This is an Operations and Maintenance Manual for the RV Sewer Dump Station located at Joint Base Charleston Short Stay Recreation Facility in Berkeley County, South Carolina. The manual, dated April 2, 2015, provides operational and maintenance guidance for a wastewater holding tank system consisting of two precast concrete tanks with a combined 15,000-gallon capacity. The system includes two 7,500-gallon tanks connected by a 24-inch equalizer pipe, with two manholes per tank. The high-level alarm activates at 75 percent capacity, approximately 11,800 gallons, with alarm activation occurring at 5.5 feet of liquid level.

The contractor's primary operational requirements include daily volume monitoring to determine when pump-out services are needed, monthly testing of the high-level alarm system, and comprehensive documentation of all inspections with date, time, volume measurements, and personnel names. The contractor must maintain holding tank volume below 9,000 gallons and perform pump, haul, and disposal services before reaching that threshold, providing certificates of disposal for each occurrence. Additional duties include keeping drain holes clean and rinsed using wash-down hydrants and ensuring tanks are pumped out prior to Memorial Day, Independence Day, and Labor Day. All inspection records must be maintained on-site throughout the contract period and transferred to the Government upon contract expiration. Facility contact information includes CE Customer Service (843-963-5027), JB CHS Environmental (843-963-1483), Short Stay Management (Mr. Richard Hahn, 843-761-8385), and Engineering Flight for construction matters (843-963-1493).

View the file

Other files

File Type Posted
Atch-01 PWS Attachment 8.8.4. Digital Analyzer US – Field Service Report.pdf PDF
Atch-01 WWTP OM Services PWS dated 16 Jan 2026.pdf PDF
Atch-01 PWS Attachment 8.7. Short Stay Wastewater Treatment Facility O&M Manual Book 2.pdf PDF
Atch-01 PWS Attachment 8.1. Short NPDES Stay Permit Jan 2026.pdf PDF
Atch-01 PWS Attachment 8.3. Short Stay Wastewater Treatment Plant Site Layout Drawings and Photos.pdf PDF
Atch-01 PWS Attachment 8.8.3. Digital Analyzer Install Inspection.pdf PDF
Atch-01 PWS Attachment 8.9. Short Stay Wastewater Treatment Plant PMI Spreadsheet.pdf PDF
Atch-01 PWS Attachment 8.7. Short Stay Wastewater Treatment Facility O&M Manual Book 1.pdf PDF
Atch-01 PWS Attachment 8.2. Short Stay Wastewater Treatment Plant Layout As-builts.pdf PDF
Atch-01 PWS Attachment 8.7. Short Stay Wastewater Treatment Facility O&M Manual Book 3.pdf PDF
Atch-01 PWS Attachment 8.8.2. Digital Analyzer Certificate of Instrument Performance.pdf PDF
Atch-01 PWS Attachment 8.8.7. pH ORP Sensor Manual.pdf PDF
Atch-01 PWS Attachment 8.8.6. Output Module Manual.pdf PDF
Atch-01 PWS Attachment 8.8.5. LDO Sensor Manual.pdf PDF
Atch-01 PWS Attachment 8.5. Short Stay Water Distribution Map.pdf PDF
Atch-01 PWS Attachment 8.4. Short Stay Fire Line and Hydrants Map.pdf PDF
Atch-01 PWS Attachment 8.8.1. Analyzer Controller Manual.pdf PDF
Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Joint Base Charleston Short Stay

RV Sewer Dump Station Operations and Maintenance Manual

2 April 2015

Table of Contents

Introduction 3

System Description 3

Inspection Requirements 3

Operation Requirements 3

Facility Contact Information 4

Tank Level Calculations 5

Lid Specifications 6

High Level Alarm Specifications 7

Holding Tank Specifications 8

O & M

Manual For

Short Stay RV Wastewater Holding Tank System

INTRODUCTION

This manual was prepared to provide a brief system description and operation and maintenance requirements for the RV Wastewater Holding Tank located at the Joint Base Charleston, Short Stay Recreation Facility in Berkeley County, South Carolina.

