Attach_1_Specifications_OLYM_PMIS_306966-307067_Signed_100__Final.pdf

PDF 3 MB Posted

Attached to
Olympic National Park REHAB HURRICANE RIDGE WATER
Solicitation number
140P8326R0002
Issued by

About this file

This document is a comprehensive construction specification manual for the rehabilitation of the Hurricane Ridge Water System at Olympic National Park in Washington State. The project encompasses replacement of the water distribution piping system (both east and west of Water Valve Box #2), rehabilitation of a 100,000-gallon dual-chamber concrete water storage reservoir through structural inspection, sandblasting, interior/exterior recoating, and pipe penetration replacement, installation of new well pump control systems with pressure transmitters and reservoir float switches, provision of temporary water service during construction, and optional demolition of obsolete surface water infrastructure (Option A) or installation of remote monitoring capabilities (Option B). The specification manual includes Division 1 general requirements covering project management, quality assurance, safety protocols, environmental protection measures including archaeological monitoring and erosion control, waste management procedures requiring 50% diversion from landfills, and Division 2-48 technical specifications detailing materials and execution for concrete work, plumbing, electrical systems (including control panels with panel meters for monitoring chlorine tank scale weight, well pump flow, and reservoir level), water distribution piping (HDPE DR11 and ductile iron with mechanically restrained joints), valve installations, disinfection procedures compliant with AWWA C651 and C652 standards, earthwork including trenching and backfill with 95% compaction requirements, and asphalt paving restoration. Critical execution requirements include notification to the Contracting Officer 48 hours before excavation, maintenance of temporary water service through portable systems, pressure testing of all piping at 225-235 psi, bacteriological testing confirming NSF 61 compliance for potable water contact surfaces, compliance with NPS regulations regarding archaeological resources and invasive species prevention, and coordination with existing systems operating throughout construction. The project targets a May 5, 2025 start date with work generally restricted to 7 a.m. to 5:30 p.m. Monday through Friday, with specific seasonal constraints for dam demolition work (August 1 through Labor Day) and requirements for native vegetation restoration including saturation watering of subalpine meadow replantings through October 1, 2025.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OLYMPIC NATIONAL PARK

REHABILITATE HURRICANE RIDGE WATER

SYSTEM

Contract No. 140P8519D0002

Task Order No. 140P8522F0113

OLYM – PMIS No. 306966 & 307067

100% FINAL SET

CONSTRUCTION SPECIFICATIONS

NATIONAL PARK SERVICE

PACIFIC WEST REGION

December 2024

VOLUME 1 OF 2

OLYM - 306966 & 307067 TABLE OF CONTENTS - 1

DIVISION 1

CONSTRUCTION SPECIFICATIONS

OLYM – 306966 & 307067 TABLE OF CONTENTS - 2

TABLE OF CONTENTS

DIVISION, SECTION & PARAGRAPH NUMBERING

The numbering and lettering of sections and paragraphs in this Project Manual are merely for identification.

Sections included are listed in this Table of Contents together with the number of pages in each section.

The Contractor shall check their copies of the Project Manual against this Table of Contents and confirm there are no missing pages or sections.

NUMBER TITLE NO. OF PAGES

00 01 10 Table of Contents

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 Summary of Work 01 11 40 Work Restrictions 01 26 01 Contract Modification Procedures 01 27 00 Definition of Contract Price Items 01 31 00 Project Management & Coordination 01 32 16 Construction Schedule 01 32 33 Photographic Documentation 01 33 23 Submittal Procedures 01 35 13.22 Archeological Protection 01 35 23 Safety Requirements 01 40 00 Quality Requirements 01 42 00 References 01 50 00 Temporary Facilities & Controls 01 57 23 Under-An-Acre Pollution Prevention 01 67 00 Product Requirements 01 73 40 Execution 01 74 19 Construction Waste Management & Disposal 01 77 00 Closeout Procedures 01 78 23 Operation & Maintenance Data 01 79 00 Demonstration & Training

See Specifications Volume 2 for required Division 2 thru 48 work.

VOLUME 1 OF 2

DIVISION 01

GENERAL REQUIREMENTS

OLYM – 306966 & 307067 01 11 00 - 1

SUMMARY OF WORK

SECTION 01 11 00

PART 1 – GENERAL

1.1 SUMMARY

A. Section includes the following:

1. Work Covered by Contract Documents

2. Contractor Use of Site

3. Public Use of Site

4. Occupancy Requirements for Buildings

5. Conduct of Operations

6. Work Restrictions

7. Special Construction Requirements

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Location: This project is located at the Hurricane Ridge developed area in Olympic National Park, WA. Hurricane Ridge is located approximately seventeen (17) miles south of Port Angeles, WA on Hurricane Ridge Road. Port Angeles lies approximately one hundred twenty

(120) miles north-west of Olympia, WA via State Highway 101 E and eighty-five (85) miles north-west of Seattle, WA via State Highway 101 W.

