36C24924B0011 0002.docx

DOCX document 181 KB Posted

Attached to
Z1DA--626-24-204 - Update / Upgrade Steam System Components Federal contract opportunity
Solicitation number
36C24924B0011
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 9

About this file

This document is a modification to Solicitation 36C24924B0011, which is for the Update/Upgrade Steam System Components project at the Department of Veterans Affairs Tennessee Valley Healthcare System (TVHS) Nashville Campus.

The key details are:

  • The project will replace failing condensate return skid pumps, piping, and associated components, as well as add venting as described in the attached drawings and documents.
  • The work includes repairing and upgrading various steam system components throughout the facility, such as steam traps, condensate return systems, and flash tanks.
  • The period of performance is 120 calendar days from the notice to proceed.
  • The contractor must adhere to applicable federal, state, and local codes and regulations, as well as VA policies and specifications.
  • Contractor submittals are due within 10 days of contract award, and the project schedule is due 10 days from the notice to proceed.
  • The facility will remain occupied during construction, and the contractor must coordinate activities to minimize disruptions to hospital operations.

View the file

Other files for this federal contract opportunity

Other files attached to Z1DA--626-24-204 - Update / Upgrade Steam System Components, newest first.
File Type Posted
36C24924B0011 0009.docx DOCX document
Atch 17 VAAR Clause 852.219-75 VA Notice of Limitations on Subcontracting CC.pdf PDF
Atch 14 VAAR Clause 852.219-75 VA Notice of Limitations on Subcontracting.docx DOCX document
36C24924B0011 0008.docx DOCX document
Atch 2 Specifications 626-24-204 Final R1.pdf PDF
36C24924B0011 0007.docx DOCX document
36C24924B0011 0006.docx DOCX document
36C24924B0011 0005.docx DOCX document
36C24924B0011 0004.docx DOCX document
Atch 6 Drawing Combined Steam-CAD Version.pdf PDF
36C24924B0011 0003.docx DOCX document
Atch 16 VA Form 6112 Equipment Record.pdf PDF
Atch 15 Construction Safety Guidebook.pdf PDF
SPEC Section 01 32 16.15.pdf PDF
Atch 14 VA TVHS Confined Space Policy.docx DOCX document
SPEC Section 01 45 00.pdf PDF
Atch 1 WD Davidson County Building TN20240178 dated 07262024.pdf PDF
36C24924B0011 0001.docx DOCX document
Atch 10 General Conditions Breakout.xlsx XLSX spreadsheet
Atch 8 Nashville VA Steam Components Name and Location Key.xlsx XLSX spreadsheet
Atch 5 Drawing Armstrong AFH 4100 J Condensate Pump 30GAL Duplex.pdf PDF
Atch 7 Drawing Typical Flash Tank Connections.pdf PDF
Atch 6 Drawing Combined Steam.pdf PDF
Atch 3 Condensate Pump Selections Basis of Design.pdf PDF
Atch 1 WD Davidson County Building TN20240178 dated 06212024.pdf PDF
36C24924B0011_1.docx DOCX document
Atch 13 Contractor EMR Certification Form.docx DOCX document
Atch 12 TAX ID UEI Document.docx DOCX document
Atch 11 Calculation of Contractor Self Performed Work.xlsx XLSX spreadsheet
Atch 9 Price Breakout Schedule Construction.xlsx XLSX spreadsheet
Atch 4 Drawing Armstrong AFH 4100 J Condensate Pump 15GAL Duplex.pdf PDF
Atch 2 Specifications 626-24-204 Final.pdf PDF
Show all 32

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C24924B0011 0002

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO:

Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 08-15-2024 626-24-3-4373-0138 626-24-204 90C Department of Veterans Affairs Network Contracting Office 9 (90C) Vance W. Rosebush, Contracting Officer 1639 Medical Center Parkway, Suite 204 Murfreesboro TN 37129 90C Network Contracting Office 9 Department of Veterans Affairs Jen Jamieson, Contract Specialist jen.jamieson@va.gov To all Offerors/Bidders

36C24924B0011

X X X

X Amendment 0002 is being issued to provide answers to the RFIs and include additional attachments.

