Att_2_140P8425Q0004_SOW.pdf
PDF 358 KB Posted
- Attached to
- Crystal Creek Camp Demolition, NPS-WHIS
- Solicitation number
- 140P8425Q0004
About this file
This is a Statement of Work (SOW) for the demolition of Crystal Creek Camp at Whiskeytown National Recreation Area in California. The project involves demolishing obsolete facilities and partially restoring the site to natural conditions, including removal of buildings, infrastructure, and site features.
The SOW details requirements across multiple areas: demolition of existing buildings (including proper handling of asbestos-containing materials in at least one building), well abandonment, site grading and restoration, and environmental protection measures. Key technical requirements include implementing erosion control measures, following specific procedures for hazardous material handling, conducting a final site survey, and complying with bat protection protocols between April 1-August 31 for buildings 914 and 915. The work is divided into five contract line items: mobilization/demobilization, hazardous waste abatement, well abandonment, site demolition/abandonment, and site grading/restoration. The contractor must obtain necessary permits, provide quality control, and follow strict environmental protection guidelines including development of an Under-an-Acre Pollution Prevention Plan. The SOW also requires specialized contractors for certain elements like well abandonment (requiring California Class C-57 license) and asbestos abatement.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WHISKEYTOWN
NATIONAL RECREATION AREA
DEMOLISH CRYSTAL CREEK CAMP
PMIS No. 319078
STATEMENT OF WORK
Solicitation #
NATIONAL PARK SERVICE
PACIFIC WEST REGION
November 20, 2024
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
Part 1 01 11 00 Summary of Work Part 2 01 27 00 Definition of Contract Line Items Part 3 01 31 00 Project Management & Coordination Part 4 01 32 16 Work Schedule Part 5 01 33 23 Submittal Procedures Part 6 01 35 25 Safety Requirements Part 7 01 40 00 Quality Requirements Part 8 01 50 00 Temporary Facilities & Controls Part 9 01 57 23 Under-an-Acre Pollution Prevention Plan Part 10 01 71 13 Mobilization / Demobilization Part 11 01 73 40 Execution Part 12 01 74 19 Waste Management and Disposal Part 13 01 78 29 Final Site Survey Part 14 01 77 00 Closeout Procedures
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition
DIVISION 31 – EARTHWORK
31 10 10 Site Clearing 31 22 10 Topsoiling & Finish Grading 31 22 13 Rough Grading 31 23 23 Flowable Fill 31 25 00 Erosion Control Products 31 11 13 Well Abandonment
Appendices
A County Well Records (x2) B State Water Board Tank Closure Record C Bridge Inspection Report D CCC Building Complex Plans E RFI Form F CM16 Transmittal Form G QC Daily Inspection Form
DIVISION 01
GENERAL REQUIREMENTS
WHIS 319078 Division 1 Demo Crystal Creek Camp
DIVISION 1 PROJECT GENERAL REQUIREMENTS
PART 1 SUMMARY OF WORK (Section 01 11 00)
1.1 PROJECT OVERVIEW
Crystal Creek Camp was originally constructed by the California Department of Forestry and Fire Pro-tection originally to house inmate firefighters. It was closed in 1993 and reopened two years later as an adult work camp and latterly as a juvenile detention facility know as Crystal Creek Boys Camp. The camp was closed in 2009 and the site transferred to the National Park Service as is.
This project demolishes the obsolete facilities and partially restores the site to natural conditions.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
Project Location: The project is located at Whiskeytown National Recreation Area, on the west side of the park, near the Crystal Creek Falls Trailhead. Access to the site is via Crystal Creek Road. Project coordinates are Lat. 40°38’3.92”N, Long. 122° 40’36.05”W
The Work consists of demolishing existing buildings, infrastructure, site features, debris removal, rough site grading, erosion and sediment control, and general site clean-up. Buildings are wood or steel framed.
Asbestos containing materials are known to exist in at least one building. See drawings for further information.
1.3 SCOPE
The Contractor shall furnish all materials, equipment, and personnel necessary to manage and accomplish the work. The Contractor shall provide sufficient technical support and project management to assure quality, accuracy of estimates, and timely completion of the project according to delivery requirements.
The Government will rely on the Contractor's expertise in recognizing and addressing problematic issues and successful execution of the work. It is the Government's clear expectation that projects executed against this contract shall exhibit superior quality, responsiveness, and customer service.
A. The Contractor's work responsibility shall include all contractor planning, programming, administration, coordination, and management necessary to provide all work as specified. The work shall be conducted by the Contractor in strict accordance with the contract and all applicable Tribal, Federal, State, and local laws, regulations, codes, or directives. The Contractor shall ensure that all work provided meets or exceeds critical reliability rates or tolerances specified or included in applicable documents. The Contractor shall provide related services such as pre-award project development, project management, quality control (QC), preparation, review, and submission of required deliverables, environmental permits, along with other administrative work required to satisfy the requirements specified under this contract.
Government-Furnished Materials: None
B. Environmental protection: Work shall include protection of the natural environment with all means necessary, including measures required by the Government and Contractor’s best management practices. To minimize environmental impact, work activity shall be limited to a small allowable work area and shall require submittal of an Under an acre Pollution Prevention Plan and adherence to the plan.