B. The work consists of the following:

1. Rehabilitate the existing water storage and distribution system for Group A public water system ID NP390 Hurricane Ridge, specifically:

a. Provide private utility locates and replace all tank fill and distribution system piping east of and including Water Valve Box #2 with DR11 high-density polyethylene (HDPE) pipe and all associated appurtenances including valves, assemblies, meters, and other elements. Place electrical conduit where trenching is shared with water lines, install electrical pull boxes as needed, and complete trench backfill, compaction, and testing. Demolish existing water distribution components above-ground (e.g. obsolete valve boxes) and below-ground when required to install new water line, including removal and disposal of asbestos cement pipe in accordance with applicable regulations. Replace all distribution system piping west of and including Water Valve Box #1 with DR11 HDPE pipe and all associated appurtenances to supply two comfort stations. Stockpile trench spoils in archaeologically sensitive areas to allow NPS sifting for artifacts prior to backfill with or removal of spoils. Restore all asphalt, traffic paint, concrete, gravel, and native vegetation surfaces; native vegetation within subalpine meadow utility corridor shall be salvaged, set aside, and re-established (watered to saturation) following utility replacement. Complete all disinfection and testing requirements to re-establish potable water service throughout the service area.

OLYM – 306966 & 307067 01 11 00 - 2

b. Furnish and install new pressure transmitter on distribution line in Reservoir Valve Vault #1, and replace float switch(es) in south reservoir for redundant well pump control. Replace conductors for well pump control from existing well building to reservoir using new and existing conduit. Furnish and install new well control panel and enclosure that includes functionality for new reservoir float switches, new pressure transmitter, and existing well pump variable frequency drive in existing treatment building. Furnish and install spill containment drum scale and portable emergency eyewash in treatment building.

c. Perform structural inspection and then rehabilitate the 100,000-gallon dual-chamber cast-in-place reinforced concrete water storage reservoir, including blasting/cleaning and recoating both interior and top surface, replacing and resealing pipe penetrations, reconstruction of appurtenances (e.g. valves, piping), and all associated testing and disinfection to return tank to service.

d. Prepare and execute a temporary water service plan to retain water service to temporary restroom and office trailers during construction, and furnish and maintain portable toilets at permanent comfort stations #1 & #2 until restoration of water service is complete.

2. Option A – Demolish all above-ground obsolete infrastructure associated with the original surface water system and restore site, specifically:

a. Demolish and dispose of abandoned surface water pumphouse.

b. Demolish and dispose of adjacent electrical transformer.

c. De-water impoundment, demolish and dispose of upper concrete intake dam, and re-grade sediment behind dam to re-establish original stream contours.

d. De-water impoundment, then partially notch and dispose of lower concrete intake dam components.

e. Demolish and dispose of other obsolete above-ground infrastructure including weather station, 2-¼” poly line, in-stream valve gate and ladder, and pumps and electrical control components associated with the lower concrete dam.

f. Restore stream channel, re-grade surface water pumphouse site, and decommission pumphouse access road in preparation for NPS revegetation.

3. Option B – Provide remote monitoring capabilities for key water system parameters in temporary utility building, specifically:

a. Furnish and install second (remote) control panel in temporary utility building with new 20 amp, 120V power circuit from existing panelboard; second control panel will provide remote readout capability of chlorine solution drum scale weight, existing RoseMount well pump flow meter, and reservoir level.

b. Install additional electrical conduit, conductors, and pull boxes, as required, to enable communication of key water system parameters from existing well treatment building to existing temporary utility building.

C. The project will be constructed under a single prime contract.

1.3 CONTRACTOR USE OF SITE

OLYM – 306966 & 307067 01 11 00 - 3

A. General: Contractor shall have limited use of site for construction operations. Limit use of premises to areas within the construction limits indicated on drawings. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Contractor may request to use the far west end of the main Hurricane Ridge parking lot for staging of equipment and materials. Any request must consider and ensure adequate space remains for safe turnaround of large vehicles including buses and Recreational Vehicles (RVs), and full lane widths are available for through-traffic to Hurricane Hill.

2. Contractor may request to use the original Visitor Center / Day Lodge site for staging of equipment and materials. Any request to use this site shall include a description of the route and any improvements or modifications required for access from the main parking lot.

B. Site Access: Contractor shall access the project site via Hurricane Ridge Road, which requires passing through the NPS Heart O’ the Hills Entrance Station. Entrance fees will be waived for Contractor and all subcontractors and suppliers directly supporting the project during the period of performance.

