Attach_06_AfdStp_AQRC242002_Restripe_Main_Apron_SOW_20240423.pdf

PDF 452 KB Posted

Attached to
Re-Stripe Airfield Parking Pavements Federal contract opportunity
Solicitation number
W50S8F-24-R-A010
Issued by
Department of the Army National Guard

About this file

This document is a Scope of Work (SOW) for the project to restripe the Main Aircraft Parking Apron at the New Jersey Air National Guard 177th Fighter Wing in Egg Harbor Township, New Jersey. The project, numbered AQRC242002, involves removing all existing airfield markings and restriping in accordance with an airfield marking plan. The Contractor is responsible for providing all management, supervision, resources, and labor to complete the project per the requirements.

The related federal contract opportunity is a Request for Proposal (RFP) for the re-striping work, solicitation number W50S8F-24-R-A010. The project is a total small business set-aside with a NAICS code of 237310 and a magnitude of construction between $100,000 and $250,000. A bid guarantee, payment, and performance bonds are required for offers over $150,000. A pre-proposal conference and site visit will be conducted. Contractors are responsible for reviewing and adhering to all solicitation requirements.

View the file

Other files for this federal contract opportunity

Other files attached to Re-Stripe Airfield Parking Pavements, newest first.
File Type Posted
24-R-A010_SF30_AfdStp_Solicitation_AMEND_02_20240613.pdf PDF
W50S8F-24-R-A010_SF30_AfdStp_Solicitation_AMEND_02_20240613.pdf PDF
24-R-A010_AMEND_02_AfdStp_Final_QA_20240613.pdf PDF
24-R-A010_AMEND_01_AfdStp_Pre-Bid_Conf_PPT_20240604.pdf PDF
Attach_06_AMEND_01_AfdStp_AQRC242002_Restripe_Main_Apron_SOW_REV_01_20240605.pdf PDF
24-R-A010_AMEND_01_AfdStp_Pre-Bid_Conf_SIGN-IN_20240604.pdf PDF
W50S8F-24-R-A010_SF30_AfdStp_Solicitation_AMEND_01_20240605.pdf PDF
W50S8F-24-R-A010_SF1442_AfdStp_Solicitation_Released_20240517.pdf PDF
Attach_10_AfdStp_DOL_Wage_20240001_Mod_02_20240308.pdf PDF
Attach_13_AfdStp_EMS_Commitment_Statement.pdf PDF
Attach_12_AfdStp_Insurance_Requirements.pdf PDF
Attach_11AfdStp_Project_Mng_Software_Pricing_2024.pdf PDF
Attach_04_AfdStp_Evaluation_Factors.pdf PDF
AfdStp_List_of_Attachments.xlsx XLSX spreadsheet
Attach_08_AfdStp_Project_Drawings_20240119.pdf PDF
Attach_15_AfdStp_177FW_Vicinity_Maps.pdf PDF
Attach_03_AfdStp_Section_00-21-00_Instructions_to_Offerors.pdf PDF
Attach_07_AfdStp_Project_Specifications_20240122.pdf PDF
Attach_14_AfdStp_OPSEC_Letter.pdf PDF
Attach_02_AfdStp_Sect_Notes.pdf PDF
Attach_01_AfdStp_Break_Out.pdf PDF
Attach_05_Exhibit_A_Past_Performance_Questionaire.docx DOCX document
Attach_09_AfdStp_ Submittal_Register_20240516.xlsx XLSX spreadsheet
Show all 23

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCOPE OF WORK

NEW JERSEY AIR NATIONAL GUARD

177th FIGHTER WING CIVIL ENGINEER SQUADRON

EGG HARBOR TOWNSHIP, NEW JERSEY

PROJECT: Restripe Airfield Apron

PROJECT NUMBER: AQRC242002

PROJECT SOLICITATION: W50S8F - 24 - R - A010

DATE: April 23, 2024

The project will include: Removal of all existing airfield markings within the NJANG Main Apron and restriping in accordance with airfield marking plan.

