GSA Public Buildings Service, Northwest/Arctic Region
TASK ORDER REQUEST FOR PROPOSAL (TORFP)
Project Name: FTA D-B Tenant Improvements 31 st Floor JFB
Solicitation Number: 47PL0120R0064
DATE: 10/05/2020
United States Department of Transportation Federal Transit Administration
Tenant Improvement 31st Floor Offices and associated spaces at the
Henry M. Jackson Federal Building 915 2nd Ave, Seattle, Washington
FTA Tenant Improvement Floor 31st JFB Solicitation Number: 47PL0120R0064
TASK ORDER SOLICITATION/REQUEST FOR PROPOSAL
1. TASK ORDER SOLICITATION INSTRUCTIONS
Project Name: FTA D-B Tenant Improvements 31st Floor JFB
Project Location: 915 2nd Ave, Seattle, Washington 98174 Note: There are public entrances to the building on 2nd Avenue and 4th Avenue.
2. Pre-proposal Conference: In order to make the process a little easier and be more prepared for the site visit, a pre-proposal Conference/Virtual Meeting will be held on Thursday 10/15/2020 at 11:00 a.m. Pacific Daylight Savings Time via Google Meet Id:
meet.google.com/eir-vknw-wou. All individuals that desiring to attend the virtual meeting or the site visit the next day are required to register for attendance via the following link https://forms.gle/HMUujbSTbmFn1ZFaA. All attendees must register.
The virtual meeting will be divided into three parts: Solicitation discussion, Technical discussion/project review, and questions and answers. Note: it is important for the same individuals that are attending the site also attend this teleconference as the project scope, specifications, and test fit drawings will be discussed in detail. We would like all parties to be thouroughly prepared for the site visit, so that time on site can be minimized.
3. Site Visit Date: A site visit is scheduled for the Friday, 10/16/2020 at 10:00 a.m. The site visit is not mandatory; however failure to participate will not alleviate the offeror of the responsibility to perform due diligence for understanding the requirements of this Task Order Request For Proposal or existing site conditions that will those that attend will be able to review.
See COVID-19 Preventative Measures regarding building access. Additional site visits may be requested (See Section 4.e. titled “Pre-Proposal Inquiries (PPIs), Questions, and Answers (Q&A)”.
3.a. Parking: Parking is not available on site due to the number of probable attendees. See Map and list below for known parking garages that may be able to accommodate your team for a nominal fee. GSA will not validate your parking or pay any costs related to site visits during the competition.
3.b. Group Sizes: Maximum group size per tour: Six (6) personnel for each Prime Contractor to include Sub-Contractor(s).
MATOC holders are requested to submit a list of attendees, including sub-consultants, and subcontractors that your firm intends to bring to the site visit to the GSA. Send the list of attendees to the GSA Project Team via the following link:
https://forms.gle/HMUujbSTbmFn1ZFaA no later than 09:00a.m. 10/16/2020. Ensure that you include the name, title, firm, email address, firm’s address, and telephone number that your attendees represent. If subcontractors or subconsultants are with multiple Prime Contractors, ensure that they include which ones that they will be providing subcontractor quotes/proposals or other offer.
FTA Tenant Improvement Floor 31st JFB Solicitation Number: 47PL0120R0064
3.c. COVID-19 Preventive Measures: The GSA has implemented additional safety precaution due to COVID-19 pandemic, for which individuals entering Federally owned or controlled facility. There are instructions posted at the building entrance that a required to be followed:
1. Face coverings are required to be worn at all times within Federal Buildings;
2. Individuals should not attend the walk if they have any of the following conditions:
a. Contact with individuals who were COVI-19 positive or presumed positive within the past 14 days,
b. Flu like symptoms which include Fever or chills, Cough, Shortness of breath or difficulty breathing, Fatigue, Muscle or body aches, Headache, New loss of taste or smell, Sore throat, Congestion or runny nose, Nausea or vomiting, or Diarrhea
Personal protective equipment like latex/nitrile gloves are optional and not required to be utilized during the site visit.
3.d. Site Visit Instructions: Attendees will meet with GSA representatives inside the 4th floor Entrance (2nd Ave) of JFB, which is located at 915 Second Ave, Seattle, Washington 98174. Ensure that you have proper identification for access to the building. Meet with GSA Project Manager (PM) Nenette Williams
(206) 225-5813. Arrive at least 15 minutes before the scheduled start time if possible to ensure that you are able to be on time.
3.e. Identification and Pictures: Be prepared to provide valid picture identification, which was issued from a United States Federal or State government entity (such as a state issued driver's license or identification card or U.S. passport.). Said identification is required to attend the site visit. Cameras and cell phones with cameras will be allowed. However, photo opportunities may be restricted.
Our tour guides will specify what areas and items can be photographed.
Cameras and cell phones content may be reviewed to ensure compliance.
3.d. Weapons Prohibited: Please ensure that no weapons, including knives, box cutters, or other sharp items that can be used weapons are brought to the site visit. Pens and pencils for writing are acceptable to bring. If you are unsure as to whether or not you should bring an item, ask at least 24 hours in advance. If you do not receive an answer before the site visit, don’t bring the item.
