This is a technical specifications document for the Muddy Creek Restoration Project issued by the West Virginia Department of Environmental Protection (WVDEP), Office of Special Reclamation. The project encompasses four distinct components: Project 1 (Lift Station), Project 2 (Preston Energy & Geotube Pad), Project 3 (Force Main), and Project 4 (Gravity AMD collection system), located in Preston County, West Virginia near the community of Ruthbelle off WV Route 26. The work involves construction of acid mine drainage (AMD) collection lines, geotube pads, pump stations, mine seals, and road systems across multiple mining permit areas (Viking Coal Co., Preston Energy, and Rockville Mining Co.). Project 1 has a 200-calendar-day contract period with a 15-month contract term; Project 2 requires 150 calendar days with a 15-month term; Projects 3 and 4 each require 200 calendar days with 15-month terms. The document establishes comprehensive specifications for mobilization, site preparation, quality control, sediment control, revegetation, electrical installation, and equipment installation, with detailed requirements for material standards, testing protocols, environmental compliance, and contractor responsibilities.

The specifications require the contractor to assume all costs for temporary facilities, utilities, equipment, materials, labor, and environmental controls, including dust control, erosion management, and water pollution prevention. Lump sum bid items are capped at specific percentages of the total contract amount: Mobilization and Demobilization (maximum 2%), Site Preparation (maximum 2%), Administration (maximum 3%), Construction Layout (maximum 1%), and Quality Control (maximum 1%). The contractor must comply with West Virginia Department of Transportation (WVDOT) Standard Specifications, AASHTO standards, ASTM testing standards, and OSHA regulations. All fill materials shall be compacted to specified densities (90-98% depending on application), with mandatory third-party laboratory testing at minimum frequencies of three tests per day during placement. The contract requires submission of detailed schedules, shop drawings, operating and maintenance manuals, and as-built plans prior to final inspection and substantial completion.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VIKING COAL CO., PERMIT UO-519

PRESTON ENERGY, PERMIT UO-235

ROCKVILLE MINING CO.,

PERMIT S-91-85

MUDDY CREEK RESTORATION

Project 1 Lift Station

Project 2 Preston Energy & Geotube Project 3 Force Main

Project 4 Gravity

SPECIAL PROVISIONS

TECHNICAL SPECIFICATIONS

MARCH 2017

VIKING COAL CO., PERMIT UO-519

PRESTON ENERGY, PERMIT UO-235

ROCKVILLE MINING CO.,

PERMIT S-91-85

MUDDY CREEK RESTORATION

Project 1 Lift Station

Project 2 Preston Energy & Geotube Project 3 Force Main

Project 4 Gravity

SPECIAL PROVISIONS

MARCH 2017

i

SPECIAL PROVISIONS

TABLE OF CONTENTS

SECTION NO. SECTION TITLE

0-0 PROJECT INFORMATION

0-1 SCHEDULE OF VALUES

0-2 COORDINATION AND MEETINGS

0-3 TEMPORARY FACILITIES AND UTILITIES

0-4 PROTECTION OF PROPERTY

0-5 ENVIRONMENTAL CONTROL

0-6 GENERAL MAINTENANCE AND CLEANING

0-7 TESTING, ADJUSTING, AND BALANCING

0-8 OPERATIONAL DEMONSTRATION

0-9 CONTRACT CLOSEOUT

0-10 PROJECT RECORD DOCUMENTS

0-11 SUBMITTALS

0-12 OPERATING AND MAINTENANCE INSTRUCTIONS

0-13 ALTERNATIVES (ENGINEER APPROVED EQUAL)

0-14 ADMINISTRATION

0.0 - 1

0-0 PROJECT INFORMATION

1.0 LOCATION / SITE DESCRIPTION

The project is located in Preston County, West Virginia (WV) near the community of Ruthbelle. The project is located off WV Route 26.

The project will involve but is not limited to the construction of AMD collection lines, geotube pads, pump station, mine seals and installation and maintenance of road systems.

DIRECTIONS TO THE SITE:

From Morgantown, WV follow I-68 (Bruceton Mills exit) take WV Route 26 South for approximately 6 miles to Valley Point, WV. The project runs from Valley Point along WV Route 26 and ends approximately ½ mile past the intersection of Muddy Fork Road (Preston County Route 17 and WV Route 26.

2.0 WORK PERFORMANCE PERIOD

A. Project 1(Lift Station): The “Contract Period” for the project is 200 calendar days commencing on the date as defined in the Notice to Proceed letter. This period is defined as the amount of contract time allowed by the WVDEP for substantial completion of the project.

B. Project 2 (Preston Energy & Geotube Pad): The “Contract Period” for the project is 150 calendar days commencing on the date as defined in the Notice to Proceed letter. This period is defined as the amount of contract time allowed by the WVDEP for substantial completion of the project.

C. Project 3 (Force Main): The “Contract Period” for the project is 200 calendar

D. Project 4 (Gravity): The “Contract Period” for the project is 200 calendar

The “Contract Period” shall comply with Standard Specifications Section 14 Determination and Extension of Contract Time.

A095682 Typewritten Text

0.0 - 2

3.0 CONTRACT TERM

A. Project 1 (Lift Station): The “Contract Term” for the project is 15 months commencing on the date as defined in the Notice to Proceed letter. The Contract Term defines the beginning and end dates of the contract, and shall remain valid beyond the “Contract Period” for administrative purposes.