Table of Content:

1. Contractor Responsibilities

2. Project Description

3. General Requirements

4. Administrative

5. Measurement Verification

6. Safety Requirements

7. Technical Compliance

8. Work Week and hours of Operation

9. Project Duration

10. Trash Disposal and Clean-up

11. Environmental Impact

12. HAZMAT Reporting

13. Anti-Terrorism and Operational Security (ATOPSEC)

14. Beneficial Occupancy Prior to Completion

15. Final Acceptance and Completion

1. CONTRACTOR RESPONSIBILITIES

1.1. The Contractor is responsible for providing all management, supervision, financial resources, plant, labor, equipment, and material necessary to perform the work detailed for this project and provide a complete and useable system to the Government.

1.2.All work and deliverables shall be in accordance with this Scope of Work (SOW), all associated documents and drawings, industry standards, Governing Codes and Federal Regulations (FAR, DFARS AND AFARS).

1.3.It is the Contractor`s responsibility to ensure compliance with requirements briefed at the Pre-Construction Meeting (i.e. Environmental, Safety, Fire Department, Security, etc.).

1.4. Complete and Usable System

1.4.1 This scope of work is for a complete and useable system. All components not specifically shown, detailed, or discussed but essential in whole or in part, and required for the intended operation of the system shall be included in the offerors proposal as if specifically shown. In the event of any discrepancy or question, the offeror shall bring it to Contracting Officer prior to submitting their proposal.

1.5 All Solicitation & Technical information shall be interpreted as whole in order to give meaning to all its parts.

2. PROJECT DESCRIPTION

2.1. Overall Project Description – The purpose of this project is to remove all existing pavement markings and to restripe the airfield in accordance with airfield marking plan. The work shall be performed according to the project drawings.

Contractor shall provide all tools, parts, equipment, materials, supervision, professional survey services, and labor to complete the project according to the applicable codes and regulations.

2.2. Detailed Project Description/ Scope of Work – Contractor shall coordinate with

Contracting Officer Representative (COR) and the Airfield Manager at least 21 days before beginning work on the apron in order to give sufficient time for aircraft to be relocated.

2.2.1 Demolition: Removal of old paint shall be to a minimum performance standard of 90% from the concrete pavement and 85% from asphalt pavement performed by high-pressure water blasting. Please reference Section 1.4 of Project Manual for clarification. (See Drawing 001 for removal plan). Contractor shall be responsible for repairing the concrete pavement at no additional cost to the Government, if damaged during removal process.

2.2.2 Installation:

2.2.2.1 The contractor shall verify and perform smooth transitions with adjoining taxiway lines.

2.2.2.2 All taxiway lines shall pass through the centerline of each building or aircraft shelter.

2.2.2.3 Reflective Glass Beads shall be used in the pavement markings at the rate recommended for the type of paint.

2.2.2.4 Contractor must follow the phasing plan provided on the drawings.

Phasing plan has been designed to allow for continued military operations and shall not be deviated from.

2.3 Estimated Quantities: Breakdown of quantity of estimated paint being removed and reinstalled are as follows. Note: Quantities are provided to allow contractor to approximate scope and magnitude of the project. Contractor is responsible for verifying all measurements and quantities in accordance with Item 5 Measurement Verification of this Scope of Work.

2.3.1 Pavement markings removal approximately 23000 LF.

2.3.2 Pavement markings installed approximately (please see sheet 2 of 5 –

Overall View):

2.3.2.1 6” Solid Yellow Reflecting Striping installed according to the attached drawings – 8155 SF

2.3.2.2 Aircraft wheel stops are required, wheel stop is 3 feet long and 1 foot wide with 6” black border. The wheels stops are located 35 feet from the end of the parking spot from each side.

2.3.2.3 6” Solid Black Border Striping is required for better visuality on each side of the yellow reflecting markings on the apron and on each side on white tow lines – 11020 SF

2.3.2.4 6” Solid Blue Reflecting Striping is required for each aircraft parking spot

– 3800 SF

2.3.2.5 6” Solid White Striping is required for end of roadway, double solid line in the middle and tow line exiting the apron – 4560 SF

2.3.2.6 Red Stop Bars, “FOD CHECK” signs and Jersey Devil Striping is required with approximate area of 1150 SF

2.3.2.7 Black background box striping with yellow numbers for all parking spot numbers is required with approximate area of 540 SF (Detail sheet 5 of 6).

2.3.2.8 White background box striping with black writing for GPS coordinates on the apron, and “TOW ONLY” sign with total area of 1025 SF (see Detail sheet 5 of 6)

2.3.2.9 Double Solid 6” Yellow Reflective line with 6” gap in the middle is required at the end of the apron, installed on concrete pavement. 3145 FT (total 3145 SF).

