This document appears to be a Solicitation for a project to upgrade the steam system components at the Department of Veterans Affairs Tennessee Valley Healthcare System (TVHS) Nashville Campus. The key details are:

The project will replace failing condensate return skid pumps, piping, and associated components, as well as add venting as shown in the attached drawings. The work includes replacing the condensate return systems in several areas of the facility, including the Boiler Room Mezzanine, Chiller Plant, Fan Rooms, Clinical Sub-Basement, SPS, and ACRE Building. The contractor must comply with all applicable federal, state, and local regulations, as well as VA policies. The period of performance is 120 calendar days from the notice to proceed. Award will be made to a single contractor. Submittals are required within 10 days of contract award, and a schedule must be provided within 10 days of the notice to proceed. The work will require coordination with ongoing medical center operations, including conducting some work during off-hours.

View the file

Other files for this federal contract opportunity

Other files attached to Z1DA--626-24-204 - Update / Upgrade Steam System Components, newest first.
File Type Posted
36C24924B0011 0009.docx DOCX document
Atch 17 VAAR Clause 852.219-75 VA Notice of Limitations on Subcontracting CC.pdf PDF
Atch 14 VAAR Clause 852.219-75 VA Notice of Limitations on Subcontracting.docx DOCX document
36C24924B0011 0008.docx DOCX document
Atch 2 Specifications 626-24-204 Final R1.pdf PDF
36C24924B0011 0007.docx DOCX document
36C24924B0011 0006.docx DOCX document
36C24924B0011 0005.docx DOCX document
36C24924B0011 0004.docx DOCX document
Atch 6 Drawing Combined Steam-CAD Version.pdf PDF
36C24924B0011 0003.docx DOCX document
Atch 16 VA Form 6112 Equipment Record.pdf PDF
36C24924B0011 0002.docx DOCX document
Atch 15 Construction Safety Guidebook.pdf PDF
SPEC Section 01 45 00.pdf PDF
SPEC Section 01 32 16.15.pdf PDF
Atch 14 VA TVHS Confined Space Policy.docx DOCX document
Atch 1 WD Davidson County Building TN20240178 dated 07262024.pdf PDF
36C24924B0011 0001.docx DOCX document
Atch 10 General Conditions Breakout.xlsx XLSX spreadsheet
Atch 8 Nashville VA Steam Components Name and Location Key.xlsx XLSX spreadsheet
Atch 5 Drawing Armstrong AFH 4100 J Condensate Pump 30GAL Duplex.pdf PDF
Atch 7 Drawing Typical Flash Tank Connections.pdf PDF
Atch 6 Drawing Combined Steam.pdf PDF
Atch 3 Condensate Pump Selections Basis of Design.pdf PDF
Atch 1 WD Davidson County Building TN20240178 dated 06212024.pdf PDF
36C24924B0011_1.docx DOCX document
Atch 2 Specifications 626-24-204 Final.pdf PDF
Atch 13 Contractor EMR Certification Form.docx DOCX document
Atch 12 TAX ID UEI Document.docx DOCX document
Atch 11 Calculation of Contractor Self Performed Work.xlsx XLSX spreadsheet
Atch 9 Price Breakout Schedule Construction.xlsx XLSX spreadsheet
Show all 32

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

3.13

6.31 16.31

17.00

LIFTING EYES

(OPTIONAL)

8.50

7.50

28.91

1-1/2" NPT

PUMP DISCHARGE

PRESSURE GAUGE, CHECK VALVE

GATE VALV AND BALL VALVE

(OPTIONAL)

1-1/2" NPT VENT

3.00 7.50

.25

FOOT PAD

12.25

15.00 3.97 3.34

29.78 44.24

1-1/2 NPT

OVERFLOW

2" NPT

PROCESS RETURN

7.50

8.76

14.25

35.44

NEMA 12

CONTROL PANEL

(OPTIONAL)

FLOAT SWITCH OR

ALTERNATOR

THERMOMETER

(OPTIONAL)

GAUGE GLASS

(OPTIONAL)

ISOLATION VALVE

(OPTIONAL) 1/2" NPT DRAIN

NOTES:

• TANK MATERIAL: STEEL

• ALL DIMENSIONS ARE ±0.25"

• DRAWING NOT FOR CONSTRUCTION

• CONSULT FACTORY AT TIME OF ORDER FOR CURRENT PRINT

• INLET BASKET STRAINER OR Y-STRAINER ALSO AVAILABLE

CONTROL PANEL OPTIONS ALSO AVAILABLE (NOT SHOWN):

• NEMA 4 OR NEMA 4X OR NEMA 3R CONSTRUCTION

• ELECTRIC ALTERNATOR

• POWER ON LIGHT

• PUMP TEST BUTTON

• PUMP RUN TIME METER

• EXTRA DRY CONTACTS

• UL/CUL LABELED PANEL

• HIGH LEVEL ALARM HORN & LIGHT W/SILENCE SWITCH

• LEAD-AUTO-LAG SELECTOR SWITCH

D

C

B

A A

B

D

12345678

8 7 6 5 4 3 2 1

5/3/2021INITIAL DESIGN

SIZE

B

THIRD ANGLE PROJECTION

SCALE: 1:10SHEET: 1 OF 1 A684.41015.00J

3/16/2018

NAME DATE

ENG APPR.

CHECKED

DRAWN

15 GALLON DUPLEX

PART NO:

GJM

684.41015.00J

TITLE

DWG NO. REV

4100 SERIES

"J" CONDENSATE PUMP

DRAWING MAY NOT BE PRINTED TO SCALE.

DATENAME

GJMA

REV DESCRIPTION ECN

WEIGHT

1359.01

FABRICATION TOLERANCES

UNLESS OTHERWISE SPECIFIED:

DIMENSIONS ARE IN INCHES

TOLERANCES:

ANGULAR DIMENSIONS 1

FRACTIONS 1/16

TWO PLACE DECIMAL 0.06

THREE PLACE DECIMAL 0.030

PRODUCT CATEGORY

HTSP Boiler and Condensate

PRODUCT FAMILY

C armstronginternational.com

Sheet1
Drawing View11
Drawing View12
Drawing View13
Drawing View14
Drawing View15

File details come from the government source that posted it. Updated .