B. Project 2 (Preston Energy & Geotube Pad): The “Contract Term” for the project is 15 months commencing on the date as defined in the Notice to Proceed letter. The Contract Term defines the beginning and end dates of the contract, and shall remain valid beyond the “Contract Period” for administrative purposes.

C. Project 3 (Force Main): The “Contract Term” for the project is 15 months

D. Project 4 (Gravity): The “Contract Term” for the project is 15 months

4.0 REFERENCE SPECIFICATIONS / DEFINITIONS

All references to "Owner" in these Specifications shall mean West Virginia Department of Environmental Protection, Office of Special Reclamation (WVDEP).

All references to "Engineer" in these Specifications shall mean the WVDEP's Engineer or authorized representative.

All references to "ASTM" shall mean the American Society of Testing and Material Specifications, Latest Edition unless otherwise noted.

All references to "AASHTO Specifications" shall mean the Standard Specifications for Transportation Materials and Methods of Sampling and Testing by the American Association of State Highway and Transportation Officials, latest edition, and all subsequent addenda thereto.

All references to "WVDOH Standard Specifications" shall mean State of West Virginia Department of Transportation, Division of Highways Standard Specifications for Roads and Bridges, adopted 2010, and all-subsequent addenda thereto.

All references to the "Contractor" shall be understood to mean the successful bidder and or firm or corporation undertaking the execution of the work under the terms of these Specifications.

0.0 - 3

All references to "OSHA" shall be understood to mean The Occupational Safety and Health Administration and the standards set in the Occupational Safety and Health Act of 1970.

All references to “AMD” shall be understood to mean all acid mine drainage discharges from the project site.

5.0 SCOPE OF WORK

The Contractor shall perform all operations necessary for:

A. Project 1 (Lift Station): The project consists of constructing the AMD lift station as depicted in the plans. The contractor shall be responsible for the piping from MH F-1 and MH V-1 to the wet well and provide a flange connection outside the fence for the Force Main. The MHs will be by other Contractors. All components within the fence boundary, inclusive of the fence shall be completed with this contract. A stabilized construction entrance off Route 26 shall be a part of this contract. The contractor shall work with the WVDEP and the local power company to bring power to the site.

B. Project 2 (Preston Energy & Geotube Pad): The project consists of rehabilitating three mine seals, collection system with flow meter, and final grading of the Preston Energy site as depicted on the plans. Construct a new Geotube Pad on the west side of Route 26 across Muddy Creek from the new AMD Plant and a siphon system to collect and transport AMD from a seep on the west side of Muddy Creek.

C. Project 3 (Force Main): The project consists of installing a 10” HDPE SDR- 11 Force Main with Fiber Optic Cable for communications from the Flange at the AMD Lift Station to designated MHs shown on the plans. The project includes two road bores and two stream crossings. Install a pH meter system at Martin Creek at the location depicted on the plans. The Contractor shall be responsible for necessary Fiber Optic Connections at the Electric MH, at pH meter system, and at the Lift Station.

D. Project 4 (Gravity): The project consists of an AMD gravity collection system from Viking site to MH V-1 inclusive of MH V-1. Install an AMD gravity collection system for the Listen Portals to MH F-1 inclusive of MH F-1.

Additional work on this project includes Viking reclamation, mine seal, seep collector, Route 26 road bore, Fickey Run AMD dike containment area, and stream relocation.

The Contractor shall also be responsible for surveying, including establishing construction baseline, measuring and developing all completed quantities on the job, and for ordering, purchase and delivery of any and all materials required for construction or required for development of support areas. The Contractor shall

0.0 - 4 perform all other operations as incidental to the program as specified herein.

6.0 SCHEDULE OF WORK

Before commencing work on this project, the Contractor shall prepare and submit a schedule of construction activities for approval by the WVDEP. The WVDEP requires that minimal treatment of the acid mine drainage continue during the construction of the facility. The sequence of construction is listed in Section 6.0 of this Specification. The Contractor will be required to maintain access at all times to the facility, and upon completion of the project the access road condition shall be equal to or better than existed upon mobilization activities.

The Contractor shall provide adequate supervision, labor, tools, equipment, and materials to prosecute the work energetically and complete the work within the time specified. The Contractor shall demonstrate to the Engineer that sufficient sized and quantity of equipment shall be mobilized to ensure this Project is completed within specified time frames or sooner. The required Schedule to be submitted (mentioned above) shall include a list of said properly sized and quantity of equipment, along with projected earth moving and excavation capabilities as well as hauling, and grading rates to complete the tasks herein specified within stated time frames.

The WVDEP has no intention to delay the work for the checking of lines or grades, but if necessary, working operations shall be suspended for such reasonable time as the Engineer may require for the purpose. No special compensation shall be paid for the cost to the Contractor for any of the work or delay occasioned by checking lines and grades, by making other necessary measurements, or by inspection.

7.0 SEQUENCE OF CONSTRUCTION

1. Sequence of construction will be discussed for each project at the Pre-Bid Conference.

8.0 BORROW (DISPOSAL) AREAS

All borrow (disposal) areas must be approved by WVDEP. Should the Contractor decide to obtain and utilize any borrow areas outside of construction limits, or move material from one property owner to another (unless designated), the Contractor shall be responsible to obtain (from the property owner(s) of the borrow areas) all necessary rights of entry, including rights of entry for WVDEP and OSMRE for inspection purposes. The said rights of entry agreement must state that the property owner(s) indemnify and hold harmless the WVDEP for Contractor’s action for any injury or damages whatsoever resulting from the use of the property.