3. GENERAL REQUIREMENTS

3.1.Technical

3.1.1. All work, materials, means, and methods shall follow generally accepted industry standards.

3.1.2. All work and material shall be installed parallel and perpendicular to the building lines and in a neat & workmanship like manner.

3.1.3. Work shall proceed in a safe and professional manner. All OSHA guidelines shall be followed.

3.1.3.1.The Government reserves the right to immediately stop work, at no additional cost to the Government, if unsafe work practices are witnessed and documented.

3.1.4. All material shall be new and for the intended purpose.

3.1.5. Installation material, means, & methods shall match existing facility standards.

3.1.6. The contractor shall request final inspection of the complete work a minimum of two workdays in advance.

3.1.6.1.Inspections shall be scheduled for Tuesday – Friday on a regularly scheduled workday.

3.1.7. If any utility shutdowns are required shall be requested a minimum of three workdays in advance.

3.1.8. CAD drawings will be available to the contractor after award.

3.1.8.1.CAD files will be in dwg format saved with Autodesk AutoCAD 2023.

3.1.9. Provided drawings are not geographically referenced.

3.2.Project Manager & Key Management Positions (ref: FAR 52.236-6)

3.2.1. The contractor shall be required to provide a dedicated Site Superintendent through completion of the project. The Site Superintendent SHALL be on site at all times during active construction activities.

3.2.2. All request for information (RFI) shall be submitted through ProjectMates software, reference Item 4.1 below. Contractor must allow the government two business days to provide a response, if a response cannot be provided within the timeframe the Government will provide the contractor with an estimated time for response.

3.2.3. Project Manager, Quality Control and Site-Superintendent Positions are considered key positions. These positions SHALL NOT be subcontracted below the Prime Contractor.

3.2.3.1.The resumes, certifications, qualifications, and training for these key positions shall be submitted to the Contracting Officer for Approval after Contract Award.

3.3.Secure Area

3.3.1. All work on the project is within a limited access Secure Area. Contractor will be escorted to the work site at the beginning of the workday, 7:00am, and escorted off site at the end of the workday, 3:30 pm. Contractor will be escorted at all times they are on site by a Government Employee.

3.3.2. Sanitary Facilities: Contractor shall provide their own sanitary facilities (port-a-john toilets, wash stations…) for the duration of the project.

3.3.3. Site Office Trailer / Storage: Government facilities are NOT available for administrative use, break areas or secure storage.

3.3.3.1.Contractor shall provide such facilities as he deems required for completion of the project.

3.3.3.2.Utilities (water, natural gas, electric, comm…) are NOT available in the immediate vicinity of the project area. Contractor shall provide for his own utilities, i.e. generator & water tanks. Propane tanks are NOT allowed.

3.3.3.3.Water can be provided by the Government by a dedicated fire hydrant.

Contractor must provide their back flow prevention.

4. ADMINISTRATIVE

4.1.Project Management Software

4.1.1. Project Management software will be utilized to efficiently manage and monitor the project.

4.1.1.1.The 177th Fighter Wing utilizes ProjectMates Construction Program

Management Software.

4.1.2. Fees: The fee schedule is provided on www.SAM.gov as an attachment to the solicitation.

4.1.2.1.Contractor is responsible for the project set-up fees; the one-time Training

Fee; and monthly fees for the duration of the project.

4.2.Bi-weekly Progress Meetings: Meetings will be held in-person at the 177th Fighter

Wing unless teleconference is approved by Contracting Officer in advance.

4.3.Progress Report – AF 3065: Contractor shall provide material and labor cost breakdowns on the Air Force Form 3065 no later than noon one day prior to each bi-weekly progress meeting.

4.3.1. AF 3065 shall be broken out by Contract Line Item Number (CLIN) if the contact contains multiple CLIN.

4.3.2. The Work Breakdown Structure (WBS) shall contain an adequate amount of detail to accurately track project progress.

4.3.2.1.The WBS shall conform to ISO 21511:2018 “Work breakdown structures for project and program management.”

4.4.Material Submittal Log / Register: Contractor is responsible for submitting all submittals prior to fabricating, procuring, or installing any equipment on the project.

Submittals shall be submitted in accordance with the attached Material Submittal Register, the construction drawings, and specifications. All submittals shall be submitted through project management software under section 4.1 above.