3.e. Business Cards: Business cards may be distributed during the site visit or may be sent directly to the Contracting Officer and COR as vCard at their email addresses included in this Solicitation. Please note:
Proposal preparation or cost associated with any pre-award site visits will not be reimbursed, as discussed in the in the base Western IDIQ MATOCs.
3.f. Pre-Proposal Inquiries (PPIs), Questions, and Answers (Q&A): it is noted that individuals often poise questions during site visits, with different individuals providing responses during the visit. It is critical that such situations be formal documented. As such, All questions and PPIs are required to be submitted in writing via the GSA survey link: https://forms.gle/KfuXhpXuiSUeNKS46. Formal responses and answers will be provided via Solicitation amendment. Questions and comments that may have been made during site are required to be followed-up with a formally submitted via the survey link above.
Note: Do not submit questions via email, use the survey link above.
FTA Tenant Improvement Floor 31st JFB Solicitation Number: 47PL0120R0064
4. Task Order Period of Performance: The period of performance will be Two Hundred Eighty Two (282) calendar days from Award to Substantial Completion and Thirty (30) calendar days from Substantial Completion to Final Completion, for a total period of performance of Three Hundred Twelve (312) calendar days.
5. Task Order Proposal Response Date and Time:
Proposals are required to be submitted electronically via email no later 11/09/2020 at 3:00 p.m. Pacific Standard Time, unless extended by amendment. See Section II. Paragraph 2. Receipt of Offers below for specific details keith.goodsell@gsa.gov and kimberlym.johnson@gsa.gov
6. GSA Project Team:
A. Task Order Contracting Officer/Specialist: Keith Goodsell /keith.goodsell@gsa.gov / (253)-253-7775 B. Project Manager: Nenette Williams/nenette.williams@gsa.gov / (206)-225-5813
Questions shall be submitted via survey link https://forms.gle/KfuXhpXuiSUeNKS46.
Attachments to questions can be uploaded via the electronic survey.
7. Task Order Solicitation and Contract:
A. This solicitation establishes the requirements for proposals submitted in response to the FTA Design- Build Tenant Improvement buildout on the 31st Floor at Jackson Federal Building (JFB) for the project as described in the attached Task Order (TO) contractual documents and incorporated Task Order Exhibits.
Proposals conforming to the TORFP will be evaluated in accordance with the Method of Award as established in this document. All terms and conditions in the WESTERN MATOC IDIQ MATOCs are hereby incorporated into this solicitation and any resultant Task Order award.
B. Neither the Solicitation nor any part of an Offerors proposal shall be part of the Task Order (TO) award except to the extent expressly incorporated in the Task Order Agreement by the Task Order Contracting Officer (TOCO) at award.
C. The Offerors proposal submitted in response to this Solicitation shall constitute a firm offer. No contract shall be formed unless and until the TOCO has countersigned the SF1442 submitted by an Offeror, and delivered to the Contractor a countersigned copy of the SF1442 together with the TO reflecting the agreed to prices.
D. Changes to the solicitation prior to the deadline for receipt of proposals will be executed via issuance of SF30 Amendment to the Solicitation. Amendments will be sequentially number beginning with the notation ‘A01’. Offerors shall acknowledge receipt of any amendment and provide confirmation upon submission of the offerors proposal on the SF1442.
8. Availability of Funds:
Issuance of this Solicitation does not warrant that funds are presently available for award of a task order.
Award of the task order shall be subject to the availability of appropriated funds, and the Government shall incur no obligation under this Solicitation in advance of such time as funds are made available to the TOCO for the purpose of task order award.
9. Project Delivery Method:
____Non-Complex Construction (no formal design documents).
____Design-Bid-Build ____Bridging Design-Build (maximum CD of 30%) _X_Design-Build
FTA Tenant Improvement Floor 31st JFB Solicitation Number: 47PL0120R0064
10. TO Solicitation Documents:
A. SF1442, Solicitation, Offer, and Award [Construction, Alteration and Repair] 47PL0120R0064
B. TO RFP Solicitation 47PL0120R0064 and Task Order Agreement
C. Construction Wage Determination: WA20200011 10/02/2020, Mod 11, King County, Building.
(Note: the Wage Determination will be automatically revised to the latest Wage Determination at the day of award. Offerors are required to ensure that they monitor changes in the wage determination at beta.sam.gov.
D. Project Documents:
D.1. Statement of Work, FTA TI – Office Build-Out, date 09/02/2020
Attachment A - Personnel Security Access
Attachment B - Construction/Renovation Green Building Materials Policy
Attachment C - Construction/Renovation Green Building Materials Policy
Attachment D – Reserved (Not provided)
Attachment E - GSA Fire and Life Safety Design, Installation and Testing Policy
Exhibit 1 - JFB Building Information
Exhibit 2 - JFB Asbestos Re-inspection Report 2013
Exhibit 3 - FTA Final Test Fit
Exhibit 4 – 31st Floor Current Lay-out Plan
Exhibit 5 - FTA Final Test Fit Presentation
Exhibit 6 - IT SOW - 08-20-20 - FTA TI – Office Build-Out
Exhibit 7 - 08-25-20 Meeting Minutes
D.2. Addendum 1 to the Statement of Work, FTA TI – Office Build-Out, date 09/23/2020
Exhibit 6 - IT SOW - 08-20-20 - FTA TI – Office Build-Out
Exhibit 8 – JFB Floor 31 Supplemental Pre Renovation Asbestos Survey Report 091020
II. TO RFP SUBMITTAL REQUIREMENTS
1. Estimated task order construction value: Pursuant to FAR 36.204: the magnitude of construction is:
____between $25,000 and $100,000.
____between $100,000 and $250,000.
____between $250,000 and $500,000.
_X_ between $500,000 and $1,000,000. For Construction only ___ between $1,000,000 and $5,000,000.
