Attach L-10 - IRES SEPI SOO (A0006).docx

DOCX document 4 MB Posted

Attached to
MDA IT Operations & Engineering Solutions (MIOES) - CANCELED Federal contract opportunity
Solicitation number
HQ0857-MIOES-ZA
Issued by
DOD Missile Defense Agency

View the file

Other files for this federal contract opportunity

Other files attached to MDA IT Operations & Engineering Solutions (MIOES) - CANCELED, newest first.
File Type Posted
MIOES TO Phase-in Schedule (Preliminary).pptx PPTX presentation
MIOES DRFP Inc1 CONSOLIDATED QandAs.xlsx XLSX spreadsheet
MIOES Industry Day Overview and Instructions.docx DOCX document
MDA 5013.06 - Source Selection Procedures.pdf PDF
MIOES MDIOC Facility Operations and Sustainment PWS DRFP Inc3.pdf PDF
Attachment L-5 MIOES Question Matrix DRFP Inc3.xlsx XLSX spreadsheet
MIOES 1-on-1 Participant List and Topics.xlsx XLSX spreadsheet
MIOES Cybersecurity PWS DRFP Inc3.pdf PDF
MIOES Section L DRFP Inc2 Rev1.docx DOCX document
MIOES Section M DRFP Inc2.docx DOCX document
Attachment L-3 OCI Analysis Disclosure Form DRFP Inc2.pdf PDF
MIOES LCAT Table DRFP Inc2.xlsx XLSX spreadsheet
Attachment L-6 MIOES Evaluation Scenarios DRFP Inc2.docx DOCX document
MIOES Basic IDIQ PWS 24 June DRAFT RFP.pdf PDF
MIOES Acquisition Strategy Summary - 14 June DRAFT RFP.pdf PDF
QA_DRFP_Inc1_MIOES.xlsx XLSX spreadsheet
MIOES Phase-In Task Order PWS 14 June DRAFT RFP.pdf PDF
MIOES Basic IDIQ PWS 14 June DRAFT RFP.pdf PDF
MIOES Industry Monthly Chargeback Showback - May.pptx PPTX presentation
MIOES Industry Monthly CSSP - June.pptx PPTX presentation
MIOES SE Overview (15 Feb 24).pptx PPTX presentation
22F8900_PWS.pdf PDF
23F3100_PWS.pdf PDF
23F8600_PWS.pdf PDF
23F7300_PWS.pdf PDF
22F5900_PWS.pdf PDF
18F8002_PWS.pdf PDF
23F8700_PWS.pdf PDF
23F1500_PWS.pdf PDF
MIOES OCI Guiding Principles (Final).pdf PDF
20230405-MIOES_Industry_Day_POC.xlsx XLSX spreadsheet
20230103-MIOES_Industry_Day_POC-1.xlsx XLSX spreadsheet
20230103-MIOES_Industry_Day_POC.xlsx XLSX spreadsheet
Attachment J-02 - IRES WBS and CSDR.pdf PDF
Attach L-02 - Team List.docx DOCX document
Attach L-05 - Consent Letter.docx DOCX document
Attach L-07 - PPQ (A0001).docx DOCX document
Attach L-14 - Cost Price WB 1 (A0001).xlsx XLSX spreadsheet
Attachment J-03 - IRES Labor Category Descriptions.xlsx XLSX spreadsheet
Exhibit A - MDA Mandatory CDRLs.docx DOCX document
Exhibit B - IRES CDRLs.docx DOCX document
Attach L-06 - Client Authorization Letter.docx DOCX document
Attach L-11 - EITS SOO (A0005).docx DOCX document
Attach L-12 - FEO SOO (A0005).docx DOCX document
Attach L-16 - Cost Price WB 3 (A0003).xlsx XLSX spreadsheet
Section M (A0006).docx DOCX document
Attachment J-01 - IRES Contract SOO (A0005).docx DOCX document
Attachment J-04 - DD254.pdf PDF
Attach L-17 - Tool App Questionnaire (A0005).docx DOCX document
Section L (A0008).docx DOCX document
Show all 50

MDA IT Operations & Engineering Solutions (MIOES) - CANCELED has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

By submitting a proposal for Task Order 2000, SE&PI, the Offeror agrees to furnish all services and items upon which the prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule if this Task Order offer is accepted by the Government anytime from award of the contract resulting from H95001-15-R-0001 through 180 calendar days thereafter.

Period of Performance

Start date:Contract Award Notification plus 180 calendar days
Duration:4.5 year base, potential for 3 one year award terms

Contract Type This is a cost-plus-incentive-fee (CPIF) / Award Fee (AF) task order. The Offeror shall propose a target cost, target fee, and the award fee pool. The target cost is inclusive of all cost elements, including labor, material, and other direct costs (ODCs). The minimum fee shall be 3% of target cost. The maximum fee shall be 15% of target cost. The share ratio above target cost is 60 (Government)/40 (Contractor). The share ratio below target cost is 40 (Government)/60 (Contractor).

The Offeror’s proposed target fee percentage shall not exceed the fee percentages as proposed on Attachment L-16: Cost / Price Workbook 3, WS3-3: Fee Structure Table.

Payments for all contract line item numbers (CLINs) will be made in accordance with FAR 52.216-7, Allowable Cost and Payment. Payments and the fee payable under the task order are subject to adjustments in accordance with FAR 52.216.10, Incentive Fee, and performance assessments conducted in accordance with the IRES Performance Evaluation and Incentive Plan (Attachment J-06).