4.4.1. Contractor shall provide a final Submittal Register to the Government for review within 10 days after the date of Contract Award.

4.4.2. Material Submittal Register: Contractor is responsible for submitting all material on the Material Submittal Register to the Government for Approval prior to fabricating, procuring, or installing any equipment on the project.

4.4.3. Additional Material Submittals may be required in accordance with Contract Provisions & Clauses included in the Contract (SF1442) or http://www.sam.gov/ as required by the Contracting Officer to ensure that the project meets all applicable Codes, Standards, Regulations, and minimum Contract Requirements. Any additional Material Submittals will be provided by the Contractor at no additional cost to the Government.

4.5.CPM Schedule: Contractor shall provide CPM Construction Schedule within 10 days after the date of Contract Award. Minimum Work Breakdown Structure on the CPM shall include start, completion dates, phasing, & critical milestones. ref: FAR 52.236- 15.

4.5.1. CPM shall be Approved by the Contracting Officer prior to Mobilizing to site.

4.5.2. Construction Schedule will be reviewed at each bi-weekly progress meeting.

4.6.Base Access and Personnel:

4.6.1. All personnel requiring access to the installation will be required to undergo a background investigation in accordance with the Anti-Terrorism and Operational Security (ATOPSEC) section below and will be issued a base ID card, Defense Biometric Identification System (DBIDS).

4.6.1.1.DBIDs badges may ONLY be issued on base, Tuesdays thru Fridays, on normal workdays.

4.6.1.2.Personnel failing their background investigation shall be replaced by the Contactor at no additional cost to the government.

4.6.1.3.Requests for background investigations shall be submitted two weeks in advance of the individual requiring base access. “Same-Day” badges are not available, and that individual will be denied access to the installation.

4.6.2. The single point of entry for the installation is the Main Gate on Tilton Rd.

4.6.3. All vehicles will be searched by Security Forces personnel before gaining access to the installation.

4.6.3.1.Contractors may not bring any weapons, drugs, alcohol, illicit substances, narcotics, or other contraband onto the installation.

4.6.3.2.Offenders will be detained and turned over to local, state, or federal authorities depending on the nature of the offense.

5. MEASUREMENT VERIFICATION

5.1. It shall be the Contractors responsibility to verify all measurements, sketches, and descriptions of work for the project.

5.2.All quantities listed in this Solicitation are for planning purposes only and to assist in the general determination of scope and magnitude.

5.3.Contractor is responsible for using his own measurements, quantities, and material take-offs for proposal purposes.

6. SAFETY REQUIREMENTS (ref. FAR 52.236-13) 6.1.The Contractor shall abide by all State, Local, and OSHA safety requirements relevant to the items described in this SOW. If the Contractor is found to be in violation of any applicable safety regulations on the job site, the Government representative shall stop all work until the unsafe practice has been ceased and corrected.

6.2.Prior to Mobilization:

6.2.1. The Contractor shall submit a Safety Plan in accordance with U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1, ref: FAR 52.236-13(c)

6.2.2. The Contractor shall nominate a dedicated Safety Representative for this project for approval to the Government. The Safety Representative shall hold a valid OSHA 30-Hour Training Card for Construction.

7. TECHNICAL COMPLIANCE

7.1.Government and Department of Defense (DOD) Criteria: Construction shall comply with applicable codes and acts, Air Force Instructions (AFI), Air Force Manuals (AFM), Engineering Technical Letters (ETL), Construction Technical Letters (CTL), MAJCOM policies and corrections as required.

7.1.1. Copies of AF publications can be obtained from the Air Force publishing website at http://www.e-publishing.af.mil.

7.1.2. The Unified Facilities Criteria (UFC), http://65.204.17.188/report/doc_ufc.html, shall be used for all service projects.

The UFC, as prescribed by MIL-STD 3007, provides planning, design, construction, sustainment, restoration and modernization criteria and applies to the Military Departments, the Defense Agencies and the DoD Field Activities in accordance with USD (AT&L) Memorandum dated 29 May 2002. UFC are distributed only in electric media and are effective upon issuance.

