENDOR GUIDE Contract Opportunities All Topics.pptx PPTX presentation
Attachment 0015 TE 1.2-04 -- USACE Accident Investigation Report.pdf PDF
Attachment 0021 TE 2.2-01 -- USAG-RIA LIST OF GOVERNMENT FURNISHED SPACES.pdf PDF
Attachment 0023 TE 2.3-02 -- ISWMP REVISION March 23.pdf PDF
Attachment 0024 TE 2.4-01 -- USAG-RIA Integrated Cultural Resource Management.pdf PDF
Attachment 0026 TE 5.2-02 -- USAG-RIA Refrigerant Log Tally.xlsx XLSX spreadsheet
Attachment 0033 TE 5.4-01 -- USAG-RIA DMO Workload Summary.pdf PDF
Attachment 0032 TE 5.2-08 -- USAG-RIA PERFORMANCE EXPECTATIONS- 20230820.pdf PDF
W519TC-24-R-2015.pdf PDF
Attachment 0007 Past Performance Questionnaire.docx DOCX document
Attachment 0008 Small Business Participation Plan.docx DOCX document
Attachment 0017 TE 1.10-02 -- DD Form 1348-1A, Issue Release Receipt Document.pdf PDF
Attachment 0018 TE 1.10-03 -- ODC Equipment Tracker.xlsx XLSX spreadsheet
Attachment 0019 TE 2.1-01 -- USAG-RIA LIST OF GOVERNMENT FURNISHED PROPERTY.pdf PDF
Attachment 0020 TE 2.1-02 -- USAG-RIA LIST OF GOVERNMENT FURNISHED SERVICES.pdf PDF
Attachment 0022 TE 2.3-01 -- Standard Form 701 -- Activity Security Checklist.pdf PDF
Attachment 0039 Site Visit Map.pdf PDF
Attachment 0003 Basis for Award.pdf PDF
Attachment 0005 Davis Bacon Wage Determination 15MAR2024.pdf PDF
Attachment 0031 TE 5.2-07 -- USAG-RIA PM GUIDE - 20230821.pdf PDF
Attachment 0034 TE 5.4-02 -- USAG-RIA PWO Workload Summary.pdf PDF
Attachment 0037 TE 6.0-02 -- Transmittal Record.pdf PDF
Attachment 0038 TE 7.1-01 -- Prevailing Wage Rates 19MAR2024.pdf PDF
Show all 38

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TECHNICAL EXHIBIT 5.2-03

CHILLER HEAT EXCHANGER EVALUATION

PART 1 - GENERAL

1.01 METHOD: Non-destructive testing using Eddy Current method.

1.02 OBJECTIVES: The testing shall be conducted in a professional manner to assure minimal tube failure by a technician having proper training, adequate experience, modern equipment, and using the latest techniques.

1.03 TECHNICIAN QUALIFICATIONS AND VERIFICATION:

A. The contractor shall provide qualified servicemen having previous experience performing eddy current testing on chillers.

The work history of the technician performing the eddy current testing shall demonstrate a minimum of 10 years of specific eddy current experience on absorption, Centrivac, and RHTB chillers.

B. The contractor shall submit training certificates of completion in nondestructive testing applicable to chillers and certification of a level 3 proficiency per the American Society for Nondestructive Testing (ASNT), Recommended Practice Number

SNT-TC-1A, “Personnel Qualification and Certification in

Nondestructive Testing.”

1.04 TEST INSTRUMENTATION

A. The test equipment shall be digital, portable and proven capable of accurate inspection of in-service heat exchanger tubes.

B. The power supply (basic instrument) shall have a wide range of frequency selections to assure full penetration of the various alloys and wall thickness. Adjustment of the signal amplitude and phase angle will be used for quantitative evaluation.

C. The scope shall display both the X and Y-axis. The displayed signal shall be maintained on the scope readout by means of memory retention.

D. The sensing probe housing shall be a material designed for maximum wear resistance. The components inside the probe shall be encapsulated in a moisture free manner. The sensing coils shall be arranged in a manner that will permit detection of any type of discontinuities. Circumferential as well as longitudinal defects shall be located.

1.05 INSTRUMENT CALIBRATION: The technician shall have in his possession a length of tube (standard) identical to the tube material to be tested. The standard shall have natural or artificial discontinuities representing the different types of defects normally found in heat exchanger tubes. The instruments shall be calibrated

(using the standard) so that the signals react in a predictable manner. Proof of instrument calibration shall be provided to the

COR prior to testing any RIA equipment. Calibration shall be checked at approximately one-hour intervals, more often if the existence of electrical interference and background noise is detected. Standards shall meet or exceed ASME codes.

1.06 TEST PROCEDURE:

A. With proper calibration attained, the technician's assistant will manually move the probe through the entire length of every tube to be inspected. The probe shall be moved at a speed not to exceed the reaction time of the test instruments.

B. The technician will monitor the scope display constantly while this test is underway. Use of alarm systems is unacceptable.

1.07 RECORD: Any tubes displaying unusual or detrimental indications will be recorded on a field report form. In addition, defective tubes may be recorded on a strip chart recorder for permanent filling, if applicable.

1.08 EVALUATION STANDARD:

Support Wear Reject tubes indicating 20 % or more wall penetration.

Pitting Reject 40% or more wall penetration

Erosion Reject 40% or more wall penetration

Corrosion Reject 40% or more wall penetration

Bulging Reject any tube exceeding 20% expansion

Cracks Reject all tubes with cracks

Restricted Tubes Reject tubes when restrictions

(scale, dirt) will not permit the probe to move through the entire length of tube.

1.09 FINAL REPORT:

The final report shall contain as a minimum:

(1) Arsenal name and address and dated cover letter to the COR

(2) Unit model and serial numbers for all chillers inspected

(3) Service Agency name and address providing testing

(4) Model and description of test equipment

(5) Job information sheet for each chiller showing tube count, type, material, length, frequencies, and type of defects, if any.

(6) Summary, containing any pertinent information about the unit, and recommendations for defective tubes.

(7) A copy of Field Report

(8) Copies of strip chart recordings, when necessary

(9) Tube sheet layout example

(10) Technicians name and copy of his certification

(11) Copy of original specification to do this work

1.10 SUBMITTALS:

A. Employee work history, training certificates, and level of proficiency per ASNT personnel qualifications.

B. Submit a copy of the final report in a 3-ring binder to the COR two weeks prior to the end of the performance period for his approval.

C. Copies of catalog descriptions of test equipment, age, and statement of ownership or rental of test equipment.

D. Two copies of final report.

END OF SECTION