1. Access from the main parking area to the reservoir for vehicles and equipment is generally possible via the asphalted High Ridge Trail. Note that the paved width of this trail is approximately 5-6 feet. Impacts to the trail and trail shoulders resulting from vehicle and equipment access shall be restored to pre-construction conditions.

C. Construction Time Period: Timing of work shall be coordinated with the Contracting Officer and follow the approved Contractor’s work schedule.

1. Target start date of project is May 5, 2025; onsite work may start earlier if seasonal snow conditions allow access. Note that NPS does not generally perform snow removal operations at Hurricane Ridge during the month of April. Late season snow storms may require NPS to close Hurricane Ridge Road to public access at Heart O’ the Hills Campground. Contractor will be allowed to access the project site but must self-perform any additional snow removal required for construction activities during the month of April.

2. Target opening date of Hurricane Hill Road (extension of Hurricane Ridge Road from main parking area to Hurricane Hill Trailhead) is Memorial Day weekend. NPS generally performs snow removal along the road corridor during the month of May to provide holiday weekend access to the public. The NPS snow removal corridor will generally extend no more than one foot beyond the edge of pavement. Contractor may request that Hurricane Hill Road remain closed to public access during weekdays (Monday – Thursday) for up to four weeks after Memorial Day weekend to facilitate rapid replacement of water line to comfort stations.

3. Contractor may request partial closures of parking areas within the main Hurricane Ridge parking lot for installation of new water line, or to provide access for equipment and materials. In general, no more than 200 lineal feet of parking area may be closed for construction at a time. Requests for partial closures of parking areas between mid-July and Labor Day will only be approved when absolutely necessary and must be kept to the minimum size and duration to complete the work.

4. If the contract option is exercised, demolition work associated with removal of the concrete intake dams shall be completed between August 1, 2025 and Labor Day (i.e., the driest time of the year) to minimize negative impacts to plant and wildlife species.

OLYM – 306966 & 307067 01 11 00 - 4

D. Staging and Storage of Materials: Confine storage of equipment and materials to the staging/lay-down/storage areas identified within the area designated by the Contracting Officer or as established at the preconstruction meeting. To minimize the amount of ground disturbance, staging and stockpiling areas shall be located in previously disturbed sites, away from visitor use areas to the greatest extent possible. All staging and stockpiling areas shall be returned to pre-construction conditions following construction.

1. To minimize impacts to vegetation surrounding the water storage reservoir, soil cover shall be excavated from one half of the storage tank lid and stockpiled on the other half during cleaning and surface sealing up to and including the seam between lid and sidewall, then vice versa for the other half until the entire water storage reservoir lid and seams have been cleaned and sealed.

E. Vehicles & Equipment: Confine parking to areas designated for parking or staging of materials and equipment.

1. No unattended motors/engines are permitted. No idling of motors or engines for extended periods of time is permitted.

2. Fueling of any type, whether equipment or vehicles, must be done either on non-pervious surfaces such as concrete or asphalt, or deploy a spill containment pad.

3. Equipment must be free of any fluid leaks (fuel, oil, hydraulic fluid, etc.) upon arrival to the work site and will be inspected at the beginning of each shift for leaks. Leaking equipment will be removed off site for necessary repairs before the commencement of work.

F. Preservation of Natural Features:

1. Re-use fill, rock, or topsoil from the project area, if possible. If not possible, then the

Contractor shall submit a list of proposed sources, end-use, and temporary storage requirements for imported material, 30 calendar days before delivery. The sources of imported rock, sand, gravel, and soil shall be inspected for invasive non-native plants, weeds, and/or seeds. The material must not be stockpiled at the quarry for more than 1 week after washing. If material comes from older stockpiles, the quarry must be certified weed-free by the County Noxious Weed Coordinator or a qualified weed inspector designated by NPS. For details on obtaining pit inspections and topsoil specifications, contact Contracting Officer’s Representative (COR) and provide at least 14 days notice that an inspection is needed. Imported material shall be free of non-native weeds and/or seeds. Imported material shall be shipped directly from the source to the Park without intermediary storage or staging.

2. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

3. Provide temporary barriers to protect existing trees and plants and root zones.

4. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer’s Representative (COR) and remove agreed-on roots, branches, and small trees that interfere with construction.

5. Do not fasten ropes, cables, or guys to existing trees.

6. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage. Where utility excavation or trenching intersects root systems of larger trees, cut roots greater than 3 inches in diameter cleanly with a sharp tool such as a saw (i.e. do not tear with the excavator).

7. Erosion control measures shall follow the approved UPPP.

OLYM – 306966 & 307067 01 11 00 - 5

8. Care shall be taken not to disturb any wildlife species (marmots, mountain beavers, reptiles, migratory birds, raptors, or bats) found nesting, hibernating, estivating, or otherwise living in, or immediately nearby, worksites.