SYSTEM DESCRIPTION

The 2014 installed system consists of two (2) 7500 gallon precast concrete holding tanks connected by a 24” equalizer pipe. There are two (2) manholes for each of the 7500 gallon holding tanks. The maximum capacity of both tanks is 15,000 gallons and a high level alarm will sound when volume reaches 75% capacity (approx. 11,800 gal).

INSPECTION

The contractor shall at a minimum:

1. Monitor the volume in each tank daily to ensure the system is functioning properly and to determine if a pump out is necessary.

2. Test the high level alarm monthly.

3. Document all inspections to include the date, time, volume and name of the person performing all inspections and any corrective measures taken. These records shall be maintained throughout the performance period of the contract and available on-site for Government review. These records will be turned over to the Government at the expiration of the Contract.

OPERATION

The contractor shall:

1. Perform daily volume measurements of the holding tanks and record the date, time, volume and name of the person performing measurement. Identify any inefficient operation or facility discrepancies to the Short Stay Facility Manager, Joint Base Charleston Environmental, and the COR.

2. Ensure the volume of the holding tanks does not exceed 9,000 gals. The contractor shall perform pump, haul and disposal services before the volume reaches 9,000 gallons. A Certificate of disposal (equivalent to a sludge ticket) shall be provided to the Joint Base Charleston Environmental Office and the COR for each occurrence.

3. Drain holes shall be kept clean and rinsed with the wash-down hydrant on an as needed bases during the inspection process. It is vital that the drain hole basin and surrounding concrete remain clean for sanitation reasons.

4. Holding tanks shall be pumped out prior to the following Holidays: Memorial Day, Independence Day and Labor Day.

FACILTY CONTACT INFORMATION

Facility maintenance and contract information:

CE Customer Service – 843-963-5027 JB CHS Environmental – 843-963-1483

Short Stay Management:

Mr. Richard Hahn – 843-761-8385

Construction information and Site Surveys CE:

Engineering Flight – 843-963-1493

Tank Level Calculations

RV Dumpstation 15,000 gallon capacity

Liquid Level and Corresponding Gallons

1 ft – 2,154 gal

2 ft – 4,308 gal

3 ft – 6,463 gal

4 ft – 8,617 gal

5 ft – 10,771 gal

5.5 ft – 11,848 gal

(Alarm will activate)

6 ft – 12,925 gal

7 ft – 15,080 gal

6'-0' 6'-0'

I

.·...•' . . i.:

... .... . · . .·· • 1; ..' . ..·>·, :·.. ..•'

..·.....:.......... .. . I ------------ - . .. :.,. :'. l--------- I<- -"' ...:•!' i:·

12'-0' 2'-8' 6'-4' .j>.

I 0 0 '

"'I ·.

;o. : ;•.

.· .. ;• i .,.4..

·.·..: :. t-- --i' .• ) · ..:,·:,...,;, ..... ----' :·;.:"·..· ..'·...·.. . ·. . : . • •• • ,11 • .· " .:

'\•·•·.":. N -\3\ 12'-0' :.::... . \ ...·. ... / . ... x 'i,;. :. .

:...•I;-.._.. ..,...... ..•..

·: ..t::

r..·.-::·.· ·:".L l> t::. . l> 4

.. l> .. 4 . .

l> 4

4. l>

•J> .l>

. 4

. ,, : 4 - .. l> '-./ ·4

... l>· 't::.

·4

4 l>

·l> 4 t::.

l>-

·l.>.

4 l>· -l> >\ l> . t::.

. .4 . l> > '...'.. .. ":. ·.1

· .·;.:i-

.•.i..-"

DEPARTMENT OF THE AIR FORCE rI I 1\ I I:;-n j t·,I n, :;r AIR MOBILITY COMMAND

DRAWING REVISIONS

CHUGACH GOVERNMENT SERVICES

DEL .DEL . JB

REV. DESCRIPTION PREP BY DATE APPR'D

R EPAIR RV DUMP STATI ON

SHO RTSTAY

DETA I LS

1 REVISED - ADDED 2ND TANK DEL 23JUL13 JB

2 REVISED-SWAPPED DRAIN HOLES DEL 2-4JUL13 JB

3 REVISED DEL 31JUL13 JB

4 REVISED- AS BUILT SURVEY PLS 22JAN15 JB

JB FOR JOINT BASE CHARLESTON

· .• ·.?• .;to.

Tank Level Calculations