The Contractor also shall submit borrow or waste area reclamation plans for prior approval by WVDEP. The Contractor shall observe the following NEPA compliance schedule relative to selecting and utilizing any off site borrow areas and or any

0.0 - 5 waste disposal areas.

A. No borrow (disposal) site operations will affect a site listed in, eligible or proposed to be listed in the National Register of Historic Places.

B. No borrow (disposal) operations will be located within one-quarter mile of any federally listed established or prospective component of the National Wild and Scenic River System under 16 USC 1274 and 1276.

C. Borrow (disposal) site operations will not cause a significant encroachment within the base floodplain (CE.O. 11988: Floodplain Management).

D. Borrow (disposal) site operations will not be located in or affect a critical habitat of a Federally listed endangered or threatened species under 16 USC 1531, et. seq.

E. No borrow (disposal) operations will occur in wetland areas which are designated by appropriate agencies.

F. Borrow (disposal) site operations will be consistent with any approved plans governing ambient air quality.

G. Adherence to these mitigation measures does not relieve the Contractor of the obligation or responsibility to obtain any other Federal, State, or local approvals required to use borrow (disposal) areas and conduct such activities.

H. Documentation: Copies of borrow (disposal) site approvals and concurrences will be submitted to the WVDEP prior to the commencement of reclamation

I. Site Monitoring: Borrow (disposal) activities will be monitored by the State to ensure compliance with contractual requirements, applicable Federal, State, and local laws, and any permit conditions.

9.0 DISPOSAL OF UNSUITABLE MATERIAL

All disposal areas shall be obtained in accordance with Section 7.0 of this Specification. All unsuitable materials (wood, trash, debris, and garbage) as determined by the Engineer, shall be wasted by the Contractor, at the Contractor’s expense, outside the limits of work conforming to the requirements of the applicable sub-sections of Section 7.0 of this Specification. Wood may be burned in designated areas in conformity with Technical Specifications Section 4-01 Site Preparation.

Coal, coal refuse, black or dark gray shales, and exposed coal seams and other similar potentially toxic (acidic) materials shall be soil covered on-site and in accordance with these Specifications.

0.0 - 6

The Contractor shall observe the NEPA compliance schedule relative to selecting and utilizing any off-site disposal areas in accordance with Section 7.0 of this Specification.

10.0 WATER SUPPLY

There is no potable water available at the site. Arrangements for water supply shall be made by the Contractor, and all costs for such arrangements shall be borne by the Contractor at no additional cost to the department.

11.0 UTILITIES AND OTHER OBSTRUCTIONS

The name, address, and phone number of the WVMIS Utility location service and of the utility companies are as follows:

WV 811 Formally WV Miss Utility 811 or 1-800-245-4848

MonPower 237 Hartman Run Road

Morgantown, WV 26505 1-800-686-0022

Frontier Communications 214 Monroe Street

Fairmont, WV 26554 1-304-935-3121

Chesapeake Energy (Natural Gas Co.)

1-888-460-0003

12.0 CITATION OF OTHER SPECIFICATIONS

Whenever the Specifications for this Contract refer to the specifications of any society, institute, association or government organization, then such specifications cited shall become a part of this Contract as if written in full. Commonly used abbreviations have the following meanings:

ASTM - American Society for Testing Materials

ASA - American Standards Association

AWWA - American Water Works Association

AASHTO - American Association of State Highway and Transportation Officials

0.1-1

0-1 SCHEDULE OF VALUES

1.0 GENERAL

1.1 SECTION INCLUDES

A. Schedule of Values

1.2 RELATED SECTIONS

A. Special Provisions Section 0-11 Submittals.

1.3 SCHEDULE OF VALUES

A. Submit typed Schedule of Values in duplicate to the WVDEP Engineer at the Pre-Construction meeting for approval.

B. Format: Identify each line item with number and title of the major specification Section. Upon request, the WVDEP shall provide the Contract of an example format.

C. The Schedule of Values shall allocate a dollar value (cost) for each

Activity of the Detailed Construction Network. Each Activity cost allocation shall include labor, equipment, and material costs, including a pro rata contribution for overhead and profit. The sum of all Activity costs shall be equal to the total Contract Sum. Each Activity cost shall be coded by the Contractor, to show which subcontractor is responsible for performing the Work so that subtotals for each coded activity of the Work can be prepared. The Contract Pay Item for each Activity shall be indicated. The sum of costs for each Pay Item shall equal the value submitted with the Contractor's proposal.

D. Revise schedule to list approved Change Orders, with each Application for

Payment.

E. In the event the Contractor does not wish to provide a Schedule of Values, the Contractor shall provide to the WVDEP a letter stating such, and will be paid when the lump sum bid item is 100% complete.

F. The Contractor shall provide to the WVDEP either a Schedule of Values or a letter as described in Section 1.3.E of this specification as a condition of approval for the first invoice of the contract.

END OF SECTION

0.2-1

0-2 COORDINATION AND MEETINGS

1.1 DESCRIPTION

A. This Section includes general requirements for the conduct and coordinating responsibility of routine and special meetings which will occur throughout the completion of the Work.

1.2 RELATED SECTIONS

A. General Conditions

1.3 COORDINATION

A. The Contractor shall coordinate scheduling, notifications, submittals, and

Work of the various Sections of specifications to assure efficient and orderly sequence of installation of interdependent construction elements.