9. All disturbed ground shall be reclaimed using appropriate best management practices, which may include planting or seeding with native vegetation, or, in the case of small treatment areas, allowing native vegetation to reclaim the area naturally. Contractor shall consult with Contracting Officer’s Representative to determine the best methods for restoration.

10. Where trenching for water line installation or replacment traverses native subalpine meadow vegetation, Contractor shall be responsible for removal, preservation, and replacement of vegetation in the form of “sheets”, “mats”, “plugs”, or similar. Vegetation within the trench cut shall be removed in the largest contiguous sheets possible, with a target depth/thickness of 6-8”, and set aside (orientation: vegetation up, roots down) until native vegetation sheets can be replaced following installation of new water line.

Vegetation sheets can be stockpiled or staged directly on top of existing vegetation if not left for longer than 72 hours. Contractor shall be responsible for watering vegetation sheets to maintain adequate moisture if vegetation sheets are outside the trench for longer than 72 hours without measurable precipitation. Contractor shall be responsible for watering subalpine meadow vegetation sheets to the point of saturation (i.e., when soil reaches its maximum capacity to hold water, and excess water begins to drain away from the root zone) within 24 hours of re-establishing native vegetation in the trench following backfill and compaction.

11. All native subalpine meadow vegetation removed and replaced within the utility corridor (i.e., from the reservoir to the main parking area) shall be watered to the point of saturation one final time between the dates of September 15 and October 1, 2025, regardless of the actual date when the work of this contract is substantially complete.

G. Driveways and Entrances: Keep driveways, areas specifically designated by the Contracting

Officer, and entrances serving premises clear and available to Government, Government employees, user groups, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

1. Schedule deliveries to minimize the use of driveways and entrances.

2. Schedule deliveries to minimize space and time requirements for the storage of materials and equipment on-site.

H. Construction Camp: The establishment of a camp within the Park is not permitted.

I. Hauling Restrictions: Comply with legal load restrictions in hauling of materials. Load restrictions on park roads are identical to state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment

J. All work is restricted to the pre-approved construction area. No impacts to areas outside of the construction area shall occur.

K. There shall be no in-water work. Any work involving demolition of intake dams associated with abandoned surface water infrastructure will require dewatering and/or stream diversion to avoid working in water.

OLYM – 306966 & 307067 01 11 00 - 6

L. Refer also to Section 01 50 00 Temporary Facilities & Controls.

1.4 PUBLIC USE OF THE SITE

A. Contractor may request that Hurricane Hill Road remain closed to public access during weekdays (Monday – Thursday) for up to four weeks after Memorial Day weekend to facilitate rapid replacement of water line to comfort stations. Contractor shall have complete control of this area during that time for construction, staging, storage of materials and equipment, etc.

B. Contractor shall conduct operations to ensure the least inconvenience to the public. Contractor may request partial closures of parking areas within the main Hurricane Ridge parking lot for installation of new water line, or access for equipment and materials. Road closures of up to four hours may be permitted, when required, upon specific approval of Contracting Officer.

Maximum duration of road closure will depend upon the time of year and level of activity for each specific road segment. Requests for any closures between mid-July and Labor Day will only be approved when absolutely necessary.

1.5 OCCUPANCY REQUIRMENTS FOR BUILIDINGS

A. Existing Buildings

1. Full Government Occupancy: Government will occupy buildings under construction during the entire contract period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform Work so as not to interfere with Government's day-to-day operations. Maintain existing exits, unless otherwise indicated.

a. Maintain existing water treatment and temporary utility buildings in weather tight condition throughout construction period. Repair damage caused by construction operations. Protect buildings and occupants during construction period.

1.6 CONDUCT OF OPERATIONS

A. Contractor shall conduct his or her operations in conformance with rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by Park Superintendent.

B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed unless stated in the Work Restrictions below or without prior consent from the Contracting Officer. Submit requests five (5) business days in advance of the work to the Contracting Officer for approval.

C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.

1.7 WORK RESTRICTIONS

OLYM – 306966 & 307067 01 11 00 - 7

A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7 a.m. to 5:30 p.m., Monday through Friday, except when otherwise indicated.

1. Weekend Hours: Same as On-Site Work Hours, with approval from the Contracting Officer

B. Existing Utilities

1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.

2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.

3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

1. Notify Contracting Officer not less than five (5) business days in advance of proposed utility interruptions.

2. Do not proceed with utility interruptions without Contracting Officer’s written permission.

3. Contractor shall furnish and install all components necessary to provide temporary water service to the existing temporary office and restroom trailers located in the main Hurricane Ridge parking area. See Sub Sheet G01 General Notes for a proposed temporary water plan. Contractor may submit an alternative temporary water plan to the Contracting Officer for review and approval. If a water service outage to the temporary restroom trailer is expected to last longer than one (1) hour, Contractor shall provide one Americans with Disabilities Act (ADA) compliant portable toilet and four standard portable toilets, each with a hand sanitizer dispenser, until functionality of the temporary restroom trailer is restored.