1.4 REFERENCE DOCUMENTS
The following documents /reports are attached to supplement the information in the drawings and specifications:
A. County Well Records (x2) B. State Water Board Tank Closure Record C. Bridge Inspection Report D. CCC Building Complex Plans
1.5 CONTRACTOR USE OF SITE
General: Contractor shall have full use of the site for work operations during the work period. Contractor's use of the site is limited only by the Government's right to perform work or to retain other contractors on portions of Project.
Staging and Storage or Stockpiling of Materials: Confine storage of materials to project site. Contractor may fence a portion of the site to secure equipment, tools, etc. including areas around containers and material storage.
Parking: Confine parking to the project site.
Waste Management: Work debris and stormwater generated by the work shall be fully contained and controlled at all times so as to not run off into the surrounding natural environment. An UPPP detailing the plan shall be developed and submitted for approval before any work begins.
Property Damage: The Contractor is required to report missing, lost, stolen, or damaged property occurring within the park. This report must be made to a Law Enforcement Ranger or WHIS Park Dispatch at the first available opportunity at (530) 242-3431.
Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government employees, and emergency vehicles at all times. Do not use for parking or storage of materials.
Work Camp: Establishment of a camp within park will not be permitted.
Hauling Restrictions: Comply with legal load restrictions in hauling of materials. Load restrictions on park roads are identical to state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government. If damage occurs to an unknown utility, notify the C.O. and await further direction.
Bridge Restrictions: Identify jurisdictions, load restrictions, permit requirements, time and calendar restrictions as outlined.
A. The bridge at the entrance to the camp is part of the camp infrastructure. The bridge was essentially abandoned in 2009 when the camp closed. The bridge is no longer open to the public. The bridge is not maintained and has not received routine inspections. The NPS has used the bridge occasionally, and fully loaded waste removal vehicles have used the bridge in recent years. The NPS makes no representation as to the overall rating and/or integrity of the bridge.
B. A copy of the most recent bridge inspection report is attached for reference.
1.6 PUBLIC USE OF SITE
The area is currently closed to the public and will remain closed during work.
1.7 CONDUCT OF OPERATIONS
Contractor shall conduct his operations in conformance with rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by Park Superintendent. Any exception must be specifically justified and approved in writing by the Contracting Officer. The Superintendent’s Compendium can be found at:
https://www.nps.gov/whis/learn/management/superintendent-s-compendium.htm
Park Regulations: Ensure all personnel (contractors, subcontractors, and vendors) entering or working in the park are familiar with and obey all park regulations. Law enforcement rangers will intervene if they perceive any unsafe or unlawful activity.
No signs or advertisements (except those specified herein) shall be displayed on the work site or within the park unless approved by the Contracting Officer.
1.8 WORK RESTRICTIONS
On-Site Work Hours: Work shall be generally performed during normal business working hours of 7a.m.
to 6 p.m., Monday through Friday, except when otherwise indicated.
1. Weekend Hours: Not allowed
2. Early Morning Hours: Not allowed
Nonsmoking Building/Tobacco Use/Vaping: Smoking and tobacco use is not permitted at this site.
Work on Saturdays, Sundays, Federal holidays or at night may not be performed unless stated in the Work Restrictions below or without prior consent from the Contracting Officer. Submit requests 2 business/calendar days in advance of the work to the Contracting Officer for approval.
Resource Protection:
1. General: The Park is committed to protecting natural and cultural resources found within the park and adjacent lands. The Contractor must comply with the following rules and conditions:
2. Preservation of Natural Features: Prevent damage to natural surroundings. Do not at-tach ropes, wires, guy lines, cables, or chains to trees or vegetation. Restore damaged areas and replace damaged trees, vegetation, and grass at no expense to the government.
Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer (CO) and remove agreed-on roots and branches that interfere with work. Do not fasten ropes, cables, or guys to existing trees. Carefully supervise excavating, grading, filling, and other work operations near trees to prevent damage.
3. Invasive Species: The introduction of non-native invasive species can threaten rare and endangered species or can create new populations of non-native species not traditionally found in the park. The contractor is required to inform personnel, subcontractors, and vendors to thoroughly clean all vehicles (especially the tires), equipment, tools, supplies, and materials prior to packing / loading. The Park requires and will perform inspections to prevent transport of non-native species PRIOR to arriving at the park entrance. Con-tact the Equipment Inspector at least (3) three days in advance of park entry to arrange for inspection(s) at the loading dock or point of origin.
4. Endangered Species: Endangered species are protected by Federal law. Obey all park regulations. Drivers must obey all traffic laws and watch for animals on or alongside road or at the jobsite. Contact Park Dispatch at (530) 242-3431 immediately if animal is hit or injured or will not move off the road. The following measures are required to min-imize disturbance to endangered wildlife:
a. Work shall be conducted to ensure the work area is cleaned up at the end of each work shift so that loose tools, debris, and materials are not left out in a manner that could present a hazard to a listed species.
b. Noise and vibrations of equipment shall be kept to a minimum when working in the vicinity of a listed species.
c. Hazmat spill prevention protocols shall be employed when using gas-powered equipment.
d. Tarps shall be used to contain all paint chips and building debris from exterior sur-faces that may fall to the ground.
e. Ensure loose nails and screws are collected each day with a magnet or other meth-ods.