See attachment 14:VA TVHS Confined Spaced Policy See attachment 15: Construction Safety Guidebook See attachment 16: VA Form 6112 Equipment Record See attachment SPEC Section 01 32 16.15 See attachment SPEC Section 01 45 00

Vance W. Rosebush Contracting Officer RFI Questions and Answers 626-24-204 Update Steam System Components Project Location: VA Tennessee Valley Health Care System 1310 24th Ave S, Nashville, TN 37212-2637

Q1) Is this a tax-exempt project?

A1) No

Q2) If tax-exempt, will the government provide the prime contractor with a tax-exempt certificate for use by subcontractors and vendors?

A2) See A1

Q3) Can both the bid and bid bond be emailed?

A3) Yes

Q4) If the bid and/or bid bond must be mailed, will the government consider extending the bid due time to no earlier than 11 a.m.? This request is made because 1030 a.m. is the earliest guaranteed time for overnight delivery, and anything before then risks not being guaranteed and potentially arriving after the current bid due time. Extending the bid’s due time would ensure that all bids are received on time and that the process is fair for all parties involved.

A4) See A3

Q5) Can the Superintendent be shared across multiple projects, or should they only be dedicated full-time to this project?

A5) No, superintendent must be on site at all time work is being performed.

Q6) Can the Superintendent fulfill the Quality Control Manager (QCM) role?

A6) Yes

Q7) If the Super cannot fulfill this role, the average ADDITIONAL cost for a dedicated QCM is approximately $26,500 per month (salary, labor burden, per diem, housing, company vehicle, monthly return trips home, company phone, etc). We expect this project to be 6 months long, and the bid is expected to increase by $150,000. Please confirm a dedicated QCM is still required.

A7) See A6

Q8) Is the QCM required to be onsite full-time, or can they make site visits as required for inspections?

A8) full time QCM is not required.

Q9) If the QCM is required to be onsite, should they be assigned to this project only, or can they be assigned to another project as well?

A9) See A8

Q10) Can a subcontractor (e.g., Terracon or a similar testing firm) fulfill the QCM role?

A10) Yes

Q11) Can the Superintendent fulfill the Site Safety & Health (SSHO) role?

A11) Yes

Q12) If the Super cannot fulfill this role, the average ADDITIONAL cost for a dedicated SSHO is approximately $26,500 per month (salary, labor burden, per diem, housing, company vehicle, monthly return trips home, company phone, etc). We expect this project to be 6 months long, and the bid is expected to increase by $150,000. Please confirm a dedicated SSHO is still required.

A12) See A11

Q13) Our interpretation of 01 35 26, 1.7 in its reference to FAR 52.236-6 is that the prime contractor would be in compliance with this section if we have a Superintendent on-site during construction, as FAR 52.236-6 does not require (or mention for that matter) an SSHO and explicitly covers the prime contractor's Superintendent only. In short, an onsite SSHO is not a requirement per FAR 52.236-6. Please confirm.

A13) This interpretation is correct.

Q14) Is the SSHO required to be on-site full-time, or can they be a home office employee (e.g., Safety Director) on the prime contractor's staff?

A14) Site safety should be readily available but is not required to be on site full time.

Q15) If the SSHO is required to be onsite, should they be assigned to this project only, or can they be assigned to another project as well?

A15) Please refer to A14.

Q16) Can a subcontractor fulfill the SSHO role with periodic visits?

A16) Yes.

Q17) Does the VA require any scope of work in this project to be performed outside of regular work hours?

A17) Only work that will affect services to the hospital or critical areas of the hospital.

18) What trades or scopes will be required to perform off-hours work for work scopes that must be performed?

A18) A superintendent and the trades required to complete the task.

Q19) What will the work hours and days be for scopes that require off-hours work?

A19) After 6 pm or when the final OR case completes for the day any day of the week.

Q20) Please provide a copy of the Site Visit Attendance Sheet.