4. Starting Memorial Day weekend, for each picnic area comfort station without water service, Contractor shall provide one Americans with Disabilities Act (ADA) compliant portable toilet and two standard portable toilets, each with a hand sanitizer dispenser.

Temporary facilities shall be serviced as needed, but at least twice per week, until permanent water service is restored to each comfort station.

D. Nonsmoking Building/Tobacco Use/Vaping: Smoking is not permitted within building or within 25 feet of entrances, operable windows, or outdoor air intakes.

E. See additional work restrictions in Section 01 11 40 Work Restrictions.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION

OLYM – 306966 & 307067 01 11 40 - 1

WORK RESTRICTIONS

SECTION 01 11 40

1.1 PARK REGULATIONS

A. General: The Contractor must comply with the following rules and conditions:

1. Ensure personnel (contractors or subcontractors) working in the park become familiar with and obey all park regulations, wear hard hats in designated areas, and do not enter any restricted areas unless required to do so and until cleared for such entry.

2. Ensure equipment is conspicuously marked for identification.

3. The Contractor shall restrict employees/representatives to the worksite and control travel directly to and from the worksite.

4. Restore all traffic/parking/security signs and markings, including space numbers, designations, and lines, to their original form if such signs/markings are defaced or deleted during construction/repair.

5. Control and provide security of Contractor-owned equipment and materials at the worksite. Report immediately missing/lost/stolen property to the park dispatch/law enforcement rangers at (360) 565-3115.

6. All work is restricted to the pre-approved construction and staging areas. No impacts to areas outside of the construction and staging areas, as designated in the drawings and by the Contracting Officer, shall occur.

7. Vehicles/Heavy Equipment:

a. Rules of the Road: All vehicles and heavy equipment will comply with posted traffic regulations, including speed limits and double-yellow center lane markings.

Vehicles and heavy equipment shall take every safe opportunity to use paved roadside pullouts to allow faster-moving traffic to pass. Failure to comply with traffic regulations will result in a citation being issued to the driver.

b. Vehicle Parking: Vehicles are not permitted within long-term or overnight parking along park roads or in associated overlooks/pullouts. Vehicles and heavy equipment will be permitted at designated parking areas only or as established at the preconstruction meeting.

c. Vehicle Exhaust: All vehicles will be properly maintained to ensure that the exhaust produced is within legal limits. Effects of excessive vehicle exhaust may be subject to enforcement of State and Federal laws regarding emissions as well as those regarding threatened and endangered species. No unattended motors/engines are permitted. No idling of motors or engines for extended periods is permitted.

d. Fueling: Fueling of any type, whether equipment or vehicles, must be done either on non-pervious surfaces such as concrete or asphalt and/or with deployment of a spill containment pad.

OLYM – 306966 & 307067 01 11 40 - 2

e. Spills: Equipment must be free of any fluid leaks (fuel, oil, hydraulic fluid, etc.)

upon arrival at the worksite and shall be inspected at the beginning of each shift for leaks. Leaking equipment shall be removed off-site for necessary repairs before the commencement of work. The contractor shall be responsible for any cleanup efforts required by 40 CFR and all applicable state environmental quality laws regarding disposal and cleanup of hazardous/industrial wastes. The contractor must immediately notify the Contracting Officer of spills.

f. DOT Compliance: All vehicles are to be compliant with all DOT requirements including but not limited to a driver with appropriate license class, medical examiner card as appropriate with license class, carrying three (3) triangles or three

(3) flares, mounted fire extinguisher, and valid DOT safety sticker.

g. Oversized Vehicles: Oversized vehicles are defined as vehicles where the width of the vehicle or load exceeds one lane (i.e., beyond the centerline of the paved road). Oversized vehicles will require an escort and drivers must avoid driving on the edges of the Park road. The Contractor is to notify the Contracting Officer of oversized vehicles, scheduled dates and estimated arrival times at the park entrance, and the identity of who is escorting the vehicle (e.g., police, contractor, etc.).

h. Road Work: The contractor shall provide adequate traffic control, including flaggers on either side of any work performed on the road. Any workers on or near the road must wear highly visible, bright clothing. (See Section 01 50 00 for additional details).

i. Law Enforcement: Law enforcement rangers will intervene if they perceive any unsafe or unlawful activity. The contractor must immediately comply with any instructions issued by a park law enforcement ranger.

k. Road & Weight Restrictions: All vehicle load, weight, and size limitations, as established by State law, apply to vehicles operated on the Park road (36 CFR § 4.11). Comply with all legal load restrictions in the hauling of materials. Load restrictions on Park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on Park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve the Contractor of liability for damage that may result from the moving of equipment.