5. Bat Restrictions: Avoid all work at buildings 914 and 915 and adjacent infrastruc-ture during the bat maternity season between April 1 and August 31. Outside of this season, a pre-demolition bat survey by a qualified bat biologist (provided by NPS) is re-quired immediately prior to removal of these buildings to ensure that roosting bats are not present in the buildings at the time of demolition. If bats are using them and it is out-side of the maternity season, bat exclusion measures on the buildings will be implemented by NPS and no work may be performed for a minimum of 3 days thereaf-ter on these buildings. NPS requires a minimum of 30 days notification of proposed work on Buildings 914 and 915 to arrange and conduct bat surveys.
PART 2 – DEFINITION OF CONTRACT LINE ITEMS (SECTION 01 27 00)
2.1 Contract Line Item Number 0001: Mobilization and Demobilization
1. This item consists of all preparatory work and operations for all items under the contract, including, but not limited to those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site and all other work or operations which shall be performed, or costs incurred prior to beginning work on the various items on the project site.
2. This item also includes permits and demobilization cost.
3. Measurement for payment shall be on a lump sum basis.
4. Payment will be made at the contract lump sum price.
2.2 Contract Line Item Number 0002: Hazardous Waste Abatement
1. This line item is intended to cover all removal and disposal of known hazardous waste in accordance with state rules and regulations. Known hazardous wastes include ACM (Asbestos Siding) on building 914 and an above ground septic tank that is believed to be partially full.
2. This pay item includes the removal and disposal of an incidental amount of freon, PCBs, lubricants, and mercury that may be found on site contained within common equipment.
While there are no known occurrences of these products on site, small amounts of these products may be discovered in common applications such as HVAC equipment, light bulbs, ballasts, and electrical transformers. If discovered, these items will require additional handling and disposal. For bidding purposes, assume that the total quantity of these materials is less than 10 pounds.
3. The plan set identifies an existing propane tank as a potential hazard. The propane tank has been emptied. While it is identified as a potential hazard, there is no anticipated waste abatement associated with it.
4. The plan set identifies two potential underground storage tanks. To the best of the NPS’s knowledge these tanks have either been removed, are empty, and/or may have never contained fuel. The NPS located a record from 1995 indicating that a tank had been removed from the site. The NPS believes that this tank was located in front of building 902, but the area has since been paved over. This bid item only covers the testing of materials for identification purposes in the unlikely event that any potentially hazardous wastes associated with underground tanks are discovered. For example, if the contractor were to smell fuel while excavating, the expectation would be that a sample is collected so that the waste could be identified. The NPS does not expect the contractor to remove stored fuel products and/or conduct any site investigation, remediation, or monitoring associated with any potential stored fuel products, spills, or leaks. In the unlikely event that an underground tank is found (either full or leaking) the NPS will coordinate with the appropriate regulatory agencies, conduct a site evaluation, and develop a remediation plan. Should any follow-on work be required it will be addressed through a contract modification, or through a separate contract as appropriate. For bidding purposes assume that two samples will be collected. Empty tanks with no indication of contamination will be removed as regular demolition waste.
5. Measurement for payment shall be on a lump sum basis.
6. Payment will be made at the contract lump sum price.
2.3 Contract Line Item Number 0003: Well Abandonment
1. This item consists of all work and materials required to properly abandon the existing water well in accordance with specification 331113.
2. This line item is only intended to cover the abandonment of the single known well located on site. If additional well(s) are located the cost for abandonment shall be via contract modification.
3. The contractor shall obtain and pay all permitting fees.
4. Measurement for payment shall be on a lump sum basis.
5. Payment will be made at the contract lump sum price.
2.4 Contract Line Item Number 0004: Site Demolition and Abandonment
1. This item consists of furnishing all labor equipment and materials to demolish and dispose of existing site features in accordance with the requirements set forth in the project plans and specifications. This item includes but is not limited to demolishing the existing buildings, foundation, architectural features, pavements, retaining walls, utilities, equipment, rubbish, and other ancillary items as shown in the plans.
2. This item does not include the demolition of hazardous wastes or well abandonment which typically require specialized licensing and may be accomplished under one or more sub-contracts.
3. Measurement for payment will be on a lump sum basis.
4. Payment will be made at the contract lump sum price.
2.5 Contract Line Item Number 0005: Site Grading and Restoration
1. This item consists of furnish all materials, labor, and equipment to complete the rough site grading and final site restoration as shown in the plans.
2. This item also includes tree & vegetation removal, tree grinding, mulching, and the furnishing and installation of all erosion control products such as fiber rolls and erosion control matting.
3. This item also includes the filling of designated tanks with sand or flowable fill according to the plans.
4. Measurement for payment will be on a lump sum basis.
5. Payment will be made at the contract lump sum price.
PART 3 – PROJECT MANAGEMENT AND COORDINATION (SECTION 01 31 00)
3.1 SUBMITTALS
A. Submittal Documents: The following documents shall be submitted a minimum of one week prior to the Pre-Service Meeting. If all of these documents have not been received one week prior to the scheduled Pre-Service Meeting date, the meeting will be cancelled and work will not be allowed to commence. Work shall not commence until written approval is received from the CO.