The magnitude for the overall project, inclusive of all work, is between $500,000.00 and $ 1,300,000.00.
2. Receipt of offers:
A. Task Order Proposals are to be submitted by email to the Task Order Contracting Officer, Keith Goodsell at keith.goodsell@gsa.gov and Kimberly Johnson, Supervisory Contracting Officer at kimberlym.johnson@gsa.gov . Offers will be considered received as of the date and time the email is in the inbox of the recipient. The maximum email inbound attachment for GSA is 25MB per single email. Multiple emails are allowed. Ensure to include the following information in the Subject Line, “Proposal 47PL0120R0064” (Insert Company
FTA Tenant Improvement Floor 31st JFB Solicitation Number: 47PL0120R0064 abbreviated name) “Email” (example: Proposal 47PL0120R0064, XRV Contractors, Email 1 of 3).
GSA bears no responsibility for the successful receipt of such emails and the contractor is encouraged to submit offers early with a read receipt to confirm receipt prior to the due date.
Original executed bid bonds, signed SF 1442s and Cover letters are to be mailed so as to be received by 11/11/2020 to the address listed below.
United States General Services Administration Public Buildings Service, Northwest/Arctic Region
Acquisition Management Division, 400 15th Street SW, Auburn, WA 98001-6599 Attention: Keith Goodsell and Kimberly Johnson
3. Proposals: Offerors are responsible for reading and understanding the entire Task Order solicitation and base contract requirements. Only complete proposals will be guaranteed to be evaluated. A ‘complete’ proposal means that all the data and information as required by the solicitation is included in the proposal package. Failure to submit a complete proposal may eliminate an Offeror from further consideration. If the Offeror communicates in its proposal any qualifications, exclusions, or conditions which are material changes to the terms of the Task Order Solicitation and associated documents, the Contracting Officer may reject the proposal as not being in compliance with Solicitation terms and conditions.
4. Proposal Instructions: Submit the documents below by email, as separate organized files as shown below, no later than the date and time due as established by this TO RFP as noted on the SF1442. Additional information may be submitted as it relates to the project.
Volume/ Section
Volume Title Page Limit
I The Offer No Limit A1 Cover Letter 3 Pages
A2 List of ALL Sub-Contractors and subconsultants to include DUNS number
No Limit
A3 Completed/signed SF 1442 with Acknowledgement of All Amendments (if any) and completed Continuation Page(s) with CLIN Structure.
A4 Original Proposal Guarantee and Surety Attorney-in-fact Power of Attorney/delegation letter
No Limit
II Technical Proposal No Limit B1 FACTOR 1 - Project Management and Planning No Limit B2 FACTOR 2 - Schedule and Phasing Plan No Limit B3 FACTOR 3 - Experience on Comparable Projects No Limit
III Price Proposal C1 See Volume I Section A3 No Limit
C2 Price breakdowns for all CLINs and SLINs No Limit
C3 Subconsultant/Subcontractor quotes/proposals with breakdown No Limit
C4 Written Evidence/Documentation of Subcontractor Competition No Limit
FTA Tenant Improvement Floor 31st JFB Solicitation Number: 47PL0120R0064
Volume I – the Offer: Binding Offer submitted by the Offeror to the Government that may be accepted or rejected by the Government. The Offer shall include the following:
A1. Cover Letter –The cover letter shall include Solicitation number and date Address to letter to the Task Order Contracting Officer Name, address, telephone and facsimile numbers, and e-mail addresses of the offeror A statement specifying the extent of agreement with all terms, conditions, and provisions included in the solicitation and agreement to furnish all items upon which prices are offered at the price set opposite each item Amendments acknowledged (if not acknowledged in the SF 1442 block 19) Names, titles, phone numbers, facsimile numbers, and e-mail addresses of persons authorized to negotiate on the offeror’s behalf with the Government in connection with this solicitation Name, title, and signature of person authorized to sign the proposal Reminder both emailed and hard copy are required to be submitted due to signature requirements
A2. List of ALL Subcontractors and subconsultants –The list shall include The Legal Name of the Subconsultant/Subcontractor firm The Data Universal Numbering System (DUNS) number of the Subconsultant/Subcontractor firm The Legal Name and DUNS shall be provided for all Subcontractors and Subconsultant firms at all tiers.
A3. Completed/signed SF 1442 and continuation pages The Offeror shall complete blocks 14, 15, 16, 17, 18, 19, and 20, as well as the Unit price and Amount for each Priced CLIN and SLIN of the SF 1442 Continuation Pages. Block 17 shall contain the Total Price, inclusive of all CLINs and SLINs In the case where negotiations are conducted after receipt and evaluation of proposals, the Offeror shall complete blocks 30a, 30b, and 30c.