The Contractor shall be responsible for the Work of Sub-Contractors and insure that the Work is in accordance with the Contract Documents.

B. The Contactor shall verify that utility requirement characteristics of operating equipment are compatible with building utilities. Coordinate work of various Sections having interdependent responsibilities for installing, connecting to, and placing in service, such equipment.

C. The Contractor shall coordinate space requirements and installation of mechanical and electrical work which are indicated diagrammatically on Drawings. Follow routing shown for pipes, ducts, and conduit, as closely as practicable; place runs parallel with line of building. Utilize spaces efficiently to maximize accessibility for other installations, for maintenance, and for repairs.

D. In finished areas, the Contractor shall conceal pipes, ducts, and wiring within the construction. Coordinate locations of fixtures and outlets with finish elements.

E. The Contractor shall coordinate completion and clean up of Work of separate Sections in preparation for Substantial Completion and for portions of Work designated for WVDEP occupancy.

F. After WVDEP occupancy of premises, the Contractor shall coordinate access to site for correction of defective Work and Work not in

0.2-2 accordance with Contract Documents, to minimize disruption of WVDEP's

G. The Contractor shall coordinate the notification and scheduling of all inspections and testing of the Work.

1.4 PRE-CONSTRUCTION CONFERENCE

A. The purpose of the Pre-Construction Conference is to review and assure understanding of the requirements of the construction Contract; to establish clear lines of communication among the various parties involved in the construction; and to introduce the administrative procedures and level of responsibility which will govern the relationship among the parties during the course of the Work.

B. The Contractor shall provide submittals required, be prepared to discuss all items on the agenda, and notify his Subcontractors and Suppliers.

C. Attendance Required:

1. WVDEP Engineer.

2. WVDEP Inspector.

3. Contractor’s Onsite Foreman or Superintendent.

4. Representatives of Government Agencies having any form of jurisdiction, if Applicable.

D. Agenda:

1. Contractor shall provide a list of Sub-Contractors.

2. Contractor shall provide a list of Suppliers.

3. Contractor shall provide a Schedule of Work.

4. Contractor shall provide a Schedule of Values.

5. Contractor shall provide a list of equipment or materials to be submitted as Engineer Approved Equals. See Special Provisions 0- 13 Alternatives (Engineer Approved Equal).

6. Discussion of Contract Documents.

7. Coordination, procedures, and processing of field decisions, submittals, applications for payments, and Change Orders.

8. Scheduling, progress meeting requirements and milestone dates, if

Applicable.

9. Procedures for inspection and testing of Work. Contractor shall supply list of inspection and testing firms. Scheduling activities of inspection, testing and geotechnical consultants, If Applicable.

10. Review the WVDEP and Contractor’s occupancy and use of the project site, If Applicable.

11. Field offices and temporary utilities, If Applicable.

0.2-3

12. Safety, Security and housekeeping procedures.

13. Procedures for maintaining record documents, If Applicable.

14. Requirements for start-up of equipment, If Applicable.

15. Contract Closeout Requirements.

1.5 PROGRESS MEETINGS

A. The purpose of the meetings is to monitor and maintain the progress of the Work quality and schedule; and to facilitate the analysis, discussion, and planning of solutions for problems that might arise in the execution of the Work.

B. The WVDEP Inspector shall schedule and administer progress meetings during the project at intervals as otherwise determined by project size, and prepare and supply the meeting agenda to the WVDEP Engineer and the Contractor’s Superintendent (Foreman). To the maximum extent possible, the Contractor and the WVDEP Inspector shall identify items to be added to the agenda at least 24 hours in advance of the Contract meeting regarding all items to be added to the agenda.

C. The Contractor shall make arrangements for the meetings. The WVDEP

Inspector will preside at meetings and record notes on daily inspection log. The daily log will be available to the Contractor upon request. To the maximum extent practical, the progress meetings shall be held at the Contractor’s field office on the site, when a field office is utilized.

D. Contractor shall provide an itemized list of work completed since the last progress meeting. Items on the list shall be tied to the detailed construction network.

E. Attendance Required:

1. Contractor Superintendent or Foreman.

2. WVDEP Inspector.

3. WVDEP Engineer.

F. Agenda:

1. Review of Work progress to date and Construction Schedule compliance.

2. Field observations, problems, and decisions.

a. Inspector’s Comments.

b. Engineer’s Comments.

c. Contractor’s Comments.

3. Proposed Changes and Clarifications.

4. Review of submittals schedule and status of submittals.

0.2-4

5. Review of Major Equipment and off-site fabrication delivery schedules, If Applicable.

6. Quality Control, If Applicable

a. Defective/Deficient Items

b. Inspection and Testing Reports

7. Construction Schedule

a. Planned progress for the next 2 and 4 succeeding weeks.

b. Corrective measures to regain projected schedules.

c. Coordination of projected progress.

8. Action Items

a. Proposed Changes

b. Corrective Measures

c. Submittals

9. Other business relating to Work.

G. The Contractor is responsible for any and all discussions and relations between subcontractors and material suppliers. These discussions or relations shall not be a part of progress meeting contents.

H. The individual designated by the Contractor to attend and participate in progress meetings shall have all required authority to commit the Contractor to solutions as agreed upon in the progress meetings.