7.1.3. The contractor is responsible for obtaining copies of these publications and other related documents for reference:

7.1.4. UFC Index

7.1.4.1.http://www.afcee.brooks.af.mil/dc/products/dcproducts.asp#dcd 7.1.4.2.http://www.afcesa.af.mil/library/ 7.1.4.3.http://65.204.17.188/report/doc_ufgs.html 7.1.4.4.http://www.wbdg.org/ccb/

7.2.Industry Codes & Standards: Applicable Codes and Standards shall include, but not be limited to, all pertinent requirements of the following organizations most current standards:

7.2.1. API – American Petroleum Institute

7.2.2. NFPA – National Fire Protection Association

7.2.3. UL – Underwriters Laboratory, Inc.

7.2.4. ASTM – American Society for Testing and Materials

7.2.5. ACI – American Concrete Institute

7.2.6. ANSI – American National Standard Institute

7.2.7. AIEE – American Institute of Electrical Engineers

7.2.8. ASME – American Society of Mechanical Engineers

7.2.9. CRSI – Concrete Reinforcing Steel Institute

7.2.10. IPCEA – Insulated Power Cable Engineers Association

7.2.11. NBS – National Bureau of Standards

7.2.12. IEEE – Institute of Electrical and Electronic Engineers, Inc.

7.2.13. NEC – National Electric Code

http://www.e-publishing.af.mil/ http://65.204.17.188/report/doc_ufc.html http://www.afcee.brooks.af.mil/dc/products/dcproducts.asp#dcd http://www.afcesa.af.mil/library/ http://65.204.17.188/report/doc_ufgs.html http://www.wbdg.org/ccb/

7.2.14. NBFU – National Bureau of Fire Underwriters

7.2.15. NEMA – National Electric Manufacturers Association

7.2.16. OSHA – Occupational Safety and Health Administration

7.2.17. NAPHCC – National Association of Plumbing – Heating – Cooling

Contractors

7.2.18. National Standard Plumbing Code

7.2.19. ARI – Air Conditioning and Refrigeration Institute

7.2.20. ASHRAE – American Society of Heating, Refrigeration and Air-Conditioning

Engineers

7.2.21. AMCA – Air Movement and Control Association

7.2.22. NRCA – National Roofing Contractors Association

7.2.23. NJDOT – Standard Specifications for Road and Bridge Construction – New

Jersey Department of Transportation

7.2.24. UFC - Unified Facilities Criteria

8. WORK WEEK AND HOURS OF OPERATION: Civil Engineering workweek is

Monday through Friday, 0700 to 1530. The Contractor shall make arrangements in advance to work outside of normal duty hours.

9. PROJECT DURATION: Duration of this project is 150 calendar days After Date of

Contact Award. On-site Performance is STRICTLY limited to a 30 continuous calendar day period between the dates of June 1, 2024, and August 7, 2024. These dates and Period of Performance are mandatory and will NOT be waived. The contractor will NOT be given to authority to mobilize until ALL Pre-Mobilization requirements have been met.

9.1. New Year’s Day - 1 January

9.2. Martin Luther King’s Birthday - Third Monday of January

9.3. President’s Day - Third Monday of February

9.4. Memorial Day - Last Monday of May

9.5. Juneteenth – 19 June

9.6. Independence Day - 4 July

9.7. Labor Day - First Monday in September

9.8. Columbus Day - Second Monday in October

9.9. Veteran’s Day - 11 November

9.10. Thanksgiving Day - Fourth Thursday in November

9.11. Christmas Day - 25 December

9.12. NOTE: Base Scheduled Day Off (SDO)

9.12.1. If the Federal holiday occurs on a Monday; the base will observe an SDO and be closed the following Tuesday in addition to the Federal Holiday.

9.12.2. Contractors will NOT have access to the base on the Tuesday SDO.

10. TRASH DISPOSAL AND CLEAN-UP: It is the Contractor`s responsibility to dispose of all trash and debris incurred during project construction, off base at an authorized disposal site in accordance with local, state and federal requirements. Contractor shall employ stringent housekeeping standards and ensure the project site is maintained in a clean and orderly condition.

10.1. Airfield Work: The project site is on or near an active military airfield.

Cleanliness in the flightline areas is critical. Foreign Object Debris (FOD) and/or loose objects shall be secured and controlled as they might cause serious injuries or damages to the aircraft. FOD is any foreign object on the airfield to include tools, hardware, stones, and construction debris.