A20) See Amendment 0001 posting in SAM.gov.

Q21) In the event of contract modifications, should contractors apply bond premiums to the individual modification or wait until the end of the job where the VA issues a final modification to reimburse contractors for bond overruns for all mods.

A21) Bonds should be adjusted at the time of and per the modification.

Q22) Where is the designated contractors' and subcontractors' parking area?

A22) The contractor lay down area is behind the boiler plant and between the VA and Vanderbilt UMC. Contractors are permitted to park one (1) necessary vehicle at a time in these areas. Additional parking is the VA parking structure floors 4 and up.

Q23) Will the VA allow 2-3 spaces for the prime contractor and each subcontractor?

A23) Parking will be arranged on site.

Q24) Where shall these people park if the VA cannot make 2-3 spaces available for the prime contractor and each of the subs?

A24) Please refer to A22 and A23

Q25) How many hours should the prime contractor and subcontractors budget for on-site badging, safety training, orientation, etc.?

A25) Four to six (4-6) hours

Q26) Is TB Testing required before contractors can commence work onsite?

A26) Yes

Q27) The period of performance (POP) on this project is given to be 120 days. However, we estimate the project will take 180 days to construct. Contractors never know when the government will issue an NTP; sometimes, it's immediately after the award; sometimes, we receive an admin NTP to begin submittals, etc. We estimate the time to construct this job is longer than the stated POP, excluding preconstruction activities. We request that the POP be extended by 60 days, assuming NTP is issued after preconstruction activities, which we estimate will take 90 days for this project.

A27) The intent is to have this project completed before the start of the heating season. POP extensions will be discussed after award.

Q28) In lieu of the provided cost estimate breakdown, will the government accept a printout report from our COTS estimating software that provides the same level of breakdown specified in the government-provided breakdown spreadsheet?

A28) No

Q29) Is temp power available for contractors to connect their temp office to?

A29) No space for an office trailer is available.

Q30) If no temp power is available, a generator will be required, which usually adds significant cost to rent and fuel. Please confirm this is necessary if no temp power is available.

A30) See A29

Q31) What are the locations for temp power?

A31) See A29

Q32) Are contractors required to set a pole and meter electric usage?

A32) See A29

Q33) Will the VA provide a space for the Prime Contractor’s Superintendent to set up, or should we add costs to our bid for a mobile office?

A33) See A29

Q34) Is space available for a 10’ x 40’ temporary ground-level office near the temporary power source?

A34) See A29

Q35) Will the VA provide space for a 20-yard dumpster?

A35) Space for a dumpster will be provided.

Q36) Where shall contractor dumpsters be located?

A36) The location will be determined at the time of delivery due to the evolving space situation at the VA.

Q37) Can the VA accommodate a dumpster near the job site?

A37) See A35

Q38) Will the VA allow contractors to use VA indoor restrooms?

A38) Contractors are to provide their own restroom facilities.

Q39) Can Porta Johns be placed within a 100’ radius of the job site if required?

A39) Yes, but must be within the laydown area.

Q40) Can contractors perform crane lifts during regular hours?

A40) Yes, with an approved crane lift plan. Some plans may require afterhours work if it impedes with patient care.

Q41) Can utility tie-ins be performed during regular hours?

A41) Yes, if there are no service interruptions to the hospital.

Q42) Can system commissioning activities be performed during regular hours?

A42) Yes, if there are no service interruptions to the hospital.

Q43) Will the VA allow for stored material so that we can procure and lay down long lead items and/or critical path material/equipment?

A43) Yes, provided space is available. Must be approved by the VA prior to storing.

Q44) Will the VA fully pay for this material/equipment if stored onsite?

A44) Yes, if material is bonded and insured by the prime contractor.

Q45) Many of the drawings and notes are not legible on Attachment 6, Drawing Combined Steam.

A45) Attachment 6 will have an AutoCad file attached so it can be read clearly.

Q46) Please provide the confined space requirements.

A46) See attachment 14 VA TVHS Confined Space Policy.

