Attach 1 SOW - Statement of Work.pdf
PDF 161 KB Posted
- Attached to
- Buffalo Creek Work Center Office & Engine Storage Additions Federal contract opportunity
- Solicitation number
- 1282B125R0021
- Issued by
- Department of Agriculture Forest Service
About this file
This Statement of Work (SOW) details a construction project for the Pike-San Isabel National Forests & Cimarron and Comanche National Grasslands (PSICC) South Platte Ranger District. The project involves constructing new office space and an additional engine bay as an addition to the existing Engine Storage building at the Buffalo Creek Work Center in Buffalo Creek, Colorado. The 3½-acre work center, originally built in 1938, currently has inefficient historical structures that require modernization.
The contract, valued between $1,000,000 and $5,000,000, requires the contractor to perform comprehensive construction tasks including site utilities installation (water, sewer, natural gas, power, telecommunications), site grading, parking area construction, demolition of existing features, and foundation and mechanical/electrical/plumbing systems construction. Key deliverables include a construction schedule, material submittals, quality control reports, operations and maintenance manual, and as-built drawings. The performance period is set from approximately September 30, 2025, to September 30, 2026, with a site visit and specific contractor personnel requirements outlined in the document.
View the file
Other files for this federal contract opportunity
Show all 41
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION C- STATEMENT OF WORK/SPECIFICATIONS/DESCRIPTION
C.1 SCOPE OF CONTRACT
1.0 Scope of Work
An asset of the Pike-San Isabel National Forests & Cimarron and Comanche National Grasslands (PSICC) South Platte Ranger District (RD), the Buffalo Creek Work Center was built in 1938 by the Works Projects Administration and is located at 18046 County Road 126, Buffalo Creek, CO 80425. The Work Center of roughly 3½ acres hosts several structures, including, but not limited to, the Office, Garage/Shop, and Dwelling constructed in 1938, and the Barracks and Engine Storage constructed in 2002, as well as several other miscellaneous structures and utility features. Like many historical buildings of this age, the office is very inefficient in terms of energy consumption and space utilization. Under this contract new office space and an additional engine bay space will be constructed as an addition to the existing Engine Storage building.
Work in the base items includes mobilization; quality control; construction staking and layout;
construction of site utilities for water, sewer, natural gas, power and telecommunications; final site grading; parking area construction; demolition of existing site features and utilities; and foundation, building, and mechanical/electrical/plumbing systems construction.
Incidental work includes submittals for quality control; submittals for safety and accident prevention; coordination with local utility companies; submittals for products and shop drawings; the construction schedule; construction waste management; operation and maintenance manuals, as well as system demonstration and training.
2.0 Background
The proposed Office and Engine Storage Additions project is located in Buffalo Creek, Colorado.
Meals and lodging may be commercially available in the nearby towns of Pine, Bailey, and Conifer, Colorado and surrounding communities.
The site elevation varies from a high point of approximately 6675 at County Road 126 to a low point of approximately 6650 feet at the northerly end of the property. The climate is temperate with average temperature ranging from the mid-80s in the summer to the low-20s in the winter.
Extremes from these averages can be expected annually. Snowfall in the winter can be abundant during an average winter.
3.0 Contractor Technical Requirements / Tasks
Generally work will consist of the following tasks:
• Mobilization;
• Quality Control, Survey and Staking;
• Construction and upgrading of utilities including water, sewer, natural gas, electrical, and telephone/data systems;
• Site demolition, improvements, grading, temporary erosion control, and identification signs;
• Construction of new office space and engine bay space as a building addition to an existing structure;
• Demolition of existing features and utilities on the site designated in the drawings for removal or replacement;
Construction includes furnishing all labor, materials, equipment, tools, transportation, supplies, storage, other incidentals and all work required to complete the proposed addition, remodel and associated items in accordance with the approved final drawings, specifications and provisions of the contract.
Construction quality control includes supplying all the personnel, equipment, special inspections, tests, and reports necessary to ensure that construction is completed in compliance with the drawings, specifications, and provisions of the contract.
The Contractor shall provide temporary toilet facilities (porta-potty) at the site during all construction work.
A trash abatement program shall be initiated during pre-construction phases of the project and shall continue through the duration of the project. All construction refuse shall be removed from the site and disposed of properly on a weekly basis and upon project completion.
Observation of excavation activities by Forest Service Heritage staff is required during foundation and utility excavation activities.
4.0 Government Furnished
• Water and electricity are available at the site for construction purposes.
5.0 Period of Performance
The awarded Base Items constituting the work of this RFP shall be provided from approximately September 30, 2025, to September 30, 2026.
6.0 Deliverables / Schedule
Key Deliverables
Item No.
Deliverable Objective Due
1 Construction Schedule
Defining the responsibilities, timeline, risks, and milestones of contract objectives.
No later than the date of the prework conference
2 Material and Equipment Submittals
All material specifications, product data, manufacturer’s instructions, and material safety data sheets
During construction according to schedule
3 Quality Control Reports
Materials testing, construction observation, and special inspections documenting compliance with the Contract Documents.
During construction as indicated
4 Operations & Maintenance (O&M) Manual
Binder including equipment manufacturer’s data, system schematics and descriptions, maintenance schedules, etc.
Prior to final inspection
5 As-built Drawings Drawings that recognize any changes in the plans, specifications, and/or approved submittal of equipment supplied
Prior to final inspection
7.0 Travel
All costs associated with travel to and from the job site, including mobilization of all equipment and materials shall be included in the Contractor’s cost proposal.
8.0 Contractor’s Key Personnel
Project Manager – individual designated by the General Contractor, serves as primary points of contact and shall have overall responsibility for managing and coordinating the performance of the Contractor’s obligations under this contract, including performance of all Subcontractors, and be authorized to act for and bind Contractor and Subcontractors in connection with all aspects of this contract.
Project Superintendent – onsite representative of the General Contractor, responsible for overall management of the project and capable of discussing technical aspects of the project.
9.0 Site Visit – See the solicitation for POC, date, time and location of the site visit.
C.2 PROJECT LOCATON
The project is located at the Buffalo Creek Work Center at 18046 County Road 126, Pine, Colorado 80470.
C.3 MAGNITUDE OF CONSTRUCTION PROJECT
Government Cost Estimate, per FAR 36.204, is between $1,000,000 and $5,000,000.
C.4 TECHNICAL SPECIFICATIONS
See Section J for Attachments
| SECTION C- STATEMENT OF WORK/SPECIFICATIONS/DESCRIPTION |
| C.1 SCOPE OF CONTRACT |
| 1.0 Scope of Work |
| 2.0 Background |
| 3.0 Contractor Technical Requirements / Tasks |
| 4.0 Government Furnished |
| 5.0 Period of Performance |
| The awarded Base Items constituting the work of this RFP shall be provided from approximately September 30, 2025, to September 30, 2026. |
| 6.0 Deliverables / Schedule |
| Key Deliverables |
| 7.0 Travel |
| 8.0 Contractor’s Key Personnel |
| C.2 PROJECT LOCATON |
| C.3 MAGNITUDE OF CONSTRUCTION PROJECT |
| C.4 TECHNICAL SPECIFICATIONS |