1.6 PRE-INSTALLATION CONFERENCES

A. When required in individual specification Section, convene a pre-installation conference at work site prior to commencing work of the Section.

B. Required attendance:

1. Contractor Superintendent or Foreman.

2. WVDEP Inspector or Engineer.

C. The Contractor shall notify the Engineer and the WVDEP Inspector five days in advance of meeting date.

D. The Contractor shall prepare the agenda and preside at conference. The

WVDEP Inspector shall record pertinent meeting information on the daily inspection report.

E. Review conditions of installation, preparation and installation procedures, and coordination with related work.

0.2-5

2.0 EXECUTION

2.1 SMOKING

All meetings, including casual meetings, shall be non-smoking occasions.

Smoking will not be permitted in field offices, other offices, and lunch/break rooms, and shall be restricted to designated physically separate smoking areas.

All conference rooms, conference areas, and computer and control equipment installation areas shall be non-smoking areas. Smoking in existing facilities or work areas shall be only in approved areas designated by the WVDEP Inspector.

All smoking shall also be restricted by applicable law or regulation which may exceed the requirements of this paragraph.

0.3-1

0-3 TEMPORARY FACILITIES AND UTILITIES

Contractor shall be responsible for all temporary facilities and utility services used during construction, inclusive of subcontractors and all utility services required for the Work, including operational demonstration. The Contractor shall make all arrangements required with the utility companies and pay all costs attendant to the service except as otherwise provided herein.

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract apply to this Section.

1.2 SUMMARY

A. This Section specifies requirements for temporary services and facilities, including utilities, construction and support facilities, security and protection.

B. Temporary utilities include but are not limited to:

1. Potable water, includes temporary construction water supply, water for testing, flushing, and cleaning, If Applicable.

2. Sanitary Facilities, If Applicable.

3. Electricity and Lighting, If Applicable.

4. Telephone, If Applicable.

5. Temporary Heat, If Applicable.

6. Site Access, If Applicable.

C. Temporary construction and support facilities include but are not limited to:

1. Temporary heat.

2. Field offices and storage sheds.

4. Sanitary facilities, including drinking water.

5. Dewatering facilities and drains.

6. Temporary enclosures.

7. Temporary Project identification signs and bulletin boards.

8. Waste disposal services.

9. Rodent and pest control.

10. Construction aids and miscellaneous services and facilities.

D. Security and protection facilities required include but are not limited to:

1. Environmental protection.

0.3-2

1.3 QUALITY ASSURANCE

A. Regulations: Comply with industry standards and applicable laws and regulations of authorities having jurisdiction, including but not limited to:

1. Building Code requirements.

2. Health and safety regulations.

3. Utility company regulations.

4. Police, Fire Department and Rescue Squad rules.

5. Environmental protection regulations.

B. Standards: Comply with NFPA Code 241, "Building Construction and

Demolition Operations", ANSI-A10 Series standards for "Safety Requirements for Construction and Demolition", and NECA Electrical Design Library "Temporary Electrical Facilities."

1. Refer to "Guidelines for Bid Conditions for Temporary Job Utilities and

Services", prepared jointly by AGC and ASC, for industry recommendations.

2. Electrical Service: Comply with NEMA, NECA and UL standards and regulations for temporary electric service. Install service in compliance with National Electric Code (NFPA 70).

C. Inspections: Arrange for authorities having jurisdiction to inspect and test each temporary utility before use. Obtain required certifications and permits.

1.4 PROJECT CONDITIONS

A. Conditions of Use: Keep temporary services and facilities clean and neat in appearance. Operate in a safe and efficient manner. Take necessary fire prevention measures. Do not overload facilities, or permit them to interfere with progress. Do not allow hazardous dangerous or unsanitary conditions, or public nuisances to develop or persist on the site.

2.0 PRODUCTS

2.1 MATERIALS

A. General: Provide new materials; if acceptable to the Engineer, undamaged previously used materials in serviceable condition may be used. Provide materials suitable for the use intended.

B. Lumber and Plywood: Comply with applicable industry standards.

1. For job-built temporary offices, shops and sheds within the construction area, provide UL labeled, fire treated lumber and

0.3-3 plywood for framing, sheathing and siding.

2. For signs and directory boards, provide exterior type, Grade B-B High

Density Concrete Form Overlay Plywood conforming to PS-1, of sizes and thickness indicated.

C. Paint:

1. For job-built temporary offices, shops, sheds, fences and other exposed lumber and plywood, provide exterior grade acrylic-latex emulsion over exterior primer.

2. For sign panels and applying graphics, provide exterior grade alkyd gloss enamel over exterior primer.

3. For interior walls of temporary offices, provide two coats interior latex flat wall paint.

D. Tarpaulins: Provide waterproof, fire-resistant, UL labeled tarpaulins with flame-spread rating of 15 or less. For temporary enclosures provide translucent nylon reinforced laminated polyethylene or polyvinyl chloride fire retardant tarpaulins.

2.2 EQUIPMENT

A. General: Provide new equipment; if acceptable to the Engineer, undamaged, previously used equipment in serviceable condition may be used. Provide equipment suitable for use intended.

B. Electrical Outlets: Provide properly configured NEMA polarized outlets to prevent insertion of 110-120 volt plugs into higher voltage outlets. Provide receptacle outlets equipped with ground-fault circuit interrupters, reset button and pilot light, for connection of power tools and equipment.