A4. Original Proposal Guarantee and Surety Attorney-in-fact Power of Attorney/ delegation letter The Offeror shall complete blocks 14, 15, 16, 17, 18, 19, and 20, as well as the Unit price and Amount for each Priced CLIN and SLIN of the SF 1442 Continuation Pages. Block 17 shall contain the Total Price, inclusive of all CLINs and SLINs In the case where negotiations are conducted after receipt and evaluation of proposals, the Offeror shall complete blocks 30a, 30b, and 30c.
Volume II– Technical Proposal: Responses to Evaluation Criteria and assertions submitted by the Offeror to the Government that will be evaluated in accordance with the Solicitation, as amended.
The Government may choose to accept or question any part of the Technical Proposal submitted for accuracy, feasibility, validity. As such, please ensure to review your proposal prior to submission.
Note: The Technical Proposal (Volume II) shall not make reference to price data. The technical approach will be evaluated strictly on technical acceptability.
As the Technical Proposal will describe the how, when, and with whom that your organization will be performing the requirements of the task order with, as well as your experience, it must be specific and
FTA Tenant Improvement Floor 31st JFB Solicitation Number: 47PL0120R0064 complete in every detail. Just providing a positive statement to the effect that you will accomplish all requirements per the statement of work (SOW) is not acceptable. The proposal shall not merely offer to perform work in accordance with the SOW, but shall outline the actual methods proposed as specifically as possible. It is the Offeror’s responsibility to ensure the completeness of the technical Proposal; hence, the Government technical review team will evaluate on the basis of the information provided in the technical approach. The Government shall not assume that an Offeror possesses any capability unless specified in the proposal. All requirements specified in the Task Order Agreement, SOW, addendums, attachments, exhibits, and references are mandatory. By submission of a proposal, the Offeror represents that they will perform all requirements specified in the ask Order Agreement, SOW, addendums, attachments, exhibits, and references. Evaluation Factors are located in below and will be used to evaluate offers proposal based on the written information submitted by the Offeror. The Technical Proposal shall address the following:
B1. FACTOR 1 - Project Management and Planning The Offeror shall ensure that its proposal complies with both the Submittal Requirements and Standard of Evaluation for Factor 1 and provide a detail response to each of the items identified in Evaluation Criteria for Factor 1.
B2. FACTOR 2 - Schedule and Phasing Plan The Offeror shall ensure that its proposal complies with both the Submittal Requirements and Standard of Evaluation for Factor 2 and provide a detail response to each of the items identified in Evaluation Criteria for Factor 2. Include Schedule in both .mpp and .pdf formats as shown in the Evaluation Criteria.
FACTOR 3 - Experience on Comparable Projects The Offeror shall ensure that its proposal complies with both the Submittal Requirements and Standard of Evaluation for Factor 3 and provide a detail response to each of the items identified in Evaluation Criteria for Factor 3.
Text size and formatting. Pages shall be single-spaced. Except for the reproduced sections of the solicitation document, the text size shall be no less than font size 10. Use at least one inch margins on all four sides of the page. Pages shall be numbered sequentially by volume.
Volume III, Factor 4 - Price. All CLIN and SLIN pricing information shall be addressed in Volume I Volume III only. All dollar amounts provided in response to these instructions shall be stated in United States (U.S.) currency.
C1. Completed/signed SF 1442 with Acknowledgement of All Amendments (if any) and completed Continuation Page(s) with CLIN Structure.
The Offeror shall ensure that its proposal complies with both the Submittal Requirements and Standard of Evaluation for Factor 4 and provide a detail response to each of the items identified in Evaluation Criteria for Factor 4, including:
Price breakdowns for all CLINs and SLINs by CSI MasterFormat at Level III Subconsultant/Subcontractor quotes/proposals with detailed breakdowns Written Evidence/Documentation of Subcontractor Competition: Copies of the Offeror’s summary analysis of subcontractor quotes/proposal received. Copies of correspondence soliciting and contacted, Subcontractor responses
II. Task Order Basis of Award
The Government will evaluate each proposal as a whole on the basis of price and technical merit and award to the offeror whose proposal represents the best value to the Government using a Best Value, Trade-Off methodology. Best Value, Trade-Off allows the government to award to the responsible offeror whose offer conforming to the solicitation is technically acceptable with lowest reasonable price.
This approach allows the Government to award to the responsible offeror, whose offer conforms to the solicitation as determined by the Task Order Contracting Officer, and is the best value to the
FTA Tenant Improvement Floor 31st JFB Solicitation Number: 47PL0120R0064
Government (not necessarily the highest rated or lowest prided offer). All proposals that conformed to the Solicitation requirements, and that were evaluated with ratings of “Satisfactory” or above will be ranked against the following factors for this Task Order award:
FACTOR 1 Project Management and Planning FACTOR 2 Schedule and Phasing Plan FACTOR 3 Experience on Comparable Projects
FACTOR 4 Price
Factor 1 is more important to Factor 2, Factor 1 is more important than Factor 3, Factor 2 is more important than Factor 3, Factor 2 and Factor 3 combined is approximately equal to Factor 1. Factor 1, when combined with Factor 2 and Factor 3 is significantly more important to Factor 4 Price.
NOTE: The importance of price will increase if the non-price (technical) factors of two or more proposals are considered essentially equal in terms of quality (e.g. a tie for the highest rated quote) or if the price of one of those proposal is so high or so low as to significantly diminish the value of a proposal’s technical superiority to the Government.