8. Emergency Medical and Accident Reporting:

a. The Contractor or subcontractor shall contact Park Dispatch for any medical emergency or traffic accident occurring within the Park.

Emergency number: Dial 911 as needed.

Park Dispatch: (360) 565-3115

b. Park Dispatch is called so that any available Emergency Medical Services personnel in the Park might respond until the ambulance arrives.

c. The Contractor or subcontractor is required to report ANY personal injury and/or property damage incident occurring within the park. This report must be made to a Law Enforcement Ranger at the first available opportunity before leaving the Park:

Park Dispatch: (360) 565-3115

OLYM – 306966 & 307067 01 11 40 - 3

1.2 RESOURCE PROTECTION

A. General: The park is committed to protecting natural and cultural resources found within the park and adjacent lands. The Contractor must comply with the following rules and conditions:

1. Invasive Species: The introduction of non-native invasive species can threaten rare and endangered species or can create new populations of non-native species not traditionally found in the park. The contractor is required to inform personnel, subcontractors, and vendors to thoroughly clean all vehicles, equipment, tools, supplies, and materials before packing/loading. Before entering the park, all workers shall check vehicles, equipment, tools, boots, and backpacks for weed seeds, mud that could harbor weed seeds, and plant parts. All equipment shall be power washed and inspected before being off-loaded at Hurricane Ridge within Olympic National Park to ensure it is free of non-native weeds and/or seeds. The park requires and will perform inspections to ensure non-transport of non-native species BEFORE equipment is off-loaded. Contact the COR at least (3) three days in advance of park entry to arrange for an inspection(s) at Olympic National Park Headquarters (600 E. Park Ave., Port Angeles, WA) prior to entering the park.

2. Endangered Species: Endangered species are protected by Federal law. Obey all park regulations. Drivers must obey all traffic laws and keep an eye out for animals on or alongside the road. Contact park dispatch at (306-565-3100) immediately if the animal is hit or injured or will not move off of the road.

a. Remove all materials, including trash and food wastes, from the project site to reduce the attraction of marbled murrelet predators such as crows and jays.

b. Care shall be taken not to disturb any wildlife species (marmot, mountain beaver, reptiles, migratory birds, raptors, or bats), whether endangered or not, found nesting, hibernating, estivating, or otherwise living in, or immediately nearby, the worksite.

3. Archaeological Resources: Archaeological resources are physical pieces of evidence of past human activity, including evidence of the effects of that activity on the environment.

Archaeological resources are found above and below the ground and underwater. If unknown archaeological resources are discovered during construction, the contractor shall stop work or relocate work to a non-sensitive area until resources can be properly recorded and evaluated, and contact the Contracting Officer immediately. Measures shall be taken to avoid further resource impacts or to mitigate their loss or disturbance.

Archaeological resources typically found in the park or at the project site will be discussed further at the preconstruction meeting.

4. Soundscape / Noise: The contractor shall minimize noise levels at the project site to protect the soundscape of the park. Perform noise-producing work in less sensitive hours of the day or week or as directed by the Contracting Officer.

OLYM – 306966 & 307067 01 26 00 - 1

CONTRACT MODIFICATION PROCEDURES

SECTION 01 26 00

PART 1 - GENERAL

A. The work of this section consists of administrative and procedural requirements for contract modifications.

1.2 DEFINITIONS AND ALLOWANCES

A. Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):

1. Rent

2. Utilities

3. Furnishings

4. Office equipment

5. Executive and management staff not exclusively assigned to the project

6. Support, accounting, and administrative staff

7. Preparation of cost proposals, estimating, and schedule analyses connected with

Modifications

8. Estimating and preconstruction services

9. Mortgage costs

10. Real estate and corporate taxes

11. Automobile maintenance and travel costs for home office personnel

12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.

13. Depreciation of equipment and other assets

14. Home office supplies (paper, staples, etc.)

15. Legal services

16. Accounting and data processing

17. Professional fees/registration

B. General Conditions (Field Office Overhead): Management and administrative costs incurred on-site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:

1. Contracting Officer, Contracting Officer Representative

2. Superintendent, Assistant Superintendent

3. Quality Control, Safety Officer, Environmental Manager, etc.

4. Engineers

OLYM – 306966 & 307067 01 26 00 - 2

5. Travel, lodging, and per diem (as established by Federal Travel Regulations)

6. Scheduling

7. Field Office Trailers and associated temporary utilities

8. Field office supplies

a. Mailing and couriers

b. Reproduction costs

c. Storage

d. Phones

e. Computers

f. Copiers

9. Personal vehicles i.e. Superintendent Pickup trucks

C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs:

1. Hoisting

2. Material handling

3. Temporary fencing

4. Portable toilets and handwashing units

5. Trash removal, dumpsters

6. Barricades

7. Small tools

8. Safety supplies

9. Scaffolding

10. Daily cleaning

11. Traffic control

12. Temporary signage

13. Temporary heating and power

D. Personnel Costs: Costs included in the modification must only be for General Conditions, staff and workers present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a forty (40) hour week and no overtime or holiday pay will be allowed.