C. Electrical Power Cords: Provide grounded extension cords; use

"hard-service" cords where exposed to abrasion and traffic. Provide waterproof connectors to connect separate lengths of electric cords, if single lengths will not reach areas where construction activities are in progress.

D. Lamps and Light Fixtures: Provide general service incandescent lamps of wattage required for adequate illumination. Provide guard cages or tempered glass enclosures, where exposed to breakage. Provide exterior fixtures where exposed to moisture.

E. Heating Units: Provide temporary heating units that have been tested and labeled by UL, FM or another recognized trade association related to the type of fuel being consumed.

F. Temporary Offices: Provide prefabricated or mobile units or similar job-built

0.3-4 construction with lockable entrances, operable windows and serviceable finishes. Provide heated and air-conditioned units on foundations adequate for normal loading.

G. Temporary Toilet Units: Provide self-contained single-occupant toilet units of the chemical, aerated recirculation, or combustion type, properly vented and fully enclosed with a glass fiber reinforced polyester shell or similar nonabsorbent material.

H. First Aid Supplies: Comply with governing regulations.

I. Fire Extinguishers: Provide hand-carried, portable UL-rated, class "A" fire extinguishers for temporary offices and similar spaces. In other locations provide hand-carried, portable, UL-rated, class "ABC" dry chemical extinguishers, or a combination of extinguishers of NFPA recommended classes for the exposures.

1. Comply with NFPA 10 and 241 for classification, extinguishing agent and size required by location and class of fire exposure.

3.0 EXECUTION

3.1 INSTALLATION

A. Use qualified personnel for installation of temporary facilities. Locate facilities where they will serve the Project adequately and result in minimum interference with performance of the Work. Relocate and modify facilities as required.

B. Provide each facility ready for use when needed to avoid delay. Maintain and modify as required. Do not remove until facilities are no longer needed, or are replaced by authorized use of completed permanent facilities.

3.2 TEMPORARY UTILITY INSTALLATION

A. General: Engage the appropriate local utility company to install temporary service or connect to existing service. Where the company provides only part of the service, provide the remainder with matching, compatible materials and equipment; comply with the company's recommendations.

1. Arrange with the company and existing users for a time when service can be interrupted, where necessary, to make connections for temporary services.

2. Provide adequate capacity at each stage of construction. Prior to temporary utility availability, provide trucked-in services.

3. Obtain easements to bring temporary utilities to the site, where the

0.3-5

WVDEP's easements cannot be used for that purpose.

4. Use Charges: Cost or use charges for temporary facilities are not chargeable to the WVDEP, and will not be accepted as a basis of claims for a Change Order.

5. The Contractor shall be responsible for all utility costs necessary for operational demonstration of all new facilities and systems until substantially complete and ready for operation. This shall include the costs for electricity, potable water, fuel, lubricants, chemicals, and expendables.

6. Contractor shall abide by all rules and regulations of the utility or authority having jurisdiction.

B. Temporary Electric Power Service: Provide weatherproof, grounded electric power service and distribution system of sufficient size, capacity, and power characteristics during construction period. Include meters, transformers, overload protected disconnects, automatic ground-fault interrupters and main distribution switch gear.

1. Power Distribution System: Install wiring overhead, and rise vertically where least exposed to damage. Where permitted, wiring circuits not exceeding 125 Volts, AC 20 ampere rating, and lighting circuits may be nonmetallic sheathed cable where overhead and exposed for surveillance.

2. The Contractor shall obtain construction power through the power company. The Contractor shall provide all labor and material necessary to furnish and install the construction power and temporary lighting services. The temporary service shall conform to all applicable provisions of the Contract Specifications, except the equipment need not be new, but shall be in serviceable condition and installed in a safe manner.

C. Temporary Telephones: Provide temporary telephone service for all personnel engaged in construction activities, throughout the construction period. Install telephone on a separate line for each temporary office and first aid station.

1. The Contractor shall provide and pay for telephone or communication systems required. The Contractor shall be responsible for coordinating installations of telephone service with the telephone company. Use of the existing telephone service is prohibited.

2. At each telephone, post a list of important telephone numbers.

D. Provide earthen embankments, diversion ditches and similar barriers in and around excavations and subgrade construction, sufficient to prevent flooding by runoff of storm water from heavy rains.

0.3-6

3.3 TEMPORARY CONSTRUCTION AND SUPPORT FACILITIES INSTALLATION

A. Locate field offices, storage sheds, sanitary facilities and other temporary construction and support facilities for easy access.

1. Maintain temporary construction and support facilities until near

Substantial Completion. Remove prior to Substantial Completion.

Personnel remaining after Substantial Completion will be permitted to use permanent facilities, under conditions acceptable to the Owner.

B. Provide incombustible construction for offices, shops and sheds located within the construction area, or within 30 feet of building lines. Comply with requirements of NFPA 241.

C. Temporary Heat: Provide temporary heat required by construction activities, for curing or drying of completed installations or protection of installed construction from adverse effects of low temperatures or high humidity.

Select safe equipment that will not have a harmful effect on completed installations or elements being installed. Coordinate ventilation requirements to produce the ambient condition required and minimize consumption of energy.

D. Heating Facilities: Except where use of the permanent system is authorized, provide vented self-contained LP gas or fuel oil heaters with individual space thermostatic control.

1. Use of gasoline-burning space heaters, open flame, or salamander type heating units is prohibited.

E. Field Offices: Provide insulated, heated, weathertight temporary offices of sufficient size to accommodate required office personnel at the Project site.