Q47) Please provide a scope for the Test and Balance required.

A47) Water side TAB to verify operation, flow, and GPM.

Q48) What brand are the boiler controls?

A48) Siemens

Q49) Spec Section 01 00 00 (1.5)(E)(3) and Spec Section 01 00 00 (1.7)(B) & (D) shown below are unclear. Please provide information on contractor laydown area, including space for office trailer. The specs say that none will be given unless requested prior to the proposal. A lay down/dumpster/office trailers will be vital at getting this project completed timely. The contractor must be allowed storage area.

A49) A space will be provided for a dumpster. A space may not be available for a contractor job trailer due to the emergency chiller and generators occupying the space normally reserved for this.

Spec Section 01 00 00 (1.5)(E)(3)

Spec Section 01 00 00 (1.7)(B)&(D)

Q50) Please provide a list of non-working management personnel that will be required on site for this project full-time.

A50) Site superintendent

Q51) Can the SSHO have collateral duties with the Site Superintendent?

A51) Yes

Q52) Can the Quality Control Manager have collateral duties with the SSHO?

A52) Yes

Q53) Can the Quality Control Manager have collateral duties with the Site Superintendent?

A53) Yes

Q54) Can the Site Superintendent have collateral duties with the SSHO and Quality Control Manager?

A54) Yes

Q55) Can the contractor obtain access to more than one set of keys as explained in the specifications?

A55) Yes. The exact number to be determined by the Chief of Engineering Nashville VA.

Q56) How much parking will the contractor be given? Parking must be allowed in order to access the job site.

A56) Adequate parking is available.

Q57) Spec Section 01 00 00(1.35) Training of VA Personnel: There is not factory witness training available for this equipment. Is the intent for training to be performed on-site? Please clarify the training required.

A57) Training for M&O personnel will be conducted for any special maintenance requirements, installation requirements, troubleshooting, and programming on installed equipment by a qualified and competent person. Qualification will be vetted by the COR through the official submittal process.

Spec Section 01 00 00(1.35)

Q58) The Equipment Record form on page 34 of the Specifications is not clear. Please provide a clear copy.

A58) See attachment 16 VA Form 6112 Equipment Record.

Q59) The requirements for project schedule conflict. One place indicates the project schedule is due from contractor 10 days from the notice to proceed, another place says 7 days from the notice to proceed. The VA review period also varies from 7 days to 14 days. Please clarify the deadlines for the project schedule, including contractor’s submittal deadline and VA review period.

A59) Project Schedule are due from the contractor 10 calendar days from the notice to proceed see SF 1442 Statement of Work section, page 11 of 72, para 10, see attached corrected copy of Specification Section 01 32 16.15 pages 2 & 3.

Q60) The number of activities required on the schedule is unclear. The solicitation limits the number of activities to 30 items, but the Specifications say “The Complete Project Schedule shall contain approximately 90 work activities/events.” Please clarify how many work activities are allowed and required for the project schedule.

A60) 30 Activities is the correct number of required items.

Q61) Specification 01 45 00(3.4)(B) & (C) have missing information regarding CQC Manager requirements. Please amend this section to include requirements.

A61) see attached corrected copy of Specification Section 01 45 00 page 7.

Spec Section 01 45 00(3.4)(B) & (C)

Q62) The Specifications contain many references to “Spec Writer Notes”, that appear to instruct the VA writer to select appropriate requirements. Additionally, the Specifications are all inclusive of every possible construction project at the facility and include requirements that are well beyond the scope of this project. Please provide project-specific Specifications.

A62) Specs were included for all possible scenarios and situations the contractor may encounter during contraction. Refer only to the relevant specs for the assigned task.

Q63) Specifically, Spec Section 01 91 00(1.7)(B) beginning at page 128 of the specifications contains a list of systems to be commissioned that is beyond the scope of this job. Please provide a revised list of items that are to be commissioned on this project.

A63) Refer to A47

Q64) Is the Contractor or the VA to provide the commissioning agent?

A64) Contractor is to supply a commissioning agent.