1. Schedule - Submit a baseline schedule with start date, end date, major work activities and durations, estimated pre-final inspection date, and other major milestones. Provide updates to baseline schedule as needed / requested during work.
2. Pay Schedule - Submit a pay schedule with a breakdown of component work activities for which progress payments will be requested. The total costs for the component work activities shall equal the total contract price.
3. Site Specific Safety Plan – provide a Site-Specific Safety Plan that will ensure that the procedures, methods and materials used in this removal and installation are compliant with OSHA standards and best practices for employee and site safety. This plan must include name of responsible on-site supervisor, first-aid procedures, outline of each phase of the work, and the hazards associated with each major phase, methods proposed to ensure property protection and safety of the public and planning for potential emer-gency situations.
4. Licenses and Certificates – Contractor is required to have an active California Contractor License. Provide a copy of all active California Contractor Licenses and Certifications for prime contractor and any subcontractors.
5. Satisfactory evidence of liability insurance coverage and workman’s compensation for the
Contactor and all subcontractors.
B. The following documents shall be submitted to the COR one week prior to the Pre-Service
Meeting. If these documents have not been received and approved by the NPS prior to the start of work, the start date may be delayed.
1. Schedule
2. Accident Prevention Plan
3. Waste Management Plan
4. Quality Control Plan
5. Under an Acre Storm Water Pollution Prevention Plan (UPPP)
6. List of Required Work Permits. Include the following information for each permit:
a. Name of Permit
b. Agency(ies) with Jurisdiction issuing the permit
c. Information required from Government to complete permit application
3.3 PRE-SERVICE MEETING
A. Pre-Service Meeting: Before the start of work, the COR will arrange for a pre-service meeting work to discuss project logistics, approved UPPP, etc.
3.4 ENVIRONMENTAL COORDINATION
A. Contractor’s Environmental Manager: Designate on-site party responsible for overseeing Contractor’s conformance to environmental goals for project and implementing procedures for environmental protection.
B. Perform project quality control in accordance with requirements specified in Related Sections, including:
1. Quality Requirements
2. Regulatory Requirements
3. Storm Water Pollution Prevention Environnemental Management
4. Waste Management
3.4 PERMITS
A. General:
1. Permits and Responsibilities: Contractor shall, without additional expense to the Government, be responsible for obtaining necessary licenses and permits, and for complying with Federal, State and municipal laws, codes, and regulations applicable to the performance of the work.
Contractor shall also be responsible for damages to persons or property that occur as a result of Contractor’s fault or negligence; and for materials delivered and work performed until completion and acceptance of the work.
2. For the purpose of this contract, Contractor will not be considered an agent of the Government.
Contractor shall comply with appropriate Federal, State and local laws.
B. Potential Permits: Permits listed below were identified during the design process as likely to be required based on typical means and methods of work. The list is provided to assist Contractor in determining which permits will be required for contract’s chosen means and methods. The list shall not be considered complete; it is the Contractors’ responsibility to determine means and methods and obtain required permits. Contractor shall obtain all permits required to legally conduct work.
1. Filing well abandonment paperwork with the state and county.
C. Coordination with Agency(ies) with Jurisdiction Issuing Permits: Contact the Agency(ies) with Jurisdiction as needed and sufficiently in advance to avoid delaying work: Coordinate meetings, reporting requirements, inspections, and other requirements.
D. Administrative Procedures:
1. Coordinate scheduling and timing of required administrative provisions of project permits with Agency(ies) with Jurisdiction, Work Manager, and Park to avoid conflicts.
2. Supply needed information to Agency(ies) with Jurisdiction issuing permits, pay fees required and provide material needed to comply with permit’s conditions and provisions.
PART 4 – SCHEDULE (SECTION 01 32 16)
5.1 SCHEDULE
A. Purpose: The Schedule ensures adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. It shall assist the Contractor and Contracting
Officer (CO) in monitoring the progress of the work, evaluating proposed changes, and processing Contractor's monthly progress payments. It shall include the dates in the contract, phases, milestones, occupancies, holidays, weather consideration, a critical path, and the requirements of this section. controlling the project. Activities included in a schedule consume time and resources.
1. Critical activities are activities on the critical path. They start and finish on the planned early start and finish times.
2. Predecessor Activity: An activity that precedes another activity in the network.
3. Successor Activity: An activity that follows another activity in the network.
4. Cost Loading: Allocation of the Payment Schedule for completion of an activity as scheduled. The sum of costs for all activities must equal the total Contract Sum, unless otherwise approved by the Contracting Officer.
5. Critical Path Method (CPM): Method of planning and scheduling a project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.
6. Critical Path: Longest connected chain of interdependent activities through the network schedule that establishes minimum overall Project duration.
7. Resource Loading: Allocation of manpower and equipment necessary for completion of an activity as scheduled.
8. Activity Report: List of activities sorted by activity number and then early start date, or actual start date if known.
9. Logic Report: List of predecessor and successor tasks for activities sorted in ascending order by activity number and then early start date, or actual start date if known.
B. SUBMITTALS
1. Electronic Copies: Schedules and reports submitted shall be emailed to the Contracting Officer and Contracting Officer’s Representative in native electronic file formats. The intent of the Government is to limit the number of printed reports to those determined by the project team as essential.
