Atch (1)_APPENDIX D Risk Assessment Example Format - 24 Jan 2023.pptx

PPTX presentation 86 KB Posted

Attached to
N61340 - Draft RFP and Pre-Solicitation Conference - Ready Relevant Learning Fiscal Year 2024 Content Conversion Aviation (RRL FY24 CC Aviation)
Solicitation number
N6134023R0073
Issued by

View the file

Other files

File Type Posted
RRL_FY24_CC_PSC_Brief_Final.pdf PDF
RRL_FY24CC_Aviation_PSC_Industry_RSVP_Attendance_Lists_12Jun23.pdf PDF
GFI_U-ATI-1000_NTP_Workbook_Draft_6Jun23.xlsx XLSX spreadsheet
Atch (1)_APPENDIX G RRL Use of Blooms Taxonomy Action Verbs - 18Apr23.docx DOCX document
Atch (8)_RRLGM 22-0001 PALS_13May22.pdf PDF
Atch (1)_APPENDIX H RRL Media Characteristics - 05 Mar 2023.docx DOCX document
GFI_RRL_FY24CC_Aviation_Appendix_A_DRAFT_6Jun23.xlsx XLSX spreadsheet
Atch (L-3) Relevancy Information_N6134023R0073_6Jun23.xlsx XLSX spreadsheet
Atch (1)_FY24_CC_DRAFT_SOW_31May23.docx DOCX document
Exh_F_RRL_FY24CC_(F00X)_Training_CDRLs_18Apr23.docx DOCX document
Atch (2)_NAWCTSD_DIT_Form_Jan2023.pdf PDF
Exh_A_RRL_FY24CC_(A00X)_Eng_CDRLs_13Mar23.docx DOCX document
Atch (1)_APPENDIX B Acronym List - 22May23.docx DOCX document
Atch (L-1) Q-A Form_N6134023R0073.xlsx XLSX spreadsheet
Atch (7)_SOW Appendices C and H aligned_22May23.docx DOCX document
Atch (L-5) Small Business Participation Committment Document (SBPCD)_N6134023R0073.docx DOCX document
Exh_B_RRL_FY24CC_(B00X)_Admin_CDRLs_10Apr23.docx DOCX document
Atch (9)_Complex_Media_VSIM_Construct_1Jun23.docx DOCX document
Atch (L-4) CLIN Pricing Form_N6134023R0073_22May23.xlsx XLSX spreadsheet
Atch (1)_APPENDIX F RRL Operational Engaging Instructional Strategies_22May23.docx DOCX document
Atch (L-2) Contractor Performance Assessment Questionaire (CPAQ)_N6134023R0073.docx DOCX document
Atch (1)_APPENDIX C Terms and Definitions_22May23.docx DOCX document
Atch (3)_NETC_RRL_Style_Guide_19NOV2021.docx DOCX document
FY24_CC_N6134023R0073_DRAFT_6Jun23.docx DOCX document
Atch (5)_NAVEDTRA 136 Question Bank Layout Template_3May23.xlsx XLSX spreadsheet
Atch (L-6) Offeror Summary Table.xlsx XLSX spreadsheet
Atch (6)_RRL Interactive Media Definitons Examples_23Nov22.pdf PDF
Atch (1)_APPENDIX E RRL Content Delivery Modes - 18Apr23.docx DOCX document
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DISTRIBUTION A. Approved for public release. Distribution is unlimited.

APPENDIX D: Risk Assessment Example Format 24 January 2023

Sailor 2025 – Ready Relevant Learning (RRL) Risk Assessment

Likelihood [5] Near Certainty (~90%)

[4] Highly Likely (~70%)

1
[3] Likely

(~50%)

[2] Low Likelihood (~30%)

[1] Not Likely (~10%)

Consequence[1]
Minimal[2]
Minor[3]
Moderate[4]
Major[5]

Unaccept-able

O

- Original X

- Current Low Moderate High

Consequence Likelihood

Action/Event Date Schd.

ECD

Act.

Current Status Risk Level if Successful C L Suc.

Comments Plan:

T

- Target New Plan - Current Plan Current Original Risk Level N/A N/A

1. Coordinate with schoolhouse staff and TYCOMs for SMEs.

10/1/16 1/26/17 1/26/17 Coordinating with schoolhouse and TYCOMs for SMEs.

Y

2. Coordinate with fleet SMEs prior to and during the acquisition phases.

1/2/17 05/10/17 5/10/17 Continuing coordination with schoolhouse and SMEs.

Y

8/14/17 8/14/17 8/14/17 Continue to coordinate with schoolhouse staff and fleet SMEs prior to and during the acquisition phases.

Y

Risk Status:

Open

Risk Type (Check one in each area Technical Schedule Cost Risk Summary Worksheet Team: Sailor 2025 Risk Owner: NAWCTSD Date Opened: 01 Oct 2016 Updated: 14 Aug 2017 Risk Title: Sufficient Access to Fleet and Schoolhouse SMEs Risk #: 1 Description of Risk: If sufficient access to fleet and schoolhouse Subject Matter Experts (SMEs) is not available during analysis, design, development, and testing, for each wave, then contractor deliverables, the analysis output, and content conversion may be late.

Root Cause: Fleet and schoolhouse SMEs are busy working and teaching classes and have limited availability for RRL visits.

Consequence: Contractor deliverables, the analysis output, and content conversion may be late.

X O X

3. Risk working group meeting

Action/Event Date Schd.

ECD

Act.

Success Criteria L C Suc.

Comments Risk Level if Successful

Plan:

New Plan - Current Plan Current

Team: Sailor 2025 Risk Owner: NAWCTSD Date Opened: 01 Oct 2016 Updated: 14 Aug 2017 Risk Title: Sufficient Access to Fleet and Schoolhouse SMEs Risk #: 1 Risk Summary Worksheet

Backup Information

Program Risk Assessment

Not Likely:

Low Likelihood:

Likely:

Highly Likely:

Near Certainty:

...Will effectively avoid or mitigate this risk based on standard practices ~10% ...Have usually mitigated this type of risk with minimal oversight in similar cases ~30% ...May mitigate this risk, but workarounds will be required ~50% ...Cannot mitigate this risk, but a different approach might ~70% ...Cannot mitigate this type of risk; no known processes or workarounds are available ~90%

Determination of consequence for Schedule and Cost are program Specific.

Consequence

HIGH

MEDIUM

LOW

LevelTechnical PerformanceScheduleCost
1Minimal or no consequence to technical performanceMinimal or no impactMinimal or no impact
2Minor reduction in technical performance or supportability, can be tolerated with little or no impact on program; same approach retainedAdditional activities required, able to meet key dates.
Slip <___Month(s)Cost increase or unit production cost increases

< 1_% of budget

3Moderate reduction in technical performance or supportability with limited impact on program objectives; workarounds availableMinor schedule slip, no impact to key milestones
Slip < __ month(s) plus available float of critical path. Sub-system slip > __ month(s) plus available float. Slip <__Month(s)Cost increase or unit production cost increase

<___ 5% of budget

4Significant degradation in technical performance or major shortfall in supportability; may jeopardize program success; workarounds may not be available or may have negative consequencesPrgm critical path affected, all sched float assoc. w/key MS exhausted
Slip <__ MonthsCost increase or unit production cost increase

<____ 10% of budget

5Severe degradation in technical performance; Cannot meet KPP or Key technical/supportabilility threshold; will jeopardize program success; no workarounds availableCannot meet key program milestones
Slip >___ MonthsExceeds APBA threshold

> ____ 10% of budget

Consequence Level Probability of Occurrence image1.bin image2.emf