Attach_09_AfdStp_ Submittal_Register_20240516.xlsx
XLSX spreadsheet 21 KB Posted
- Attached to
- Re-Stripe Airfield Parking Pavements
- Solicitation number
- W50S8F-24-R-A010
- Issued by
-
Department of the Army National Guard
About this file
This document is a Submittal Register for the "Re-Stripe Airfield Parking Pavements" federal contract opportunity. The Submittal Register outlines the various submittals required from the contractor, including a Job Specific Safety Plan, Quality Control Plan, Project Schedule, Progress Reports, Material Safety Data Sheets, and various paint specifications and samples.
The related federal contract opportunity is a Request for Proposal (RFP) for the re-striping of the Main Aircraft Parking Apron at the 177th Fighter Wing in Egg Harbor Township, NJ. The solicitation is a 100% small business set-aside with a NAICS code of 237310 and a magnitude of construction between $100,000 and $250,000. Bid Guarantee, Payment, and Performance Bonds are required for all offers greater than $150,000. A pre-bid conference and site visit will be conducted by the Government.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| SCHEDULE OF MATERIAL SUBMITTALS | Restripe Main Apron | AQRC242002 | AQRC242002 | ||||||||||||||||||
| TO BE COMPLETED BY PROJECT ENGINEER | Contractor | TO BE COMPLETED BY CONTRACT ADMINISTRATOR | |||||||||||||||||||
| NUMBER OF COPIES REQUIRED | DATE RECEIVED IN CONTRACTING | DATE TO CIVIL ENGINEERING | RETURN SUSPENSE DATE | SUBMITTAL NUMBERS | CONTRACTOR RESUBMITTAL | FINAL APPROVAL | REMARKS | ||||||||||||||
| SUBMITTAL NUMBER | ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL | CERTIFICATION OF COMPLIANCE | SHOP DRAWINGS | SAMPLES | COLOR SELECTION | MFGR'S RECOMMENDATIONS | MANUFACTURER'S WARRANTY | CATALOG DATA | OPERATION INSTRUCTION | PERFORMANCE TEST REPORT | OTHER | SUBMISSION DATE | DATE CONTRACTOR NOTIFIED | ||||||||
| ALL SUBMITTALS SHALL BE SUBMITTED THROUGH PROJECT MANAGEMENT SOFTWARE PER THE SOW | APPROVED | DISAPPROVED | |||||||||||||||||||
| 1 | Job Specific Safety Plan | x | Prior to NTP | 1 | |||||||||||||||||
| 2 | Job Specific Quality Control Plan | x | Prior to NTP | 2 | |||||||||||||||||
| 3 | Project Schedule | x | Prior to NTP | 3 | |||||||||||||||||
| 4 | AF 3065 – Progress Report -DRAFT | x | Prior to NTP | 4 | |||||||||||||||||
| 5 | Key Personnel Letter | x | Prior to NTP | 5 | |||||||||||||||||
| 6 | MSDS Sheets as required | x | Prior to NTP | 6 | |||||||||||||||||
| 7 | Type of paint and quantity of beads required | x | x | x | x | x | Prior to NTP | 7 | |||||||||||||
| 8 | Yellow Reflective paint | x | x | x | x | x | Prior to NTP | 8 | |||||||||||||
| 9 | Yellow Non- reflective paint | x | x | x | x | x | Prior to NTP | 9 | |||||||||||||
| 10 | Blue Reflective paint | x | x | x | x | x | Prior to NTP | 10 | |||||||||||||
| 11 | Black paint | x | x | x | x | x | Prior to NTP | 11 | |||||||||||||
| 12 | White paint | x | x | x | x | x | Prior to NTP | 12 | |||||||||||||
| 13 | Red paint | x | x | x | x | x | Prior to NTP | 13 | |||||||||||||
| 14 | Other submittals as required by Specifications or Drawings | x | x | x | x | x | 14 | ||||||||||||||
| 15 | Field Test Reports | x | NLT 5 Days from date of test | 15 | |||||||||||||||||
| 16 | Close-out Documents - Electronic copies only | Prior to Final Payment | 16 | ||||||||||||||||||
| 17 | Contractor Warranties | 3 | Prior to Final Payment | 17 | |||||||||||||||||
| 18 | Record Drawings | 3 | Prior to Final Payment | 18 | |||||||||||||||||
| 19 | O&M Manual (if applicable) | 3 | 3 | 3 | 3 | Prior to Final Payment | 19 | ||||||||||||||
| 20 | Maintenance Summary Forms | 3 | Prior to Final Payment | 20 | |||||||||||||||||
| 21 | DD 1354 Worksheet | 1 | Prior to Final Payment | 21 |