Keep the offices clean and orderly for use for small progress meetings.

Furnish and equip each office as follows:

F. Storage and Fabrication Sheds: Install storage and fabrication sheds, sized, furnished and equipped to accommodate materials and equipment involved, including temporary utility service. Sheds may be open shelters or fully enclosed spaces within the building or elsewhere on the site.

G. Temporary Paving: Construct and maintain temporary roads to adequately support the indicated loading and to withstand exposure to traffic during the construction period. Locate temporary paving for roads, storage areas and parking where the same permanent facilities will be located. Review proposed modifications to permanent paving with the Engineer.

H. Sanitary facilities include temporary toilets, wash facilities and drinking water

0.3-7 fixtures. Comply with regulations and health codes for the type, number, location, operation and maintenance of fixtures and facilities. Install where facilities will best serve the Project's needs.

1. Provide toilet tissue, paper towels, paper cups and similar disposable materials for each facility. Provide covered waste containers for used material.

2. Sanitary facilities will not be furnished to the Contractor by the WVDEP. The Contractor shall provide all labor and material necessary to furnish and install its own temporary water and sanitary sewer service for the Work and to field offices, and shall pay all relevant fees and charges.

I. Toilets: Install self-contained toilet units. Shield toilets to ensure privacy.

Use of pit-type privies will not be permitted.

K. Dewatering Facilities and Drains: For temporary drainage and dewatering facilities and operations not directly associated with construction activities included under individual Sections, comply with dewatering requirements of applicable Technical Specifications Sections 5-0, 6-0, and 7-0. Where feasible, utilize the same facilities. Maintain the site, excavations and construction free of water.

L. Temporary Enclosures: Provide temporary enclosure for protection of construction in progress and completed, from exposure, inclement weather, other construction operations and similar activities.

1. Where heat is needed and the permanent building enclosure is not complete, provide temporary enclosures where there is no other provision for containment of heat. Coordinate enclosure with ventilating and material drying or curing requirements to avoid dangerous conditions and effects.

2. Install tarpaulins securely, with incombustible wood framing and other materials. Close openings of 25 square feet or less with plywood or similar materials.

3. Close openings through floor or roof decks and horizontal surfaces with load-bearing wood-framed construction.

M. Project Identification and Temporary Signs: Prepare project identification and other signs of the size indicated; install signs where indicated to inform the public and persons seeking entrance to the Project. Support on posts or framing of preservative treated wood or steel. Do not permit installation of unauthorized signs.

1. Project Identification Signs: Engage an experienced sign painter to apply graphics. Comply with details indicated.

0.3-8

2. Temporary Signs: Prepare signs to provide directional information to construction personnel and visitors.

N. Collection and Disposal of Waste: Collect waste from construction areas and elsewhere daily. Comply with requirements of NFPA 241 for removal of combustible waste material and debris. Enforce requirements strictly. Do not hold materials more than 7 days during normal weather or 3 days when the temperature is expected to rise above 80 deg F (27 deg C). Handle hazardous, dangerous, or unsanitary waste materials separately from other waste by containerizing properly. Dispose of material in a lawful manner.

3.4 OPERATION, TERMINATION AND REMOVAL

A. Supervision: Enforce strict discipline in use of temporary facilities. Limit availability of temporary facilities to essential and intended uses to minimize waste and abuse.

B. Maintenance: Maintain facilities in good operating condition until removal.

Protect from damage by freezing temperatures and similar elements.

1. Maintain operation of temporary enclosures, heating, cooling, humidity control, ventilation and similar facilities on a 24-hour day basis where required to achieve indicated results and to avoid possibility of damage.

2. Protection: Prevent water filled piping from freezing. Maintain markers for underground lines. Protect from damage during excavation operations.

C. Termination and Removal: Unless the Engineer requests that it be maintained longer, remove each temporary facility when the need has ended, or when replaced by authorized use of a permanent facility, or no later than Substantial Completion. Complete or, if necessary, restore permanent construction that may have been delayed because of interference with the temporary facility. Repair damaged Work, clean exposed surfaces and replace construction that cannot be satisfactorily repaired.

1. Materials and facilities that constitute temporary facilities are property of the Contractor. The WVDEP reserves the right to take possession of Project identification signs.

2. Where the area is intended for landscape development, remove soil and aggregate fill that does not comply with requirements for fill or subsoil in the area. Remove materials contaminated with road oil, asphalt and other petrochemical compounds, and other substances which might impair growth of plant materials or lawns. Repair or replace street paving, curbs and sidewalks at the temporary entrances, as required by the governing authority.

0.3-9

3. At Substantial Completion, clean and renovate permanent facilities that have been used during the construction period, including but not limited to:

a. Replace significantly worn parts and parts that have been subject to unusual operating conditions.

0.4-1

0-4 PROTECTION OF PROPERTY

A. Standard Specifications, Design Drawings, Technical Specifications, and Special Provisions of the Contract, apply to the work of this Section.

1.2 DESCRIPTION

A. Work Included

1. Protection and Maintenance of Public and Private Property

2. Protection of Trees and Plants

2.0 PRODUCTS (Not Applicable)

3.1 APPLICATION

A. Protection and Maintenance of Public and Private Property:

1. The Contractor, insofar as his work is concerned, shall protect all property, including but not limited to, driveways, buildings, fences, trees, flowers, shrubbery, guard rails, retaining walls, and other structures and for foundations and appurtenances along or adjacent to the line of work.