2. Payment Schedule: After contract award and before the Pre-Service Meeting, submit a schedule of dollar values based on the contract price schedule.
3. Schedule: After contract award and before the Pre-Service Meeting, submit baseline schedule, large enough to show entire schedule for entire work period. Utilize Payment Schedule in preparation of schedule.
PART 6 – SAFETY REQUIREMENTS (SECTION 01 35 23)
6.1 SUBMITTALS
A. Accident Prevention Plan (APP): Submit APP after contract award and before Pre-Service Meet-ing. Contracting Officer (CO) will review proposed APP. If APP requires any revisions or corrections, Contractor shall resubmit Plan within 10 days. No progress payments will be made until the APP is accepted.
B. Site Safety Supervisor:
1. Designate authorized onsite representative for preparation and maintenance of the APP.
2. Shall be responsible for:
a. Implementation and enforcement of the APP
b. Daily safety inspections
c. Conducting and documenting weekly and monthly safety meetings
d. Review of safety requirements at progress meetings
e. Compilation and maintenance of Safety Data Sheets (SDS) and safety reference materials
f. Tracking and resolution of safety violations
g. Site personnel and visitor compliance with site safety and health requirements and APP
h. Investigation and reporting of accidents and injuries
C. Qualifications of Employees:
1. Physically and able to perform their assigned duties in a safe manner.
2. Do not allow employees whose ability or alertness is impaired because of prescription or illegal drug use, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury to perform work.
3. Provide operating instructions for equipment. Operators of vehicles, hoisting equipment, and hazardous plant equipment shall be able to understand signs, signals, operating instructions, and be fully capable of operating such equipment. Retain copies of operator licenses and certifications onsite.
D. ACCIDENT REPORTING
1. Reportable Accidents: Defined as: death, occupational disease, and/or traumatic injury to employees or the public; fires; and/or property damage by accident in excess of $100.
a. Notify Contracting Officer immediately in the event of a reportable accident.
b. Fill out and forward an Accident/Property Damage Report Form (CM-22) to Contracting Officer within 7 days of a reportable accident. Obtain form from Contracting Officer.
E. ACCIDENT PREVENTION PLAN (APP)
1. APP shall be written to comply with OSHA and project requirements (generic plan is not acceptable) including but not limited to:
a. Name and qualifications of supervisor responsible to carry out program.
b. Weekly and monthly safety meetings shall be documented with topics and attendees.
c. First aid and rescue procedures.
d. Job Hazard Analysis (JHA) for each major phase. List of associated hazards and methods proposed to provide for property protection and safety of the public, National Park Service personnel, and Contractor's employees. Include initial and continuing training.
e. Planning for possible emergency situations, as detailed in Article 1.2. Such planning shall take nature of work, site conditions, and degree of exposure of persons and property into consideration.
f. Infectious Disease Preparedness:
1. Contractors are responsible for their employees’ safety and the safety of job site visitors during the performance of this contract. We encourage Contractors to follow guidance from the Department of Labor (DOL), Occupational Safety and Health Administration (OSHA), the Centers for Disease Control and Prevention (CDC), and all other applicable local, city, and state mandates. We encourage Contractors to develop policies for infection prevention and an Infectious Disease Preparedness and Response Plan.
2. To the extent appropriate, Contractors should include the protective health and safety measures they intend to implement in any accident prevention or safety submittals required under this contract. These plans should contain preventive measures the Contractor intends to follow while performing work on government property as well as responsive and corrective actions to be taken if an employee exhibits symptoms or tests positive for contagion.
3. Upon contract award, Contractors should communicate with Contracting Officer regarding Contractor decisions and actions to protect the health and safety of workers for the duration of contract performance under which pandemic conditions exist.
6.2 SAFETY REQUIREMENTS
A. First Aid Equipment: Provide adequate first aid equipment for all contract employees and the hazards associated with the types of ongoing work at the site.
B. First Aid Training: Provide adequate training to all Contractor personnel to ensure prompt and efficient application of first aid.
C. Personal Protective Equipment (PPE): Provide personal protective equipment (PPE) that meets applicable OSHA and ANSI standards for all contract employees.
D. Hazardous Materials: Hazardous materials are defined as explosive, flammable, poisonous, cor-rosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury.
Store hazardous materials in accordance with manufacturers and OSHA recommendations.
Maintain MSDS onsite for each chemical used on the jobsite. Immediately report all spills of hazardous materials to the COR.
E. Safety Meetings: At a minimum, conduct weekly "toolbox" safety meetings. These meetings shall be conducted by a foreman or supervisor and attended by all personnel at the worksite.
Topics need to coincide with work scheduled for the week.
F. Emergency Contacts: Post telephone numbers and reporting instructions for ambulance, hospi-tal, fire department, police, and park dispatch in conspicuous locations at the site.
G. Emergency Reporting: In the event of an emergency medical incident, the Contractor shall Dial 911 as needed. The Contractor shall also contact Park Dispatch at (415) 561-4700 for any med-ical emergency, traffic accident, or personal injury occurring within the Park. Park Dispatch is called so that the entrance station will be prepared should any emergency vehicles need to enter the Park and so that any available Emergency Medical Services personnel in the Park might respond until such time as the ambulance arrives.