In addition to adjustments authorized in accordance with FAR 52.216-10(d), adjustment of the target cost due to a variance in the actual cost incurred when compared to the Government’s plug number (GPN) for other direct costs (ODC) may be considered if actual ODC costs exceed +/- 15%. The adjustment will only be made by the amount the actual cost incurred exceeds the +/- 15% threshold; no adjustments to fee will be made.

The CLIN structure for Task Order 2000 – SE&PI is provided in Table 1: Task Order 2000 – CLIN Structure.

Task Order Award Fee Plan / Evaluation Elements and Weights In addition to the incentive fee, the contractor may earn Award Fee on this task order (CLINs 0080, 0081 and 0082) for above satisfactory (good or higher) performance. In accordance with the IRES Performance Evaluation and Incentive Plan, task orders receiving an evaluation of satisfactory or less will result in zero award fee; satisfactory performance is acknowledged within the incentive target fee.

The IRES Performance Evaluation and Incentive Plan defines the roles, responsibilities and process for evaluating and determining the Award Fee. The evaluation elements and weights for Task Order 2000 – SE&PI are defined in Table 2: Task Order 2000 – SE&PI Award Fee Evaluation Elements and Weights.

Table 1: Task Order 2000 – CLIN Structure

CLIN
Supplies / Services
Type
QTY
Unit
Amount
0001
Services/Solutions (Base)
CPIF
54
Month
Target Cost:*
Target Fee:*
Total Target Cost + Fee*
Minimum Fee:*
Maximum Fee:*

Share Ratio Above Target (Gov/Cont): 60/40 Share Ratio Below Target (Gov/Cont): 40/60

0002
Expensed CAP IT Hardware (Base)
Cost
54
Combo
Target Cost*, **
0003
Expensed CAP IT Software (Base)
Cost
54
Combo
Target Cost*, **
0080
Award Fee Period 1 (Base)
Cost
1
Lot
Award Fee Pool:*
0081
Award Fee Period 2 (Base)
Cost
1
Lot
Award Fee Pool:*
0082
Award Fee Period 3 (Base)
Cost
1
Lot
Award Fee Pool:*
0090
Data (Base)
FFP
1
Lot
Not Separately Priced (NSP)
0091
CAP Delivery / CDRL (Base)
FFP
1
Lot
Not Separately Priced
1001
Services/Solutions (Award Term (AT) 1)
CPIF
12
Month
Target Cost:*
Target Fee:*
Minimum Fee:*
Maximum Fee:*

Share Ratio Above Target (Gov/Cont): 60/40 Share Ratio Below Target (Gov/Cont): 40/60

1002
Expensed CAP IT Hardware (AT1)
Cost
12
Combo
Target Cost*, **
1003
Expensed CAP IT Software (AT1)
Cost
12
Combo
Target Cost*, **
1090
Data (AT1)
FFP
1
Lot
Not Separately Priced (NSP)
1091
CAP Delivery / CDRL (AT1)
FFP
1
Lot
Not Separately Priced
2001
Services/Solutions (Award Term(AT) 2)
CPIF
12
Month
Target Cost:*
Target Fee:*
Minimum Fee:*
Maximum Fee:*

Share Ratio Above Target (Gov/Cont): 60/40 Share Ratio Below Target (Gov/Cont): 40/60

2002
Expensed CAP IT Hardware (AT2)
Cost
12
Combo
Target Cost*, **
2003
Expensed CAP IT Software (AT2)
Cost
54
Combo
Target Cost*, **
2090
Data (AT2)
FFP
1
Lot
Not Separately Priced (NSP)
2091
CAP Delivery / CDRL (AT2)
FFP
1
Lot
Not Separately Priced
3001
Services/Solutions (Award Term (AT) 3)
Cost
12
Month
Target Cost:*
Target Fee:*
Minimum Fee:*
Maximum Fee:*

Share Ratio Above Target (Gov/Cont): 60/40 Share Ratio Below Target (Gov/Cont): 40/60

3002
Expensed CAP IT Hardware (AT3)
Cost
54
Combo
Target Cost*, **
3003
Expensed CAP IT Software (At3)
Cost
54
Combo
Target Cost*, **
3090
Data (AT3)
FFP
1
Lot
Not Separately Priced (NSP)
3091
CAP Delivery / CDRL (AT3)
FFP
1
Lot
Not Separately Priced
*Cost Price Workbook 3, WS3-5: TO 2000 Prop
**Fee, if proposed, will be incorporated into the target fee on CLINs 0001, 1001, 2001 or 3001. These CLINs are for funding and invoicing only; the contractor’s work breakdown structure must associate the purchase of all other direct costs (including the CAP under these CLINs) with the activity accomplished.

H95001-15-R-0001-0006 Attachment L-10

Sep 21, 2016 Table 2: Task Order 2000 – SE&PI Award Fee Evaluation Elements and Weights

Performance Adjective
Unsatisfactory
Satisfactory
Good
Very Good
Excellent
AF Rating
0
1 – 50
51 – 75
76 – 90
91 – 100
AF Earned
0%
0%
51% – 75% of AF Pool
76% – 90% of AF Pool
91% – 100% of AF Pool
Element
Weight
Unsatisfactory
Satisfactory
Good
Very Good
Excellent
Risk Management
40%
Contractor fails to perform at the satisfactory level.
Risk analyses performed at the task order level.
Contractor develops risk analyses of proposed and/or required technical or schedule changes that include an integrated assessment of the impact on all task orders.
Good plus:

Mitigation plans include alternative or parallel courses of action and nominates preferred solutions. Plans contain sufficient data (e.g., estimated financial impact) to allow the government to make an informed decision.