Q65) Specification Section 01 91 00(1.14) is missing valuable dates. Please amend to include relevant deadlines.

A65) This should be 14 calendar days.

Q66) Specification Section 01 91 00 (3.4) indicates phased commissioning is required. Please provide a phasing schedule anticipated for this project.

A66) Phasing will be determine on site and by section through contractor and COR coordination.

Q67) Specification Section 01 91 00(3.5) includes a table for DDC controls beginning at page 160 that is beyond the scope of this job. Please clarify which portions are applicable, if any, to this project.

A67) CRPS will have the following points; enable/disable. Proof, alarm status

Q68) Specification Section 01 91 00(3.6)-(3.9) include testing and training that is far beyond the scope of this job. Please clarify what applies to this project.

A68) Testing will consist of testing and verifying proper installation and operation of the equipment. Training will be provided to the VA M&O staff on operation and maintenance of said equipment.

Q69) Note 9, Part V of the Bid Solicitation. “Provide a stamped QC report and certification prior to requesting final inspection.” Please clarify is this “stamp” from a third-party engineer or will this be by the manufacturer’s representative? Who provides the stamp and what are the qualifications required by the stamp holder?

A69) Third party or Manufacture’s rep for equipment will be sufficient.

Q70) Much more information is needed to properly price the work required. I feel like I am missing part of the documents. Is this 100% design build and we need to hire an engineer to design the piping revisions and repairs required. In Part IV note 3 it states that PE stamped drawings are not required for this project, but there is significant missing information.

A70) All reports, and available information has been provided.

Q71) On Attachment 8 there are some comments and recommendations in the far-right hand column. Are we to perform the work in the “Recommended” column from Attachment 8 along with the work listed in the scope of work from the Bid Solicitation? If so, please provide more detail on what is required.

A71) Attachment 8 is provided for informational purposes only. Refer to the SOW for the contracted tasks.

Q72) To perform the work listed in the SOW or the work “Recommended” on Attachment 8 we need existing and new piping sizes, routing drawings and details to properly price the work. For example, there are several notes in the scope of work that say, “Upsize piping as required.” I didn’t find anything detailing what size the pipe is now and what size the pipe needs to be upsized to.

A72) Piping sizes are to be field verified by the contractor.

Q73) There are some comments about installing a new condensate pump and I see model and details for some condensate pumps. Which pump is to go in which location? Same with Flash Tanks. Scope notes to “install properly sized flash tank at pumping station.” What is the proper size for the flash tanks?

A73) Condensate pumping station locations are called out in the SOW. Please refer to the SOW. Flash tank sizes are to be installed following industry standard and sizing guidelines.

Q74) The scope of work note 3 states to “Repair the pumping mechanism on trap and correct piping. Upsize as required.” What needs to be repaired and what is the pipe correction required? What is the size of the existing and what is the upsize?

A74) Pumping mechanism’s operation is to be diagnosed and repaired by contractor. Piping sizes are to be field verified by the contractor.

Q75) SOW note 4… ”separate return lines. Upsize as required.” How do they need to be separated? Can you provide more information?

A75) low and medium pressure return lines are to be separated from one another from the main condensate return system. Piping to be upsized as determined on site.

Q76) SOW note 5… ”separate high and low-pressure return lines. Upsize as required.” How do they need to be separated? What size pipe is the existing and the new upsize?

A76) low, med, and high pressure return steam need to be piped separately and the piping configuration upsized as required by code.

Q77) The rest of the SOW continues in the same vein. Please provide piping plans, sizes and details with enough information to properly price the work you require.

A77) All reports, and available information has been provided.

END OF RFI Questions and Answers

ATTACHMENTS

See attached document: Atch 14 VA TVHS Confined Space Policy.

See attached document: Atch 15 Construction Safety Guidebook.

See attached document: Atch 16 VA Form 6112 Equipment Record.

See attached document: SPEC Section 01 32 16.15.

See attached document: SPEC Section 01 45 00.

image5.png image6.png image7.png image1.png image2.png image3.png image4.png