H. HARD HATS AND PROTECTIVE EQUIPMENT AREAS
i. A hard hat use area shall be designated by Contractor. Hard hat area shall be posted by Contractor in a manner satisfactory to Contracting Officer.
ii. It is Contractor's responsibility to require persons working on or visiting site to wear hard hats and PPE in good repair at all times. As a minimum, maintain two hard hats and other APP required equipment.
I. Hazardous Material: Train and instruct each employee exposed to hazardous material in safe and approved methods of handling and storage.
PART 7 – QUALITY REQUIREMENTS (SECTION 01 40 00)
7.1 QUALITY REQUIREMENTS
A. General: The Contractor is responsible for all quality control to guard against defects and deficiencies in the work. Inspect and test work as needed to ensure that the quality of materials, workmanship, finishes, and functional performance are in compliance with applicable specifications, drawings, building codes and standards.
PART 8 – TEMPORARY FACILITIES & CONTROLS (SECTION 01 50 00)
8.1 TEMPORARY FACILITIES & CONTROLS
A. General: The contractor will be allowed to set up temporary facilities and controls. These items should be discussed at the pre-work meeting, if needed. All temporary facilities and controls shall be removed from the site before final acceptance of the work. The contractor should secure the site to prevent public access and reduce theft and vandalism.
B. Temporary Utilities: The following utilities / services are available for use at the project site:
1. Electrical Power Service: Electrical power is not available at the site. The contractor may use battery powered tools or furnish portable generators with proper fuel containment and emergency spill kits.
2. Water Service: No water, either potable or non-potable, is available at the site. No drafting from the creek is allowed.
B. Sanitary Facilities: Restrooms are not available at the site. Provide temporary toilets, and wash facilities for use by personnel.
1. Place in approved locations secluded from public observation and convenient to work stations. Relocate as work progress requires.
2. Maintain and clean toilet facilities at least weekly.
3. Completely remove sanitary facilities on completion of work.
C. Telephone Cellular Service: The project site has limited cellular service availability.
D. Temporary Office: The set up of temporary office trailers will be allowed within the project site only. Locate facilities to limit site disturbance and as directed by the Contracting Officer.
E. Temporary Enclosures: If necessary, the contractor shall construct an enclosure fence, barrier, or partition to prevent people and animals from entering the project site except by gates / doors.
F. Temporary Traffic Controls: If traffic flow is to be impeded, the contractor shall erect and maintain barricades, danger signals, and warning signs in accordance with the Manual on Uniform Traffic Control Devices (MUTCD), 2009 edition. Maintain access for fire-fighting and emergency vehicles and equipment. The contractor shall provide adequate traffic control, including flaggers on either side of any work performed in the road. Any workers on or near the road must wear highly visible, bright clothing.
G. Temporary materials may be new or used, but must be adequate in capacity for required usage, must not create unsafe conditions, and must not violate requirements of applicable codes and standards.
H. Waste Disposal Facilities: Provide waste-collection containers in sizes adequate to handle waste from work operations. Comply with requirements of agency(ies) with jurisdiction.
I. Lifts and Hoists: Provide facilities necessary for hoisting materials and personnel.
1. Truck cranes and similar devices used for hoisting materials are considered "tools and equipment" and not temporary facilities.
J. Environmental Protection: Provide protection, operate temporary facilities, and conduct work in ways and by methods that comply with environmental regulations and minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.
K. Cleaning of Equipment: Contractor shall ensure prior to moving on to Project Area, equipment, is free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds. Ensure equipment has been pressure washed and is free of exotic species. Equipment shall be considered free of soil, seeds, and other debris when visual inspection does not disclose such material. Disassembly of equipment components or specialized inspection tools are not required. Equipment shall be inspected each time it arrives in the park. The inspection location will be just outside the park at a site to be determined.
L. Pest Control: Follow NPS requirements to minimize attraction and harboring of rodents, roaches, and other pests and perform extermination and control procedures at regular intervals so Project will be free of pests and residues at Substantial Completion. Perform control operations lawfully, using environmentally safe materials.
M. Security Enclosure and Lockup: Install substantial temporary enclosure around partially completed areas of work. Provide lockable entrances to prevent unauthorized entrance, vandalism, theft, and similar violations of security.
N. Termination and Removal: Remove each temporary facility when need for its service has ended, when it has been replaced by authorized use of a permanent facility, or no later than Substantial Completion. Complete or, if necessary, restore permanent work that may have been delayed because of interference with temporary facility. Repair damaged Work, clean exposed surfaces, and replace work that cannot be satisfactorily repaired.
PART 9 – UNDER AN ACRE POLLUTION PREVENTION (SECTION 01 57 23)
9.1 SUMMARY
A. NPS Standards and Guidelines require that water quality be protected at all times to ensure compliance with the Organic Act. The Contractor must prepare an Under-An-Acre Pollution Prevention Plan (UPPP) for each project resulting in less than 1 acre of soil disturbance or not otherwise subject to the requirements of the NPDES program. (UPPP Guideline)
B. The work of this section consists of implementing measures to prevent discharges of pollutants, including temporary storm water pollution during work activities, either through compliance with NPDES permit program, or in conformance with NPS guidance for UPPPs.