Very Good plus:

Contractor employs early corrective action(s) and planning to preclude potential mission impacts.

Innovative Methods, Techniques, or Technologies
40%
Contractor fails to perform at the satisfactory level.
Contractor identifies innovative methods, techniques, or technologies.
Contractor identifies and implements appropriate use innovative methods, techniques, or technologies to accomplish tasks more efficiently.
Good plus:

Innovative methods, techniques, technologies and/or process improvements result in increased effectiveness and efficiencies throughout the contract.

Very Good plus:

Effectiveness and efficiencies gained are quantified and documented.

Financial Forecasts
20%
Contractor fails to perform at the satisfactory level.
Forecasts are reasonably documented and are reconcilable.
Contractor delivers cost and schedule data that provides visibility into current and forecast program costs and schedule.

Forecasts are fully traceable within and between reports.

Good plus:

Contractor delivers cost and schedule data that provides clear visibility and traceability from current status to forecasted costs and schedule.

Very Good plus:

Contractor recognizes where cost growth may occur and provides detailed explanations for actual or potential problems; projections and justification are detailed in the variance analysis report.

IRES

Integrated Research & Development for Enterprise Solutions

Attachment L10:

IRES Systems Engineering and Program Integration (SE&PI) Statement of Objectives (SOO)

Sep 21, 2016 Table of Contents

1.0Vision and Purpose Statement1
1.1Vision1
1.2Purpose1
2.0Background1
3.0Scope1
4.0Service Summary Items2
5.0Statement of Objectives and Outcomes2
5.1Task Order Administration4
5.1.1Description4
5.1.2Outcomes4
5.1.3Desired Attributes4
5.1.4Constraints4
5.2Systems Engineering5
5.2.1Description5
5.2.2Outcomes5
5.2.3Desired Attributes5
5.2.4Constraints6
5.2.5Workload Data6
5.3Program Integration6
5.3.1Description6
5.3.2Outcomes6
5.3.3Desired Attributes10
5.3.4Constraints10
5.3.5Workload Data11
5.4Continuity of Services11
5.4.1Description11
5.4.2Outcome11
5.4.3Desired Attributes11
5.4.4Constraints11
6.0Contract Deliverable Requirements List (CDRL)12
6.1CDRL Identification12
6.2CDRL Tailoring14
6.3Milestones14
7.0Government Furnished Equipment (GFE) / Government Furnished Information (GFI)14
8.0Special Requirements14
9.0Applicable Directives / Regulations14
10.0Contractor-developed PWS (CPWS)14
11.0Contractor-proposed Service Summary Item Table14
TO 2000 Exhibit C15

Sep 21, 2016 Page i IRES Systems Engineering and Program Integration (SE&PI)

1.0Vision and Purpose Statement
1.1Vision

Effective systems engineering and program integration that results in a consistent requirements execution methodology and increased mission assurance at reduced program costs. Innovative solutions are desired, but not at the expense of mission success.

1.2 Purpose

Task orders to be issued under the IRES program are dependent, either wholly or partially, on one another. It will be the responsibility of this task order to provide efficient and effective systems engineering processes to deliver integrated solutions across all stakeholders utilizing this contract to execute requirements.

2.0 Background

NOTE: This information is provided as an aid to offerors; it is not intended to direct or influence the proposed solutions or contractor-developed performance work statement submitted in response to this SOO.

Task orders issued on the JRDC that are considered predecessor task orders to this SOO include:

· 8001, Program Execution & Systems Engineering

· 8003, Facility Support, Task B.4

· 6001, Program Execution & Engineering

· 6003, Facility Support, Task B.4

· 5002, Management and Integration

· 5001, Engineering

· 5003, Facility Support, Task H.4

· 4002, Management and Integration

· 4001, Engineering

· 3002, Management and Integration

· 3001, Engineering

· 2002, Management and Integration

3.0 Scope

The task order issued as a result of this SOO will protect Ballistic Missile Defense System (BMDS) baseline integrity while supporting the successful technical execution of all Missile Defense Agency (MDA) events and mission activities performed under the IRES contract.

4.0 Service Summary Items

In accordance with the IRES Performance Evaluation and Incentive Plan, Service Summary Items (SSIs) 1 through 4 are common [required] on all task orders and will be assessed at the contract level.

SSI 5 through n [Technical Performance] captures the specific task order Service Summary Items deemed essential to successful execution of the task order (note: To be developed / defined using the performance measures proposed by the contractor.) Exhibit 1 defines the SSIs applicable to this task order.

5.0 Statement of Objectives and Outcomes

The MDIOC assets support the BMDS operational, training and test missions; these assets must be protected to ensure their availability and ability to support MDA mission activities. MDA’s BMDS Integrated Master Test Plan (IMTP) establishes the framework for the BMDS test program. The BMDS IMTP is an overarching document that describes the BMDS test environment, supporting test organizations, developmental and operational test programs, and management of MDA test resources, and is the definitive source for detailed test planning and execution guidance. MDA partners with the Services and Combatant Commands to plan and execute the BMDS training, exercise and war gaming missions. Operational BMDS support activities are directed by the war fighting community and strongly influenced by uncertain real-world events.

The systems engineering function performed under this task order ensures that the work provisioned and executed under the numerous IRES task orders is fully coordinated and synchronized, and that the work is executed in accordance with program governance. The program integration function performed under this task order ensures that the technical solutions for task orders in the acquisition pipeline adhere to appropriate governance documents, and are optimized and integrated for maximum effectiveness and performance. Together these functions monitor and govern all work executed under the contract.