11. ENVIROMENTAL IMPACT: Contractor shall adhere to all applicable Federal, State and Local Regulations.

11.1. Collections of waste shall be disposed of properly IAW State and Federal

Regulations including proper manifesting and tracking.

11.2. Under NO CIRCUMSTANCES shall any waste materials, cleaning fluids, solvents, paints, etc. be poured into the base storm drains, sanitary sewer systems, or discharged onto the ground.

11.3. All materials on the job shall be accompanied by a SDS (Safety Data Sheet).

11.4. All containers shall be marked clearly and legibly as to the contents inside.

11.5. All containers shall have lids firmly affixed and stored in accordance with the manufacturers written instructions.

11.6. Provide the Contracting Officer with the quantities of all recycled materials discarded such as metals, concrete, etc.

11.6.1. Recycling slips shall be submitted in Projectmates.

12. HAZMAT REPORTING: (ref. FAR 23.3; FAR52.232-2; & DFARS 252.223-7001)

12.1. The contactor shall submit anticipated amounts of all HAZMAT material to be used on the project to the Government in Projectmates. Submission of anticipated amounts shall include the Safety Data Sheet (SDS) in accordance with FAR 52.232-2.

12.2. The anticipated amounts shall be updated at project completion to indicate actual quantity consumed on the project of each identified HAZMT material.

12.3. HAZMAT Reporting Requirement will be reviewed at the bi-weekly Progress Meetings.

12.4. Hazardous material is defined in the latest version of Federal Standard No.313.

(ref: FAR 23.301)

13. ANTI-TERRORISM AND OPERATIONAL SECURITY (ATOPSEC)

Access and General Protection/Security Policy and Procedures. (This standard language is for contractor employees with an area of performance within Government controlled installation, facility, or area.)

13.1. Access and General Protection/Security Policy and Procedures. This standard language is for contractor employees with an area of performance within Government controlled installation, facility, or area. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services or local Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, HAF and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.

13.2. For Contractors that do not require CAC, but require access to a DoD Facility and/or Installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (AFI 31-101 and AFI 10-245), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

14. BENEFICIAL OCCUPANCY PRIOR TO COMPLETION: (ref: FAR 52.236-11 Use & Possession Prior to Completion)

14.1. At the project milestone in which the project may be used for its intended purpose or to meet critical mission requirements, the Government may assume beneficial occupancy in accordance with the above FAR clause.

14.1.1. Prior to the Government taking possession of any portion of the project or system; the Contacting Officer shall provide the Contractor with a Letter of Beneficial Occupancy stating the date and the portion of the project that the Government is intending use for beneficial occupancy.

14.2. The Government shall have the right to take possession of or use any completed or partially completed part of the work. Before taking possession of or using any work, the Contracting Officer shall furnish the Contractor a list of items of work remaining to be performed or corrected on those portions of the work that the Government intends to take possession of or use. Failure of the Contracting Officer to list any item of work shall not relieve the Contractor of responsibility for complying with the terms of the contract. The Government’s possession or use shall not be deemed an acceptance of any work under the contract.

15. FINAL ACCEPTANCE AND COMPLETION: When the project is completed, the Contractor shall notify the Contracting Officer and make arrangements for a Final Inspection. The project WILL NOT be accepted by the Government and Final Payment made until:

15.1. Close-Out Documentation: The Government has received and reviewed all Test

Reports, Equipment Start-Up Reports, Commissioning Reports, Close-Out Information, Manufactures & Installers warranty paperwork, Contractors Warranty (ref: FAR 52.246-21), Attic Stock, and Release of Liens.

15.2. DD Form 1354, Transfer & Acceptance of DOD Real Property: Contractor shall submit DD Form 1354 data in accordance with UFC1-300-08 Criteria for Transfer & Acceptance of DoD Real Property.

15.2.1 The DD Form 1354 is an instrument used to accept new construction or capital improvements, to transfer real property assets between Services, or to document inventory adjustment (found on site) assets into the real property inventory. The form is part of the lifecycle of real property asset accountability business processes that crosses communities such as planning, programming, construction, contracting and real estate.

15.2.2 The contactor will receive a Draft 1354 with anticipated Category Codes and quantities at time of contract award.

15.2.3 It shall be the contractor’s responsibility to provide actual quantities and values of the installed systems to the Government.

15.3. Restoration: The entire project site and Government facilities are returned to original or better condition according to applicable codes and standards.