1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:

a. Base Rate: This is the hourly rate paid directly to the worker

b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums, such as:

1) Social Security

2) Medicare

3) Workers’ Compensation – Policy and company calculation to be made available.

4) FUTA – Cap Rate and percentage to be proportionally allocated over one year.

5) SUTA – Cap Rate and percentage to be proportionally allocated over one year.

6) Union agreement costs – Other costs required under an enforceable collective bargaining agreement.

c. Fringe Benefits: Various non-wage compensations provided to employees such as:

1) Health Care Insurance Premiums http://en.wikipedia.org/wiki/Employee

OLYM – 306966 & 307067 01 26 00 - 3

2) Cell Phone

3) Clothing

4) 401K and Pensions

5) Vehicle allowances

6) Gas allowance

7) Life insurance premiums

8) Disability insurance

9) Other Fringe Benefits required under an enforceable collective bargaining agreement

E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.

F. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party.

G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee the satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each project based on a sliding scale that relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.

H. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.

1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS

A. General:

1. Your proposal must be received in the format and within the time frame specified in the

Request for Proposal letter. Costs or delays resulting from the failure of the contractor to submit within the time frame specified will not be compensable.

2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor, Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that they are included in the hourly rate shown, or the contractor is not requesting reimbursement.

The contractor may utilize the government-provided Contractor Estimate Form or their form, provided that it contains comparable information as the Government-provided form and is acceptable to the Contracting Officer.

3. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.

4. The contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing before submission to the NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.

http://en.wikipedia.org/wiki/Surety_bond http://en.wikipedia.org/wiki/Insurance http://en.wikipedia.org/wiki/Bank http://www.nps.gov/dscw/publicforms.htm#ct

OLYM – 306966 & 307067 01 26 00 - 4

5. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include a built-in contingency.

B. Labor:

1. The contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each, and itemizing the hours required for each craft that will be directly engaged in modification work. Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be following the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State, or local laws.

2. Itemize labor costs for equipment operators separate from equipment costs.

3. The labor cost for foremen shall only be costs for related work required for the modification.

C. Materials:

1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.

2. No markup shall be applied to any material provided by the NPS.

D. Equipment:

1. Equipment used for the project must be appropriately sized for the work being performed.

2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of five hundred dollars ($500) or less. Costs shown over five hundred dollars ($500) must be broken out separately.

3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:

a. U.S. Army Corps of Engineers, Ownership and Operating Expense Schedule (use the latest edition and applicable region)

b. Construction Blue Book

c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.

4. The estimated rental rates shall include the cost of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of a major overhaul is not included), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.

5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.

6. Standby unit rates used are to be following paragraph 1.3, D, 2, above. If the US Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then one-half (½) of the equipment costs minus any operating costs will be accepted.

7. If the equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.

OLYM – 306966 & 307067 01 26 00 - 5

8. Equipment that is not used and on the job site for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work.

Equipment that is still on the job site but not in use after five consecutive days will not be considered in the modification pricing.

9. Requests for compensation for equipment stand-by time must be justified, documented, and itemized separately.

10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.

E. Establishment and Application of Overhead and Profit Percentages:

1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts, and overhead shall not be applied to profit. Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in the FAR Part 31which have been applied to the specific type of work included in this project. The following percentages establish the maximum allowable markups (OH&P) for contractor self-performed work:

Overhead………………10% Profit…………………..12%

2. The total aggregate limit of markup (OH&P) for contractors and subcontractors on modification work shall not exceed twenty-five percent (25%). The NPS will not be responsible for the allocation of percentages between contractors and subcontractors at any tier.

3. If contractors form a partnership, then the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3, E,1 above). It is the responsibility of the partners to decide on the division of revenue.

4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.

5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.

PART 2 - PRODUCTS (not used)

PART 3 - EXECUTION (not used)

OLYM – 306966 & 307067 01 27 00 - 1

DEFINITION OF CONTRACT LINE ITEMS

SECTION 01 27 00

A. This section intends to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.

B. If no contract line item exists for a portion of the work, include costs in a related item.

1.2 QUALITY ASSURANCE

A. Contract line items for drinking water utility piping, modification to existing drinking water piping, and provision/installation of the new drinking water system shall involve materials, equipment, and commissioning approved by the American National Standard Institute NSF/ANSI 61 or Washington State Department of Health for use in potable water systems.