Outcomes are task order requirements that must be captured in the Contractor Performance Work Statement (CPWS). Thresholds which identify a specific performance level must also be incorporated into the CPWS. Desired attributes are both quantifiable and non-quantifiable performance goals/objectives that the Government would like to achieve, and are provided as assistance in developing proposal/CPWS performance thresholds and service summary items. Constraints are limitations on the contractor’s technical or management approach/solution. The contractor's approach/solution must comply with the constraints.

All activities conducted on this task order must adhere to the special requirements identified in the contract-level SOO (Contract Attachment J-1). In the event of a conflict between Section 5.0 of the SOO and the CPWS, Section 5.0 of the SOO takes precedence.

Sep 21, 2016 Page 1 Exhibit 1. SSIs and Weights Applicable to This Task Order

SSI #
Title
Description
Performance Threshold

UNACCEPABLE

Performance Threshold

ACCEPTABLE

Performance Threshold

OBJECTIVE

Weight
Assessment Method
SSI 1
Integration
Task order activities / requirements are coordinated / deconflicted with other task orders to meet negotiated schedules. Contract / Task order schedules provides a realistic performance baseline that allows for early identification and mitigation of risk.
The integrated master schedule (IMS) is not resource loaded and critical path does not identify external task order or contract dependencies.
The IMS is resource loaded but critical path does not identify external task order or contract dependencies.
The IMS is resource loaded and critical path identifies external task order and contract dependencies
25%

25 QPI

EVM Program Analyst: review of the task order schedule(s) and the IMS.

QPI Score = 0
QPI Score = 12.5
QPI Score = 25
SSI 2
Small Business Utilization
On track to meet or exceed all goals established in the Small Business (SB) Participation and Commitment Plan.
Contractor fails to meet the SB goal in the SB Participation and Commitment Plan.
Contractor meets the SB goal, and meets greater than 25% but less than 50% of the SB subcategory goals in the SB Participation and Commitment Plan.
Contractor meets the SB goal and meets 50% or more of the SB subcategory goals in the SB Participation and Commitment Plan.
5%

5 QPI

COR: Review of Task Order 2000 – CDRL C012

QPI Score = 0
QPI Score = 2.5
QPI Score = 5
SSI 3
Customer Satisfaction
‘Customer’ is defined as any service provider or user of the products and services delivered under the task order.
Customer surveys result in product and service rating of 1.5 or less out of a possible 5.0.
Customer surveys result in product and service rating greater than 1.5 but less than 4.0 out of a possible 5.0.
Customer surveys result in product and service rating of 4.0 or higher out of a possible 5.0.
20%

20 QPI

COR: Customer Survey: twice annually prior to performance evaluations (mid and final)

QPI Score = 0
QPI Score = 10
QPI Score = 20
SSI 4
CDRL, Proposal and Milestone Timeliness
CDRLs, proposals and milestones are delivered / accomplished in accordance with the agreed to timeline and specifications.
85% or less of CDRLs proposals, and milestones are delivered or accomplished in accordance with agreed to time line and in accordance with SF1423, Data item Description (DID) and /or request for proposal specifications.
Greater than 85% but less than 95% of CDRLs proposals, and milestones are delivered or accomplished in accordance with agreed to time line and in accordance with SF1423, DID, and / or request for proposal specifications.
95% or more of CDRLs proposals, and milestones are delivered or accomplished in accordance with agreed to time line and in accordance with SF1423, DID, and / or request for proposal specifications.
5%

5 QPI

Data manager: 100% Inspection: CDRL / Proposal delivery / milestone accomplishment record.

QPI Score = 0
QPI Score = 2.5
QPI Score = 5
SSI 5 – SSI n
Technical Performance 5 – n
* to be specified in the Task Order Service Summary Item Table.
*
*
*
45%

45 QPI

Sep 21, 2016Page 3
5.1Task Order Administration
5.1.1Description

Successfully integrate and coordinate all activity necessary to efficiently execute this task order.

5.1.2Outcomes
5.1.2.1An Integrated Program Management Report (IPMR) that contains data for measuring cost and schedule performance for the SE&PI task order. The required SE&PI IPMR required formats are:

· Format 1 defines cost and schedule performance data by product oriented Work Breakdown Structure (WBS); Format 1 will provide data at WBS Level 4.

· Format 2 defines cost and schedule performance data by the contractor's organizational structure.

· Format 5 is a narrative report used to provide the required analysis of data contained in Formats 1 and 2.

· Format 7 defines the time-phased historical and forecast cost submission.

CDRL C001: TO 2000: Integrated Program Management Report

5.1.2.2 Delivery of the contractor acquired property (CAP) for the SE&PI task order.

CDRL C002: TO 2000: Interim Government Property Inventory Report

5.1.2.3 Initial task order baseline review and monthly task order status reports consisting of significant accomplishments, issues, concerns, and risks.

CDRL C003: TO 2000: Task Order Status Report MILESTONE: Initial Baseline Review

5.1.2.4Delivery of task order modification proposals. [Note: costs associated with future task order modification proposals should not be proposed in response to this SOO statement and should not be included in the Task Order Administration algorithm requested under Subfactor 1a. This SOO statement is for future cost collection purposes, if modification proposal preparation costs are a direct charge to the contract.]
5.1.3Desired Attributes

a. Situational awareness of task order activities.

b. Frequent and open communication.

5.1.4 Constraints

None.