The Government reserves the right to award on initial offers without discussions. Therefore, Offerors are encouraged to submit their most favorable proposal packages. Offerors are cautioned that proposals containing qualifications, conditions, or expressing unilateral interpretations of the RFP/Task order requirements may be rejected by the Task Order Contracting Officer. In the case where most if not all proposals are rated at “Marginal” or “Unsatisfactory” or there is adverse past performance information, the Government may choose to enter into communications/clarifications/negotiations to address said information. In the case where it is determined that negotiations will be held, notification will be provided to Offerors individually. The Government reserves the right to reject any or all proposals if such action is deemed in the Government’s best interest. The Government may accept minor irregularities in the proposals received if the irregularities are determined to be insignificant or inconsequential to the overall evaluation.
III. Technical Evaluation
1. Definitions: The following definitions shall be used in the evaluation of proposals submitted in response to this Solicitation, as amended.
Word/Phrase Definition
Deficiency A material failure of a proposal to meet a Government requirement or a combination of significant weaknesses in a proposal that increases the risk of unsuccessful contract performance to an unacceptable level.
Weakness A flaw in the proposal that increases the risk of unsuccessful contract performance.
Significant Weakness
A flaw in the proposal that appreciably increases the risk of unsuccessful contract performance.
Strength Means an aspect of a proposal that appreciably decreases the risk of unsuccessful contract performance or a favorable attribute of the proposal that provides benefit and/or efficiency over the minimum requirements of the solicitation that represents a significant benefit to the Government.
Uncertainty Any aspect of the proposal for which the intent of the Offeror is unclear because there may be more than one way to interpret the offer or because inconsistencies in the offer indicate that there may be an error, omission, or mistake.
Deviation Proposal implies or specifically offers a deviation below the specified criteria. The Offeror may or may not have called the deviation to the Government’s attention. A deviation is a deficiency. The proposal must conform to the solicitation requirements for award.
FTA Tenant Improvement Floor 31st JFB Solicitation Number: 47PL0120R0064
2. Technical Evaluation Factors and Criteria
FACTOR 1: Project Management and Planning
Description: This factor considers the extent that the Offeror understands the project requirements as demonstrated in its plan to staff, manage and coordinate this design-build project with the right people to make the project succeed, it’s review of current market conditions for necessary services, materials, equipment, and other needed items, and it’s assessment of the likely risks and different scenarios about what could go wrong with the project and what contingency actions are included to ensure success.
Submittal Requirement:
1. Project Management Plan: The Offeror shall submit a detailed Project Management Plan specific to this project that includes a staffing plan with organizational chart, showing the lines of authority and communication, for the various types of work to be performed from the start through the finish of the project.
a. Provide a short biographical profile (bio) of the Project Manager, Lead Architect, Lead Engineer, Superintendent, and Quality Assurance/Safety Manager of ten sentences or less for each individual. The bios should include key information of professional licensing, experience, and leadership that will show that these individuals are the right fit for this project.
b. Provide a narrative with the rationale as to why various subcontractors and subconsultants selected for this project by the Offeror are believed to be the right firms and people that will make the project succeed.
c. Clearly identify all subcontractor and subconsultant tiers projected for the project, the lines of communication/control, and how the offeror will minimize the number of tiers.
d. If more than a two tiers of subcontractors or subconsultants will be utilized, include an explanation as to why the third or lower tier subcontractor and subconsultant is not directly under the e prime contractor or first tier subcontractors or subconsultants.
e. Provide a narrative that provides the technical approach that will be utilized to ensure that this project is completed on time, on budget, and with the high quality and customer satisfaction.
Discuss interaction and communications with the Key stakeholder, such as the GSA project team, the Client Agency, the GSA Contracted Tenant Outfitting Design Services Contractor, and GSA contracted Construction Management assistance firm.
2. Market Conditions Assessment: The Offeror shall submit a narrative a review of current market conditions and the projected impact on this project, especially in regards to necessary services, materials, equipment, and other needed items. Ensure to address the following items in the narrative:
a. Long Lead Items: Clearly identify what materials, equipment, and other items that have a long lead time, the projected time for them, and if authorization will be required from the Task Order Contracting Officer will be necessary for early procurement during the Design phase of the project.
b. Subcontractor Availability: Clearly identify market conditions regarding the availability of the various subcontractors and subconsultants that are needed for this project. State whether the market had sufficient quantities of firms available and willingness to participate in
FTA Tenant Improvement Floor 31st JFB Solicitation Number: 47PL0120R0064 subcontractor competition for this project.
