About this file

This document is an Amendment (0001) to a federal solicitation for the Buffalo Creek Work Center & Engine Storage Additions project located in Buffalo Creek, Colorado. The amendment modifies the original solicitation (1282B125R0021) by: 1) extending the proposal due date from June 24, 2025, to July 15, 2025, at 10:00 a.m. Central Time; 2) providing a site visit attendee list with sixteen participants; and 3) indicating that an additional amendment responding to contractor questions, updated drawings, and specifications is anticipated by June 30, 2025.

The project involves constructing new office space and an additional engine bay at the Buffalo Creek Work Center, a 3-acre facility built in 1938 by the Works Projects Administration. The contract scope includes mobilization, quality control, site utilities installation, grading, parking area construction, demolition of existing site features, and construction of building foundations, mechanical, electrical, and plumbing systems. The performance period is set for 09/30/2025 to 09/30/2026, and the solicitation is issued by the USDA Forest Service for the Pike San Isabel & Cimarron and Comanche National Grasslands.

View the file

Other files for this federal contract opportunity

Other files attached to Buffalo Creek Work Center Office & Engine Storage Additions, newest first.
File Type Posted
A0003_BCWC.pdf PDF
A0002_SUMMARY OF CHANGES.pdf PDF
2023-06-05_R2 - CO_PKSI - BCWC_Water Wastewater Memo.pdf PDF
2024-10-10_R2 - CO_PKSI - BCWC_CORE Electric Construction Install.pdf PDF
2022-12-29_R2 - CO_PKSI - BCWC_MEP Summary.pdf PDF
2024-10-10_R2 - CO_PKSI - BCWC_CORE Electric Construction Removal.pdf PDF
A0002_BCWC.pdf PDF
Attach 10-Specifications Project Manual 06.24.25.pdf PDF
Attach 03 - Updated Drawings_06.24.2025.pdf PDF
2024-01-01_R2 - CO_PKSI - BCWC_CORE Electric Builder Developer Service Requirements.pdf PDF
2022-10-12_R2 - CO_PKSI - BCWC_Existing Fence.jpg JPG image
Reduced _Attach 12 - A and E Report BCWC.pdf PDF
Reduced_Attach 7b - Drawings 5 of 7 Elec.pdf PDF
Reduced_Attach 7a - Drawings 5 of 7 Elec.pdf PDF
1282B125R0021_BCWC.pdf PDF
Attach 1 SOW - Statement of Work.pdf PDF
Attach 3 - Drawings 1 of 7 Arch.pdf PDF
Attach 10 a_Parts 1-10 Specifications BCWC.pdf PDF
Attach 10 i_Parts 57-64 Specifications BCWC.pdf PDF
Attach 13 - Commissioning Plan.pdf PDF
Attach 14 - Guiding Principles.pdf PDF
Attach 17 - WD_CO20250023 dated 05.16.2025.pdf PDF
Attach 4- Drawings 2 of 7 Civil.pdf PDF
Attach 7 - Drawings 5 of 7 Elec.pdf PDF
Attach 10 d_Parts 23 -26 Specifications BCWC.pdf PDF
Attach 2_Schedule of Items.xlsx XLSX spreadsheet
Attach 5 - Drawings 3 of 7 Structural.pdf PDF
Attach 6 - Drawings 4 of 7 Mech_Plumb.pdf PDF
Attach 9 - Drawings 7 of 7 Tech.pdf PDF
Attach 10 b_Parts 11-15 Specifications BCWC.pdf PDF
Attach 10 e_Parts 27 -35 Specifications BCWC.pdf PDF
Attach 10 f_Parts 36 -43 Specifications BCWC.pdf PDF
Attach 10 g_Parts 44 -49 Specifications BCWC.pdf PDF
Attach 10 h_Parts 50 -56 Specifications BCWC.pdf PDF
Attach 15 - Materials Board.pdf PDF
Attach 8 - Drawings 6 of 7 Fire.pdf PDF
Attach 10 c_Parts 16 -22 Specifications BCWC.pdf PDF
Attach 11 - Geotechnical Report.pdf PDF
Attach 12 - A and E Report BCWC.pdf PDF
Attach 16 - Survey.pdf PDF
Attach 18_Buffalo Creek HazMat Report 032825.pdf PDF
Show all 41

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUMMARY OF CHANGES

PROJECT: BUFFALO CREEK WORK CENTER & ENGINE STORAGE ADDITIONS

PSICC (PIKE SAN ISABEL & CIMARRON and COMANCHE NATIONAL GRASSLANDS) BUFFALO CREEK, COLORADO

SOLICITATION #: 1282B125R0021

The purpose of Amendment 0001 is as follows:

1) to change the proposal due date from June 24, 2025, at 10:00 a.m. Central Time to

July 15, 2025, at 10:00 a.m. Central Time;

2) to provide the Site Visit's Attendee's List of sixteen participants;

3) An additional Amendment to respond to contractor’s questions, provide updated Drawings, and updat tions is anticipated to be issued on or before June 30, 2025. All other terms and conditions remain the same. See the Summary of Changes for details.