5.2Systems Engineering
5.2.1Description

An overarching, program-wide perspective is necessary to effectively perform systems engineering in the dynamic operating environment supported by the IRES contract. Events, activities, projects and products conducted or delivered under the numerous IRES task orders must be coordinated to maintain configuration control, reduce execution risk and result in mission assurance. The systems engineering function executes the work processes that cross multiple stakeholders and are considered necessary to provide mission assurance. The systems engineering function also develops, manages, and maintains Department of Defense Architecture Framework (DoDAF) data used in a Federal and Department of Defense (FEA, DODEA) compliant architectural repository for the IRES contract.

5.2.2Outcomes
5.2.2.1Execute a configuration management program, ensuring positive configuration control for all IRES provisioned or MDIOC-hosted systems and services enabling BMDS concurrent test, training, and operations.
5.2.2.2Execute the mission assurance program ensuring protection of critical mission operational and shared infrastructure resources.
5.2.2.3Implement the risk management program providing insight to mission execution and performance risk.
5.2.2.4Operational asset and event coordination and critical systems and services protection, to include event identification and planning, event architecture coordination, Critical Asset List (CAL) development and sustainment of event coordination, event and resource de-confliction, and proactive event asset (CAL) protection.

CDRL C004: Event Packages (Assume 35 – 45 annually)

5.2.2.5 A robust Systems Engineering Management Plan (SEMP) that enables full integration of the activities performed under the contract.

CDRL C005: Systems Engineering Management Plan (SEMP)

5.2.2.6Development of reliability, availability, maintainability (RAM) assessments utilizing reliable data, allowing the government to make informed decisions.
5.2.2.7Implementation of the environmental and safety program providing the necessary cooperation, coordination, and technical support for external inspections and audits.

CDRL C006: Accident / Incident Report(s) (Assume 12-16 annually) CDRL C007: Chemical Inventory and Hazardous Material Usage Report

5.2.3 Desired Attributes

a. Performance measures that demonstrate improved product and services.

b. Situational awareness and health and status for monitored systems and assets.

c. A real-time technical baseline ensuring positive configuration control enabling informed decision making.

d. No mission or event impacts due to lack of thorough systems engineering, configuration management or event coordination of activities.

e. Environmental compliance and safety awareness are integral to all activities.

f. Zero Environmental Notices of Violation (NOVs).

5.2.4 Constraints

None.

5.2.5Workload Data
a.Nine active stakeholders, but IRES is an Agency-level contract vehicle and therefore is available to all MDA two-letters.
b.20 – 25 active task orders.
c.Freeze periods (periods during which configuration management and configuration control is of heighten interest) ranged between 200 and 230 days in calendar year 2014. Events activating a freeze included: 8 wargames, 12 exercises, 8 flight tests, 12 ground tests, and 300 separate network enclaves.
5.3Program Integration
5.3.1Description

Program integration provides for the planning, coordination, technical direction, and surveillance of the activities necessary to assure disciplined work performance and timely resource application to accomplish all task orders issued under the IRES.

Program integration also assures the technical excellence, cost effectiveness, non-duplication of services, and timeliness of all ordered (procured) work and deliverable products/services. The driving requirement is to balance risks and opportunities with clear intent to adjust processes and resources to achieve mission success.

5.3.2Outcomes
5.3.2.1Program-level reports are delivered.

Program-level reports consist of overarching contract requirements as well as a consolidation of reports delivered under various task orders.

5.3.2.1.1 A program management plan that describes the contractor’s organization, assignment of functions, duties, and responsibilities, management procedures and policies, and reporting requirements for the conduct of contractually-imposed tasks, projects, or programs.

CDRL C008: IRES Program Management Plan

5.3.2.1.2 A Contractor Work Breakdown Structure (CBWS) that satisfies the guidelines of DoD 5000.04-M-1 and the requirements in the Government-approved CSDR plan for the contract, Exhibit C - DD Form 2794.

CDRL C009: Contract Work Breakdown Structure (CBWS)

5.3.2.1.3 A Contract Funds Status Report (CFSR) providing funding data about task orders for the purpose of: (a) updating and forecasting contract funds requirements, (b) planning and decision making on funding changes to contracts, (c) developing funds requirements and budget estimates in support of approved programs, (d) determining funds in excess of contract needs and available for de-obligation, and (e) obtaining rough estimates of termination costs.

CDRL C010: Contract Funds Status Report (CFSR)

5.3.2.1.4 A labor hour report in accordance with latest Enterprise-wide Contractor Manpower Reporting Application (eCMRA) directive. This report is designed to collect information on funding source, contracting vehicle, organization supported, mission and function performed, and labor hours and costs for contracted efforts providing services to the MDA. The contractor’s transmittal letter shall contain the following information for all subcontractors required to submit an annual report: Subcontractor, Subcontract Number, Subcontractor Size Classification, and Subcontractor NAICS.

CDRL C011: Enterprise-wide Contractor Manpower Reporting Application (eCMRA)

5.3.2.1.5 A report that provides actual achievements relative to the utilization goals in the Small Business Participation and Commitment Plan and the results of the Contractor’s efforts to (a) expand the pool of qualified small businesses, (b) engage small businesses to serve as second sources, and (c) involve small businesses in each of the IRES HLOs.

CDRL C012: SB Subcontractor Report, IRES Contract

5.3.2.1.6 An IRES Integrated Program Management Report (IPMR) that contains data for measuring cost and schedule performance at the IRES Program Level. This report is a compilation of all IMPRs submitted under individual task orders into a single delivery. This report does not create or develop new data.

CDRL C013: IRES Integrated Program Management Report

5.3.2.1.7 A consolidated IRES program status report that captures (archives) program management reports developed under individual task orders. This report is a compilation of all program management reports submitted under individual task orders into a single delivery. This report does not create or develop new data.