The contractor shall provide documentation following material submittal requirements.

PART 3 - EXECUTION

3.1 LIST OF CONTRACT LINE ITEMS

A. For all line items, no separate measurement for payment will be made. Payment will be at the contract unit (lump sum) price. Distribute mobilization, demobilization, administrative and overhead costs proportionally across contract line items.

B. Contract Line Item No. 1 – Water Distribution System Replacement

1. This line item includes replacement of all tank fill and distribution system piping east of (and within) Water Valve Box #2, and all distribution system piping west of (and within) Water Valve Box #1, with DR11 high-density polyethylene (HDPE) pipe and all associated appurtenances including valves, assemblies, meters, and other elements per the drawings and specifications. This includes private utility locates; all temporary water and portable toilet service required by the contract; placement of all electrical conduit and pull boxes when trenching is shared with new water lines; trench excavation, backfill, compaction, and testing; stockpiling of trench spoils within archaeologically sensitive areas to allow NPS sifting for artifacts prior to backfill or removal of spoils;

competent management and disposal of asbestos cement pipe; saw cutting and removing all concrete and asphalt surfaces as required for water utlility trenching; demolition of existing water distribution system components above-ground (e.g. valve box assemblies) and below-ground when required to install new water line; removal, salvage, and re-

OLYM – 306966 & 307067 01 27 00 - 2

establishment of native vegetation mats for all trenching withing subalpine meadows;

and restoration of all asphalt, traffic paint, concrete, gravel, native soil, and native vegetation surfaces. Include all disinfection and testing requirements to re-establish potable water service throughout the water system service area.

C. Contract Line Item No. 2 – Water System Controls

1. This line item consists of replacing the well pump control system, which includes installing a new well pump control panel with enclosure and alarm system inside the treatment building; connecting the existing well pump variable frequency drive (VFD);

replacing existing reservoir floats with new high and low level alarm floats; installing a new pressure transmitter (level transducer) in Reservoir Valve Vault #1 with remote readout back to the treatment building; adding any electrical pull boxes that may be required to access existing electrical conduit between the treatment building and Water Valve Box #2; and pulling all new electrical control wire between the existing treatment building and storage reservoir for a fully integrated and functional well pump control system. This item also includes installing a spill containment drum scale and portable emergency eyewash inside the treatment building.

2. Installation of electrical conduit and pull boxes for control wire between Water Valve Box #2 and storage reservoir – including all required trenching, compaction, and backfill

– should be captured under Contract Line Item No. 1 – Water Distribution System Replacement.

D. Contract Line Item No. 3 – Water Storage Tank Rehabilitation

1. This line item includes structural inspection of the reservoir; sand blasting/cleaning the

100,000-gallon dual-chamber cast-in-place reinforced concrete underground water storage reservoir; re-coating the tank interior and top surface; replacing and resealing pipe penetrations; replacement of piping and valves between chambers as well as overflow and drain lines adjacent to the reservoir; and all testing associated with confirming quality of coating and proper disinfection to return the rehabilitated water storage reservoir to service.

1.2 LIST OF CONTRACT OPTIONS

A. Option A – Demolition

1. This option consists of demolishing all above-ground obsolete infrastructure associated with the original surface water system and restoring the site, including demolition and disposal of the abandoned cast-in-place concrete surface water pumphouse; demolition and disposal of the adjacent electrical transformer; dewatering the original (north) intake dam impoundment, demolishing the concrete intake dam, and regrading sediments to re-establish the original stream contours; dewatering the lower (south) water supply dam impoundment and notching the dam down approximately 24” by 6’ width to original stream width for passing of large debris; demolishing and disposing of all other obsolete above-ground infrastructure including weather station, poly line, in-stream valve gate and ladder, pumps and electrical control components associated with the lower concrete dam; and general site restoration including restoration of the original stream channel, re-

OLYM – 306966 & 307067 01 27 00 - 3

grading the surface water pumphouse site, and decommissioning of the access road using scarification to prepare the area for revegetation by the NPS.

B. Option B – Remote Monitoring

1. This option consists of providing remote monitoring capabilities for key water system parameters from inside the temporary utility building, including installation of a second (remote) control panel inside the temporary utility building to provide remote readout capability for monitoring chlorine solution tank drum scale weight, existing well pump flow meter/totalizer value, and reservoir level; and installation of power circuits from existing panelboards, additional electrical conduit, conductors, pull boxes, and any other appurtenances required to enable…

This is the start of the file's text. The full file is on GovTribe.