9.2 DEFINITIONS
A. Environmental Pollution and Damage: The presence of chemical, physical, or biological elements or agents which adversely affect human health or welfare; unfavorably alter ecological balances; or degrade the utility of the environment for aesthetic, cultural, or historical purposes.
B. UPPP: Developed and implemented pollution prevention plan to protect the environment from pollutants on work projects with less than one acre of disturbance in conformance with NPS guidelines.
9.3 SUBMITTALS
A. After contract award and before the pre-work conference, prepare and submit:
1. A UPPP in conformance with NPS guidelines and adherence to all applicable storm water management practices.
B. Inspection Schedule: Submit schedule for inspection and monitoring of all pollution prevention measures.
C. Erosion Control Products: Submit manufacturer's product information and installation recommendations for silt fence, filter fabric, erosion control blanket, straw bales, wattles, and any other materials proposed for use on this project.
9.4 QUALITY ASSURANCE
A. The Contractor must prepare and submit a plan to the Contracting Officer’s Representative (COR) for review and concurrence.
B. Orientation Meeting: The Contractor is responsible for arranging and conducting Pollution Prevention meetings/briefings to inform all parties scheduled to be on-site during the project of the measures to be implemented for proper pollution prevention and control.
1. Installation of silt fences, straw bales, wattles storm, and other forms of pollution prevention controls must not begin until after this meeting has occurred.
C. Pollution Prevention Manager: The Contractor must designate the Pollution Prevention Manager who will be responsible for the implementation, inspection, maintenance, and amendments to the approved plan.
1. The Pollution Prevention Manager must be familiar with UPPP procedures and Best Management Practices (BMPs) and must ensure that emergency procedures and the plan are updated as needed and available for inspection.
2. When changes in the approved plan are required, the Pollution Prevention Manager must prepare and certify an amendment and submit to the Contracting Officer for review and concurrence.
9.5 UNDER AN ACRE POLLUTION PREVENTION PLAN
A. Provide a UPPP which conforms to all NPS requirements and include the following information and forms:
1. Responsible Parties;
2. General Information: Project Scope, Project Details, Site Information, Spill Prevention, and Precipitation Forecasts;
3. Standards and Constraints;
4. Project Scheduling;
5. Known Data on Soil and Fill;
6. Activities with the Potential to Generate Sediment;
7. Activities and Materials with the Potential to Pollute Storm Water;
8. Management and Reporting BMPs;
9. Waste Management BMPs;
10. Non-Storm Water Pollution Control BMPs;
11. Soil Stabilization BMPs;
12. Sediment Control BMPs;
13. Other Pollution Control BMPs;
14. References;
15. Preparer's Certification;
16. Appendices: Contact Information, Pollution Prevention Control Map or Sheet(s), Standard Installation Specifications for each BMP, and Blank forms.
9.6 ENVIRONMENTAL PROTECTION
A. Protection of Natural Resources: Comply with applicable regulations and these specifications.
Preserve the natural resources within the project boundaries and outside the limits of work performed under this Contract in their existing condition or restore to an equivalent or improved condition as approved by the COR.
B. Work Zone: Arrange work activities to minimize pollution (i.e., erosion, trash, etc.) to the maximum practical extent.
1. Work zone is limited to the area mowed around the structures.
2. Clearing, excavation, and grading must be limited to those areas of the project site necessary for work. Minimize the area exposed and unprotected.
3. Clearly mark and delineate the limits of work activities.
4. Equipment must not be allowed to operate outside the limits of work or to disturb existing vegetation.
5. Material must be stored away from locations where water is present to the greatest extent practicable.
6. All drilling fluids shall be contained and disposed of off the Park in a legal manner.
9.7 UNDER AN ACRE POLLUTION PREVENTION PLAN EXECUTION
A. Review and Acceptance: The Contractor and the COR will jointly review the draft Plan and agree to any needed revisions. The Contractor will incorporate all jointly agreed to revisions, and then sign and submit the final Plan to the COR. The final Plan will be the document enforced on the project.
1. The jointly agreed to Plan will describe and ensure implementation of the practices which will be used to reduce the pollutants in storm water discharges.
2. The Contractor must maintain a current copy of the Plan and all associated records and forms at the jobsite throughout the duration of the project.
3. The Plan must be available at all times for public inspection and for the inspection and use of the COR.
4. Concurrence by the COR to the jointly agreed to Plan will not relieve the Contractor of responsibility for compliance with other applicable environmental regulations.
B. Implementation: The Contractor must implement the Plan as required throughout the work period and maintain all erosion control elements in proper working order.
1. Do not perform clearing and grubbing or initiate work until the Plan has been implemented.
9.8 SITE INSPECTIONS AND PLAN REVISIONS
A. Inspections: The Contractor and the COR (or authorized representative) will perform weekly inspections of the site.
1. The inspections will look at disturbed areas that have not been completely stabilized, areas used for storage of materials, locations where vehicles enter or exit the site, and all other erosion and sediment controls that are included in the Plan.
B. Plan Revisions: It may be necessary to revise the Plan during work to make necessary improvements, revisions, or to respond to unforeseen conditions noted during work or site inspections.