CDRL C014: IRES Program Status Report

5.3.2.1.8 Delivery of the Data Accession List (DAL), providing a medium for identifying contractor internal data which has been generated under the various task orders.

CDRL C015: IRES Data Accession List (DAL)

5.3.2.1.9 Cybersecurity Risk Management Plan that includes threat analysis, system exposure to threats, integration of Cybersecurity risk management with other systems engineering process areas, and Cybersecurity risk mitigation.

CDRL C016: Cybersecurity Risk Management Plan

5.3.2.1.10 Cybersecurity Controls Statement(s) of Compliance that detail policies, procedures and standards for protecting critical unclassified information (CUI) from unauthorized access from both internal and external sources. A statement of compliance is required for all team members that may access CUI.

CDRL C017: Cybersecurity Controls Statement(s) of Compliance

5.3.2.1.11 Cyber Incident or Compromise Report(s) reporting as much of the information defined in DFAR Clause 252.204-7012 (d)(1) as can be obtained within 72 hours of any reportable cybersecurity incident.

CDRL C018: Cyber Incident or Compromise Report(s)

5.3.2.1.12 Verification that the contractor workforce performing cybersecurity functions are in compliance with the guidelines found in DoD 8570.01-M (chapters 3, 4, 5, 10 and 11).

CDRL C019: Cybersecurity Workforce Management Report

5.3.2.2 Program-level plans and programs are documented and deployed.

Program-level plans and programs provide overarching contract governance, contributing to mission assurance.

5.3.2.2.1 A quality assurance program that contains processes to enable the workforce to efficiently and effectively perform the myriad tasks required to successfully execute the efforts issued the IRES contract.

CDRL C020: Quality Assurance Program Plan

5.3.2.2.2 A robust risk management program that identifies, tracks and mitigates (to the extent possible) mission execution and performance risk.

CDRL C021: IRES Risk Management Plan

5.3.2.2.3 A comprehensive configuration management plan / program that enables the identification and management of critical asset lists, facility/IT modifications, project designs and proposals, and test architectures.

CDRL C022: IRES Configuration Management Plan

5.3.2.2.4 An environmental program that addresses Environmental Compliance, Pollution Prevention, and Conservation and is in accordance with Federal, State, Schriever AFB, and MDA environmental laws and regulations. Specific programs include, but are not limited to:

· Hazardous/Universal Waste Management

· Hazardous Material (to include HAZMART pharmacy and Green Procurement)

· Qualified Recycling Program

· Energy/resource conservation

· Ozone-depleting chemicals (ODC’s)

· Emergency Planning and Community Right-to-Know (EPCRA)

· Hazardous Material Spill Response CDRL C023: Environmental Program Plan

5.3.2.2.5 A mishap prevention and program safety plan that addresses safety of IRES-managed facilities (MDIOC), equipment and workforce.

· Compliance with the requirements of the designated Air Force HAZMAT authorization and tracking system, which is currently the Enterprise Environmental, Safety, and Occupational Health – Management Information System (EESOH-MIS).

· Mishap Prevention and Safety Plan that addresses lock-out/tag-out, confined space entry, electrical safety, mishap investigation and reporting, safety risk assessment, safety education and training, Hazard Communication Program, and other areas that ensure full compliance with 29 CFR 1910.1200, Hazard Communication Program.

· Documented ergonomic procedures that ensure that the MDIOC workforce are reasonably accommodated to perform their individual work activities.

· MDIOC Facility Evacuation Plan.

· Documented regular safety and fire protection inspections at the MDIOC followed by corrective action plans.

CDRL C024: Mishap Prevention and Safety Plan CDRL C025: MDIOC Facility Evacuation Plan

5.3.2.3 Task order close-out documentation is provided

As a task order period of performance ends, task order close-out documentation will be delivered. This documentation includes, at a minimum: identification of primary companies contributing to the execution of the task order; a summary of significant accomplishments; status of work in progress; task order cost data; a list of CDRLs delivered; a list of data accession list items (DAL) produced; a task order level labor hour report, similar to the Enterprise-wide Contractor Manpower Reporting Application (eCMRA) directive; and a task order level Small Business Subcontractor Utilization Report. Assume approximately 200 task orders will be issued over the life of the contract.

CDRL C026: TO TBD: Task Order Close-Out Report CDRL C027: TO TBD: Final Contractor Acquired Property Report

5.3.2.4 Information management system

A program-level, on-line, searchable management information system that captures all products (i.e., CDRLS) developed / submitted (i.e., Data Ascension List (DALs)) on the contract.

CDRL C028: IRES Program Information Management System Documentation

5.3.3 Desired Attributes

a. Situational awareness of program activities.

b. Reliable forecasts that can be used for management decisions. Realistic performance baselines that facilitates early identification and mitigation of risk; baseline integrity is maintained and changes are fully documented.

c. The Contractor Work Breakdown Structure efficiently supports the tenants of MIL-STD-881c.

d. Small business reports capture both the quantitative performance measures (e.g., subcontracting dollars / percentages) as well as the qualitative performance measures (e.g., contributions to mission execution).

e. The program status reports capture accomplishments, issues, concerns at both the task order and program level. The report documents cost control initiatives implemented at the task and project level.

f. The prime contractor collects / consolidates team members Cybersecurity Controls Statement(s) of Compliance into a single document for delivery.

g. Program plans are applicable to all task orders issued under the contract.

· Processes that are streamlined, well-defined, transparent to the customers and incorporate performance measures.

· Processes that can be tailored, as necessary, by an innovative and creative workforce to respond to immediate and unique needs of customers.