3. Risk Assessment: The Offeror shall provide an assessment of the likely risks and different scenarios about what could go wrong with the plan and what contingency actions are included to ensure success.
a. Risk Analysis Chart: provide a risk analysis chart for the project that (1) identifies likely risks and scenarios, (2) qualifies the risks and its impact to the project if it does occur and the likelihood of the risk occurring, (3) the watch list risk triggers to be monitored, and (4) the contingency actions/strategies to be taken if the risk if it does occur. Include a succinct narrative with the chart to addresses any or all the items that need further application
Standard of Evaluation: Evaluation of this factor will be an objective assessment of the quality of Project Management Plan, Market Conditions Assessment, and Risk Assessment submitted specifically for this project. Failure to meet all Submittal Requirements for this Factor will result in the proposal not meeting the Standard of Evaluation for this Factor. If the all the Submittal Requirements are met, then the Standard of Evaluation is met when the proposal demonstrates that the Offeror understands the project requirements and has:
a. presented a sound and realistic Project Management Plan that is achievable, with evidence that it has put together a project team with the right people, subcontractors/subconsultants, disciplines and trades in order for the project to succeed;
b. presented a reasonable assessment of current market conditions in order to properly staff, equip, obtain all necessary materials and services needed for the project; and
c. presented a reasonable risk assessment of the likely risks and different scenarios about what could go wrong with the plan and what contingency actions it has included to ensure project success.
Project Management and Planning will be rated using the ratings in Table A-1:
Table A-1: Factor 1 Ratings and Definitions Rating Definition Exceptional The Proposal clearly exceeds the minimum requirements of the solicitation for this
Factor required for ratings of Satisfactory and Above Average and the offeror has addressed the required items and Submittal Requirements for this Factor. The Proposal contains multiple strengths or significant strengths and no deficiencies.
The overall quality of the Proposal in relation to the evaluation criteria is superior and there is a high probability of success.
Above Average The Proposal clearly exceeds the minimum requirements of the solicitation for this Factor and those required items for a rating of Satisfactory. The proposal has addressed the required items and Submittal Requirements. The Proposal is comprehensive and provides greater detail to the Reader than those required items for a rating of Satisfactory. The proposal contains one or more strengths and no deficiencies. The overall quality of the qualifications/ proposal in relation to the evaluation criteria is good and there is a high probability of success.
Satisfactory The Proposal clearly meets the minimum requirements of the solicitation for this Factor and the offeror has addressed the required items. The Proposal is realistic and demonstrates the Offeror’s ability to satisfactorily plan, staff and assess current Market Conditions and Risks that will lead to the successful accomplishment of the project. The proposal may contain one or more weaknesses and no deficiencies.
The overall quality of the proposal in relation to the evaluation criteria is good and there is a reasonable probability of success.
FTA Tenant Improvement Floor 31st JFB Solicitation Number: 47PL0120R0064
Marginal The proposal meets most the minimum requirements of the solicitation for this Factor and the offeror has addressed the required items. The proposal contains one or more significant weaknesses, but no deficiencies. The overall quality of the Proposal in relation to the evaluation criteria is fair and there is a limited probability of success. Several minor revisions to the proposal may be necessary.
Unsatisfactory The proposal does not clearly meet the minimum requirements of the solicitation for this Factor and the offeror did not address the required items. The proposal contains one or more deficiencies or a combination of significant weaknesses in the proposal that increases the risk of unsuccessful contract performance to an unacceptable level.
FACTOR 2: Schedule and Schedule Narrative
Description: This factor considers the extent that the Offeror technically understands the project requirements and has presented a realistic, attainable schedule containing all key work elements necessary to include a phasing plan to ensure successfully completion of the project within the stated performance period.
Submittal Requirement: The Offeror shall submit a comprehensive and fully developed Critical Path Method (CPM) project schedule/Phasing Plan (no page limit) and associated Schedule Narrative (no page limit)
1. Preliminary Schedule: The proposed schedule (in form of a Gantt chart for the .pdf version) shall include all milestones and phase on which the Contractor contemplates starting and completing with the several salient features of the work. The schedule shall have a minimum of 35 activities, including all anticipated critical path activities, including, but not limited to, award, bonds/insurance submission, bonds/insurance acceptance, Security clearance form submission, Security Adjudications, Kickoff, and activities needed for NTP through the different phase closeout identified in the SOW and related attachments in order to receive a “Satisfactory” or higher rating.
a. In the case where milestone dates are dependent upon approval of an activity and individual notice-to-proceeds for specific areas, the Offeror shall ensure that such milestones are annotated in the narrative that they are dependent upon specific approval from the GSA and call out action required on the part of the FTA or regulatory agency.
b. The schedule shall be of suitable scale to indicate appropriately the percentage of work scheduled for completion by any given date during the period. The Offeror shall identify and describe the critical path schedule and coordination for this project to meet the design, abatement, demolition, construction, inspection/testing and Closeout phase requirements including, but not limited to, key initial submittals, field survey, charrettes/design and other meeting, key submittals and reviews, Notices to proceed, abatement and demolition activities, ordering of materials, construction, inspections (internal and external), key testing, substantial completion, final completion/closeout, and other anticipated work elements which clearly defines the Offeror’s understanding of the project and ability to meet the project required delivery date.
c. Ensure that the schedule network logic shall be linked (e.g. project milestones and activities, etc.), and the logic shall show the general management approach for constructing, performing testing, and any associated work related to the Project.
d. Float time between activities should be calculated and identified.
FTA Tenant Improvement Floor 31st JFB Solicitation Number: 47PL0120R0064
e. The Critical Path shall be clearly identified. The schedule shall be a fully developed master project schedule (Gantt with Critical Path Method) in Microsoft Project (version10 (.mpp)), as well as in Portable Document Format (.pdf) that will allow the Government to evaluate activity relationships.