1. The Plan must specify the mechanism whereby revisions may be proposed by the Contractor or the COR.
2. The Contractor and the COR will jointly review each revision to the Plan before changes are incorporated and implemented. The Contractor will then provide a revised copy of the Plan to the COR.
3. Accepted modifications will be implemented within seven (7) calendar days following the date of the inspection when deficiencies or necessary corrections are first noted.
C. Negligence: Provide additional temporary erosion and pollution controls made necessary by Contractor's errors or negligence at no additional cost to the Government.
9.9 HOUSEKEEPING AND SITE MANAGEMENT
A. Store materials onsite in conformance to Federal, state, local, and manufacturer’s regulations and specifications. Use Best Management Practices to minimize risk of materials coming into contact with environmental conditions (i.e. water and wind) that could disperse them.
B. Manage solid waste in conformance to Federal, state, and local regulations. Best Management Practices should be used to minimize risk of materials coming into contact with environmental conditions (i.e. water and wind) that could disperse them.
C. Manage hazardous waste (including contaminated soil) in conformance to Federal, state, local and NPS regulations and guidelines.
9.10 EROSION CONTROL MEASURES
A. Erosion control measures must consist of appropriate BMPs for storm water discharges, including but not limited to silt fencing, barrier protectors, straw bales, wattles, temporary soil retention blankets, excelsior drainage filters, and sediment traps. Note: If straw bales are used locally purchased rice straw only is allowed to reduce chance of invasive species introduced to site.
B. Erosion control measures must be used to contain stormwater discharges within the work zone.
A sufficient area should be established to allow the discharged water to infiltrate into the native soil in such a manner that does not result in erosion of the natural ground surface.
C. All opportunities to facilitate the surface water to percolate into the ground must also be considered, such as utilizing sprinkler heads to evenly distribute the water or utilizing a diffuser pipe manifold and adequate vegetated flow paths.
D. Earthen barriers (non-jurisdictional dams) or holding ponds will not be authorized.
E. Stormwater discharge water and precipitation runoff must be direct around and away from all fuel containment, storage, and work areas within the work site boundary.
F. Divert stormwater discharge water and precipitation runoff away from sensitive areas.
G. Work water used for dust control must have a controlled application rate to prevent sheet flow within the project area as well as out from the work boundary and into other areas of the Park.
Excess water used for dust control shall be contained within demolition areas by erosion control measures.
H. Furnish, install, maintain, and operate necessary control measures and other equipment necessary to prevent erosion as described in the approved UPPP.
I. Before work begins, sufficient equipment shall be available on site to assure operation and adequacy of erosion control system can be maintained.
9.11 MAINTENANCE OF TEMPORARY FACILITIES
A. Ensure erosion and sediment control features remain effective throughout the work. Maintain these features as necessary and reconfigure to adapt to changing conditions.
B. Continuously monitor erosion and sediment control features during work. Inspect these features before and after each significant precipitation event. Promptly repair weakened, damaged, and lost erosion and sediment control features.
9.12 REPORTING
A. If a discharge occurs or if the project receives a written notice or order from any regulatory agency, the Contractor will immediately notify the COR and will file a written report to the AHJ within seven (7) days of the discharge event, notice, or order. Corrective measures must be implemented immediately following the discharge, notice, or order. The report to the AHJ must contain the following items at a minimum:
1. The date, time, location, nature of operation, and type of discharge, including the cause or nature of the notice or order.
2. The BMPs deployed before the discharge event, or prior to receiving the notice or order.
3. The date of deployment and type of BMPs deployed after the discharge event, or after receiving the notice or order, including additional BMPs installed or planned to reduce or prevent re-occurrence.
4. An implementation and maintenance schedule for any affected BMPs.
9.13 SEDIMENT DISPOSAL
A. Sediment resulting from stormwater processes removed from temporary sediment control features must be disposed on the site within previously disturbed area at the end of the project as part of the site restoration. Sediment must be dried out prior to use in site restoration. The locations the sediment is applied must not be in areas susceptible precipitation runoff.
B. Sediment resulting from mud drilling processes shall be removed from the site and disposed of in an acceptable manner.
9.14 REMOVAL OF TEMPORARY POLLUTION CONTROL MEASURES
A. All temporary control measures shall be removed with permission of the COR within ten (10) working days after final acceptance of the project, and/or once grading is completed, and slopes have stabilized.
PART 10 – MOBILIZATION / DEMOBILIZATION (SECTION 01 71 13)
10.1 MOBILIZATION / DEMOBILIZATION
A. General: The work under this section consists of the mobilization and demobilization of the contractor's forces and equipment necessary for performing the work required under the contract. It does not include mobilization and demobilization for specific items of work for which payment is provided elsewhere in the contract. Mobilization will not be considered as work in fulfilling the contract requirements for commencement of work.
B. Mobilization shall include all activities and associated costs for transportation of contractor's personnel, equipment, and operating supplies to the site; establishment of offices, buildings, and other necessary general facilities for the contractor's operations at the site; premiums paid for coinsurance and reinsurance agreements as applicable; and other similar miscellaneous items.
C. Demobilization shall include all activities and costs for transportation of personnel, equipment, and supplies not required or included in the contract from the site; including the disassembly, removal, and site cleanup of offices, buildings, and other facilities assembled on the…