· Non-value added process steps and outdated, bureaucratic processes are systematically eliminated.

· Program plans are reviewed and updated annually.

h. The management information system is accessible to the MDA workforce with no access restrictions.

5.3.4 Constraints

None.

5.3.5 Workload Data

a. Nine active stakeholders, but IRES is an Agency-level contract vehicle and therefore is available to all MDA two-letters.

b. 20 – 25 active task orders; formal EVMS may not be required on all task orders, however all task orders will be required to report cost data on IPMR formats 1 and 2.

c. Historically, 350-450 CDRLs and 1,000-1,500 DALs have been provided annually; development of CDRLs and DALs is accomplished under the various task orders.

5.4Continuity of Services
5.4.1Description

Services delivered under this contract are vital to the Government and must be continued without interruption upon contract expiration. In the event a follow-on contract is awarded to other than the IRES incumbent, the contractor shall cooperate fully to the extent required to permit an effective, orderly, and successful transition from IRES to the follow-on contract(s). The contractor shall furnish sufficient orientation, training, and equipment/system familiarization required by any follow-on Contractor(s). This may include a collective daily discussion between the contractor, follow-on contractor(s), and the Government on the status of the phase-out/phase-in.

5.4.2 Outcome

An IRES contract phase-out plan that provides for an orderly and effective transition of products and services to the follow-on contractor(s) with no interruption or impact to mission.

CDRL C029: Program Phase-Out Plan

5.4.3 Desired Attributes

a. Products and services are transitioned from IRES to the follow-on contractor(s) with no interruption or impact to mission.

b. Task order continuity logs are maintained in a manner that minimizes learning curves.

c. The legacy of projects that transcend / extend over multiple task order performance periods is retained.

5.4.4Constraints
5.4.3.1Contract phase out activities to be accomplished during the last 3 months of IRES contract performance.
5.4.3.2Each task order will be formally transitioned to a follow-on task order (reference ¶ 5.3.2.3).
6.0Contract Deliverable Requirements List (CDRL)

The point of delivery for all CDRL products, except as noted in Exhibit C, is the MDA E-CaRT system. The Contractor shall deliver all such products by saving and profiling them in E-CaRT, with the appropriate notification of delivery letter transmitted electronically to the Government’s Data Management Office. Reference Exhibit C for specific CDRL delivery instructions.