2. Project Schedule Narrative: Offerors shall provide a Preliminary Project Schedule narrative that both correlates with the preliminary project schedule submitted and that discusses the various milestones and important activities and challenges associated with the project. Offerors should include discussions of how the schedule for the project will be met while, at the same time, managing any changes that may occur. The Preliminary Project Schedule narrative submitted shall be one (1) or more pages and be comprehensive enough to leave no doubt that the Offeror is fully aware of the requirements of the project and has planned out a sound and fully developed Critical Path Method (CPM) project schedule in the form noted above under the Submittal Requirements for the Preliminary Schedule.
Preliminary Schedule and Schedule Narrative submitted specifically for this project. Failure to meet all Submittal Requirements for this Factor will result in the proposal not meeting the Standard of Evaluation for this Factor. If the all the Submittal Requirements are met, then the Standard of Evaluation is met when the proposal demonstrates that the Offeror understands the project requirements and has:
a. presented a well thought out, sound and realistic Preliminary Schedule that is achievable, with evidence adequate planning for proper phasing of the project, that includes evidence of review and compliance with Base Contract, Task Order Agreement, Statement of Work, P100, and other requirements; and
b. presented a Schedule Narrative that correlates with the Preliminary Schedule, with amplification and discuss of the projects phases, milestone events, important activities and tasks required to start and complete the project.
The Schedule and Phasing Plan: will be rated using the ratings in Table A-2:
Table A-2: Factor 2 Ratings and Definitions Rating Definition Exceptional The Preliminary Schedule and Schedule Narrative clearly exceeds the minimum requirements of the solicitation for this Factor required for ratings of Satisfactory and Above Average and the offeror has addressed the required items and Submittal Requirements for this Factor. The schedule provides a clear savings in time to the Government and is still realistic. The Schedule narrative is comprehensive and provides greater detail to the Reader in the Offeror’s approach in showing the schedule is realistic and provides time savings.
Proposal contains multiple strengths or significant strengths and no deficiencies. The overall quality of the Proposal in relation to the evaluation criteria is superior and there is a high probability of success.
Above Average The Preliminary Schedule and Schedule Narrative clearly exceeds the minimum requirements of the solicitation for this Factor and those required items for a rating of Satisfactory, with a more details including milestones, critical path, and work breakdown tasks that may provide schedule savings due to activity planning. The proposal has addressed the required items and Submittal Requirements. The Schedule and associated narrative is comprehensive and provides greater detail to the Reader than those required items for a rating of Satisfactory. The proposal contains one or more strengths and no deficiencies. The overall quality of the qualifications/ proposal in relation to the evaluation criteria is good and there is a high probability of success.
Satisfactory The Preliminary Schedule and Schedule Narrative clearly meet the minimum requirements of the solicitation for this Factor and the offeror has addressed the required items. The Preliminary Schedule and Schedule Narrative are realistic and demonstrate the Offeror’s ability to satisfactorily plan, manage, and coordinate all work activities for the successful
FTA Tenant Improvement Floor 31st JFB Solicitation Number: 47PL0120R0064 accomplishment of the project within the stated performance period and provide sufficient coordination between stakeholders to minimize interferences and delays. The proposal may contain one or more weaknesses and no deficiencies. The overall quality of the proposal in relation to the evaluation criteria is good and there is a reasonable probability of success.
Marginal The proposal meets most the minimum requirements of the solicitation for this Factor and the offeror has addressed the required items. The proposal contains one or more significant weaknesses, but no deficiencies. The overall quality of the Proposal in relation to the evaluation criteria is fair and there is a limited probability of success. Several minor revisions to the proposal may be necessary.
Unsatisfactory The proposal does not clearly meet the minimum requirements of the solicitation for this Factor and the offeror did not address the required items. The proposal contains one or more deficiencies or a combination of significant weaknesses in the proposal that increases the risk of unsuccessful contract performance to an unacceptable level.
FACTOR 3: Experience on Comparable Projects
Description: This factor considers the extent of the Offeror’s relevant experience for the several work elements necessary to ensure successfully completion of the project, from design through construction and closeout.
Submittal Requirements:
The offeror shall submit a minimum of two, with a maximum of four, project examples demonstrating relevant experience. “Relevant” is defined as projects similar to the project described in this RFP in scope, magnitude and complexity and have a logical connection with the requirements of this RFP.
Examples of relevant experience include similar construction projects in office buildings.
Examples shall include Offeror’s ability to effectively coordinate A-E disciplines, Construction trades, and the ability to complete projects within the approved schedule, and critical phasing of work.
Examples of relevant experience include the Prime Contractor leading similar design-build projects in occupied Federal Office spaces, in Federal leased spaces/facilities, Federal owned buildings or Federal leased or owned Courthouses... Narrative should demonstrate offerors’ ability to ensure delivery of quality product and service; effectively control costs, manage contract changes; complete projects within the approved schedule; and management of resources/subcontractors.