6.1CDRL Identification
Task
CDRL
DID
Title
Description
5.1.1.1
C001
DI-MGMT-81861/T
TO 2000: Integrated Program Management Report
Contains data for measuring cost and schedule performance. The IPMR is structured around seven formats that contain the content and relationships required for the electronic submissions.
5.1.1.2
C002
DI-MGMT-80441/T
TO 2000: Interim Government Property Inventory Report
Itemizes contractor acquired property (quarterly) that will be entered into the MDA Accountable Property inventory.
5.1.1.3
C003
DI-MISC-80508B/T
TO 2000: Task Order Status Report, [month ending]
Provides significant accomplishments, issues, concerns, lessons learned, and risks associated with the task order.
5.2.2.4
C004
DI-MISC-80508B/T
Event Package: [Insert Event Name]
Event packages provide situational awareness of events participated in or conducted by the IRES contractor.
5.2.2.5
C005
DI-SESS-81785
Systems Engineering Master Plan (SEMP)
Defines the technical approach and proposed plan for the conduct, management, and control of the integrated activities performed under the contract.
5.2.2.7
C006
DI-SAFT-81563/T
Accident / Incident Report(s)
Provides information / situational awareness of accidents / incidents occurring at the MDIOC.
5.2.2.7
C007
DI-MISC-80508B/T
Chemical Inventory and Hazardous Material Usage Report
Identifies and provides the location, quantity and status (e.g., used, depleted, destroyed) of all chemicals and/or hazardous material in the inventory or acquired for use on Schriever AFB to ensure compliance with federal, state, and local regulations.
5.3.2.1
C008
DI-MGMT-80004/T
IRES Program Management Plan
Defines the contractor’s organization, assignment of functions, duties, and responsibilities, management procedures and policies, and reporting requirements for the conduct of contractually-imposed tasks, projects, or programs.
5.3.2.1
C009
DI-MGMT-81334D
IRES Contract Work Breakdown Structure (CBWS)
CWBS using the latest version of MIL-STD-881 as a guide.
5.3.2.1
C010
DI-MGMT-81468
IRES Contract Funds Status Report (CFSR)
Provides funding data about task orders for the purpose of: (a) updating and forecasting contract funds requirements, (b) planning and decision making on funding changes to contracts, (c) developing funds requirements and budget estimates in support of approved programs, (d) determining funds in excess of contract needs and available for de-obligation, and (e) obtaining rough estimates of termination costs.
5.3.2.1
C011
DI-FNCL-81566C
Enterprise-wide Contractor Manpower Reporting Application (eCMRA)
Identifies funding source, contracting vehicle, organization supported, mission and function performed, and labor hours and costs for contracted efforts providing services to the MDA. Required for prime and all subcontractors.
5.3.2.1
C012
DI-MISC-80508B/T
SB Subcontractor Report, IRES Contract
Provides actual achievements relative to the utilization goals in the Small Business Participation and Commitment Plan and the results of the Contractor’s efforts to achieve other Plan objectives.
5.3.2.1
C013
DI-MGMT-81861/T
IRES Integrated Program Management Report
The IPMR contains data for measuring cost and schedule performance. The IPMR is structured around seven formats that contain the content and relationships required for the electronic submissions.
5.3.2.1
C014
DI-MISC-80508B/T
IRES Program Status Report, [Quarter ending]
Compilation of program management reports prepared / delivered under individual task orders.
5.3.2.1
C015
DI-MGMT-81453A
IRES Data Accession List (DAL)
Provides a medium for identifying contractor internal data which has been generated by the contractor in compliance with the work effort described in the Statement of Work (SOW). The DAL is an index of the generated data that is made available upon request.
5.3.2.1
C016
DI-MISC-80508B/T
Cybersecurity Risk Management Plan
Cybersecurity Risk Management Plan that includes threat analysis, system exposure to threats, integration of Cybersecurity risk management with other systems engineering process areas, and Cybersecurity risk mitigation.
5.3.2.1
C017
DI-MISC-80508B/T
Cybersecurity Controls Statement(s) of Compliance
Statement of compliance that specify the contractor’s policies, procedures and standards for protecting CUI from unauthorized access from both internal and external sources.
5.3.2.1
C018
DI-MISC-80508B/T
[Enter Company Name, Report #]: Cyber Incident or Compromise Report(s)
This CDRL is required for all contractor and subcontractor cyber incidents and must be performed in accordance with the provision found in Para 6.4 of the Cloud Computing Security Requirements Guide (SRG) (version in effect at the time of contract award) and provisions defined in DFARS 204.73.
5.3.2.1
C019
DI-MISC-80508B/T
Cybersecurity Workforce Management Report
This CDRL reports the status of IRES contractors performing Cybersecurity functions in order to verify compliance with guidelines found in DOD 8570.01-M (specified in Chapters 3, 4, 5, 10, and 11).
5.3.2.2
C020
DI-QCIC-81794
Quality Assurance Program Plan
Defines the quality / mission assurance program and the methods, procedures, and controls employed for effective mission assurance.
5.3.2.2
C021
DI-MGMT-81808
IRES Risk Management Plan
Defines the process to monitor management, cost and schedule of the contract efforts relative to a system and equipment. This information will provide the government with risk data for all risks associated with the system/ equipment.
5.3.2.2
C022
DI-CMAN-80858B
IRES Configuration Management Plan
Defines the configuration management program and the methods, procedures, and controls used for effective configuration identification, change control, status accounting, and audits of the total configuration, including hardware, software and firmware.
5.3.2.2
C023
DI-MISC-80508B
Environmental Program Plan
Defines the procedures and process to ensure compliance with the federal state and local laws, regulations, and programs.
5.3.2.2
C024
DI-MISC-80508B
Mishap Prevention and Safety Plan
Provides the framework in which the MDIOC conducts its mission in a healthy and safe manner.
5.3.2.2
C025
DI-MISC-80508B/T
MDIOC Facility Evacuation Plan
Provides the procedures for a safe, orderly and thorough evacuation of the MDIOC workforce.
5.3.2.3
C026
DI-MISC-80508B
[Enter Task Order #]: Task Order Close-Out Report
Provides a summary of the activities / accomplishments of each task order.
5.3.2.3
C027
DI-MGMT-80441/T
[Enter Task Order #]: Final Government Property Inventory Report
Itemizes contractor acquired property (final report) that will be entered into the MDA Accountable Property inventory.
5.3.2.4
C028
DI-MISC-80508B/T
IRES Program Information Management System Documentation
Provides a description, user documentation and source code (if applicable) of the contractors’ program information management system employed to track CDRLs and DALs.
5.4.2
C029
DI-MISC-80508B/T
IRES Program Phase-Out Plan
Describe activities necessary to successfully and efficiently transition the IRES contract to the follow-on contract. Lessons learned during the IRES Transition Task Order should be addressed.

6.2 CDRL Tailoring

Reference Task Order 2000 Exhibit C (Enclosure 1).

6.3Milestones
Task
Activity
Date / Days After Contract (DAC)
5.1.1.3
Integrated Baseline Review
90 DAC
5.3.2.1
Program Reviews
Quarterly

Note: DAC = Days after task order period of performance start date

7.0 Government Furnished Equipment (GFE) / Government Furnished Information (GFI) In addition to the GFE / GFI identified in the IRES Contract SOO, paragraph 6.0, the following is applicable to this task order:

· RFP Attachment J-05 - GFP List

· MDA approved SW List 20151207 (Bidders’ Library)

8.0 Special Requirements

In addition to the Special Requirements identified in IRES Contract SOO, paragraph 7.0, the following are applicable to this task order:

· None

9.0 Applicable Directives / Regulations

In addition to the directives and regulations identified in RFP Attachment J-07, the following are applicable to this task order:

· CFR, Title 29, Subtitle B, Chapter XVII Part 1910.1200, Hazard Communication Program

· 50th Space wing Instruction 32-2001, Emergency Services

10.0 Contractor-developed PWS (CPWS)

The final, negotiated CPWS will be appended to this document.

Note: The CPWS will also serve as the initial or baseline Quality Assurance Surveillance Plan (QASP). The QASP will not be incorporated into this document; a change to the QASP after task order award does not constitute a change to the task order.

11.0 Contractor-proposed Service Summary Item Table

The contractor shall propose service summary items; the weight must total 45%. The final, negotiated SSIs accepted by the Government will be appended to the table in Section 4.0, Service Summary Items.

SSI #
Title
Description
Performance Threshold

UNACCEPABLE

Performance Threshold

ACCEPTABLE

Performance Threshold

OBJECTIVE

Weight
Surveillance Method

SSI 5

SSI n

TO 2000 Exhibit C

Sep 21, 2016 Page 15 image1.png image2.emf