Offerors shall submit a current Point of Contact (POC) for each project. The POC information shall include the name, phone number, and email address for each project submitted. The Government reserves the right to contact the point of contact provided by the offeror to verify the offeror’s experience on comparable projects. All projects submitted must be at least 75% complete or must have been completed within the last three (3) years from the date proposals are due (for this RFP).
a. Include Narrative summaries of the submitted projects that demonstrate the Offeror’s capabilities, technical expertise, and experience managing complex projects with reference to considerations of timeliness and technical success.
b. Include for each project how the project relates to this Solicitation project as well as how the project pertains to the noted area of experience. Also identify whether your firm was the prime or subcontractor for the project listed. If experience is based upon the experience of the PM, Superintendent or trades personnel, ensure to identify those individuals and their relevant experience.
c. For each project presented in relation to this factor, the Offeror shall explain how the characteristics of the project relate to the characteristics of this project. The similarity to this project is more important than the quantity of projects presented. Ensure that valid information is provided for verification purposes for each project presented. Also the Offeror
FTA Tenant Improvement Floor 31st JFB Solicitation Number: 47PL0120R0064 shall submit the following data/information for each project submitted:
1). Project Title 2). Project Owner and contact information (name, telephone number, e-mail). 3). Location 4). Description including Gross Square Footage, Construction Cost and similar scope elements that demonstrate equal or greater overall project complexity associated with them (especially relevant shall include tenant improvement project(s).
5). Contract Number, Task Order Number (if applicable) and Award Date 6). Contract Type and Contractor's Responsibilities (Scope of Work) (if individuals, list names and relevant responsibilities) 7). Date of Substantial Completion 8). Date of Final Completion 9). Contract or Task Order Value at Award
10). Contract or Task Order Value at Completion 11). Original Schedule Completion Time at Contract Award (Calendar Days) 12). Actual Completion Time (Calendar Days) 13). Number of Change Orders 14). Classification (reason) of Changes Orders (Owner Instituted, Design Errors & Omissions, unforeseen site conditions, etc.)
Relative experience submitted specifically for this project. Failure to meet all Submittal Requirements for this Factor will result in the proposal not meeting the Standard of Evaluation for this Factor. If the all the Submittal Requirements are met, then the Standard of Evaluation is met when the Offeror provides evidence of two (2) or more successful recent and relevant design-build tenant improvement projects where full design and build-out was required using multiple A-E disciplines and multiple-trade (i.e. at least five or more of the trades needed for this project).
Higher ratings may be given for experience of the workforce that will be included as part of the project (PM, Superintendent, contractor/subcontractor workforce) for the following:
Relevant experience with tenant improvement design-build or construction projects with the GSA may be considered as a Strength.
Relevant experience with office space tenant improvement in the Jackson Federal Building within the last10 years may be considered as a Significant Strength.
The Schedule and Phasing Plan: will be rated using the ratings in Table A-2:
Table A-3: Factor 3 Ratings and Definitions Rating Definition Exceptional The Proposal clearly exceeds the minimum requirements of the solicitation for this
Factor required for ratings of Satisfactory and Above Average and the offeror has addressed the required items and Submittal Requirements for this Factor. Proposal contains multiple strengths or significant strengths and no deficiencies. The overall quality of the Proposal in relation to the evaluation criteria is superior and there is a high probability of success.
Above Average The Proposal clearly exceeds the minimum requirements of the solicitation for this Factor and those required items for a rating of Satisfactory. The proposal has addressed the required items and Submittal Requirements. The proposal contains one or more strengths and no deficiencies. The overall quality of the qualifications/ proposal in relation to the evaluation criteria is good and there is a high probability of success.
FTA Tenant Improvement Floor 31st JFB Solicitation Number: 47PL0120R0064
Satisfactory The proposal clearly meets the minimum requirements of the solicitation for this Factor and the offeror has addressed the required items. The proposal may contain one or more weaknesses and no deficiencies. The overall quality of the proposal in relation to the evaluation criteria is good and there is a reasonable probability of success.
Marginal The proposal meets most the minimum requirements of the solicitation for this Factor and the offeror has addressed the required items. The proposal contains one or more significant weaknesses, but no deficiencies. The overall quality of the Proposal in relation to the evaluation criteria is fair and there is a limited probability of success. Several minor revisions to the proposal may be necessary.
Unsatisfactory The proposal does not clearly meet the minimum requirements of the solicitation for this Factor and the offeror did not address the required items. The proposal contains one or more deficiencies or a combination of significant weaknesses in the proposal that increases the risk of unsuccessful contract performance to an unacceptable level.
III. Price Evaluation
FACTOR 4: Price Reasonableness: Price will not be rated. Submit pricing for all Contract Line Item Numbers (CLINs). Provide total pricing for the entire offer. Offeror must submit detailed pricing to include detailed sub-contractor pricing.
Price will be evaluated using various price analysis techniques and the following:
The proposed prices will be evaluated for reasonableness. Price reasonableness determines whether an Offeror’s price is too high or too low. Price will also be checked for appearance of unbalanced line item pricing. Analysis of price proposals will be performed using one or more of the techniques defined in FAR 15.404 in order to determine price reasonableness. Normally, price reasonableness is established through adequate price competition, but may also be determined through price analysis techniques as described in FAR 15.404-1. Analysis of pricing for the individual CLINs and SLINs will be compared to the description of what is be included by the Offeror for the work matches the requirements of the Solicitation and associated attachments, exhibits, and references.
Total Price: The total price is the sum of the prices for all the Contract Line Items (CLINs) of this solicitation (Total Price equals CLIN 0001 plus CLIN 0002 plus CLIN 0003 plus CLIN 0004 plus CLIN 0005.
CLIN 0004 equals the sum of…