2. The Contractor, insofar as his work is concerned, shall protect, shore, brace, support and maintain all underground structures, pipes, mains, sewers, culverts, conduits, drains and their appurtenances.

3. The Contractor shall indemnify, defend and save harmless the Owner and Engineer against all damages, actual or alleged, arising out of (or incidental to the work.

4. All pavement, surfacing, driveway, curbs, walks, buildings, utility poles, guy wires and other surface structures affected by the construction operations in connection with the performance of the contract shall be restored to their original condition thereof as determined and approved by the Engineer.

5. All replacements of underground construction and surface structures or parts thereof shall be made with new materials conforming to the requirements of these specifications or, if not specified, as approved by the Engineer.

6. The Contractor shall be responsible for all damage to streets, roads, 0.4-2 highways, railroads, shoulders, ditches, embankments, culverts, bridges, power transmission lines, oil lines, gas lines, or other public or private property or facility, regardless of location or character, which may be caused by moving, hauling, or otherwise transporting equipment, materials, or men to or from the work or any part or site thereof, whether by the Contractor or the Contractor’s subcontractors.

The Contractor shall make satisfactory and acceptable arrangement with the owner of, or the agency or authority having jurisdiction over, the damaged property or facility concerning its repair or replacement or payment of costs incurred in connection with said damage.

B. Protection of Trees and Plants

1. During the project all the trees within the construction limits shall remain standing. The Contractor shall not deface, injure, or destroy trees or shrubs, nor remove or cut them without special authority. No ropes, cables, or guys shall be fastened to or attached to any existing nearby trees for anchorage unless specifically authorized. Where such special emergency use is permitted, the Contractor shall first adequately wrap the trunk with a sufficient thickness of burlap or rags over which softwood cleats shall be tied before any rope, cable, or wire is placed. The Contractor shall in any event be responsible for any damage resulting from such use.

2. Where, in the opinion of the Engineer, trees may possibly be defaced, bruised, injured, or otherwise damaged by the Contractor's equipment or by dumping, or other operations, the Engineer may direct the Contractor to protect adequately such trees by placing boards, planks, or poles around them. When earthwork operations are liable, in the opinion of the Engineer, to cause spoil to roll or otherwise be displaced into uncleared areas, the Contractor shall construct barriers of heavy planking to protect the trees. Spoil that is displaced into uncleared areas shall be removed.

3. Any trees or other landscape features scarred or damaged by the Contractor's equipment or operations shall be restored as nearly as possible to its original condition at the Contractor's expense. The Engineer will determine what methods of restoration shall be used, and whether damaged trees shall be treated and healed or removed and disposed of under requirements for clearing and grubbing.

4. All scars made on trees by equipment, construction operations, or by the removal of limbs larger than 1 inch in diameter shall be coated as soon as possible with an approved tree wound dressing. All trimming or pruning shall be performed in an approved manner by experienced workmen with saws or pruning shears. Tree trimming with axes will not be permitted. The use of climbing ropes will be required where deemed necessary for safety. Trees that are to remain that are subsequently damaged by the Contractor and are beyond saving in

0.4-3 the opinion of the WVDEP, shall be immediately removed and replaced with a nursery grown tree of the same species. The replacement tree shall be planted according to accepted practice of the American Association of Nurseryman during the proper season and be guaranteed to live for 1 full growing season.

C. Watchmen

1. Watchmen will not be provided by the WVDEP. The Contractor will be held responsible for loss or injury to persons or property where his work is involved, and shall provide such watchmen and take such precautionary measures as the Contractor may deem necessary to protect personnel interests.

0.5-1

0-5 ENVIRONMENTAL CONTROL

A. Standard Specifications, Design Drawings, Technical Specifications, and Special Provisions of the Contract, apply to work of this Section.

B. Seeding and mulching specifications for permanent seeding, including soil amendments, found in Technical Specifications Section 6-0 Revegetation are applicable to temporary seeding.

C. Description of Work

1. Environmental Protection

2. Land Resources Protection

3. Noise Control

4. Dust Control

5. Debris Control

6. Water Pollution Control

7. Sediment Control Plan

8. Erosion Control

9. Air Pollution

10. Protection of Archeological and Historical Findings

2.1 TEMPORARY SEEDING PRODUCTS

A. Seed, mulch and soil amendments used for temporary seeding shall be in accordance with the specifications for permanent seeding found in Technical Specifications Section 6-0 Revegetation.

3.1 APPLICATION

A. Environmental Protection

1. In order to prevent, and to provide for abatement and control of, any environmental pollution arising from the Contractor’s construction activities, the Contractor shall comply with all applicable Federal, State, and Local laws and regulations concerning environmental pollution control and abatements, as well as all specific requirements

0.5-2 stated elsewhere in the contract specifications.

2. The WVDEP will notify the Contractor in writing of any non-compliance with the foregoing provisions and the action to be taken. The Contractor shall, after receipt of such notice, immediately take corrective action. Such notice, when delivered to the Contractor or the Contractor’s authorized representative at the site of the work, shall be deemed sufficient for the purpose. If the Contractor fails or refuses to comply promptly, the WVDEP may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time loss due to any such stop orders shall be made the subject of a claim for extension of time or for excess costs or damages by the Contractor unless determination was made that the Contractor was in compliance.

a. The Contractor shall obliterate all signs of temporary construction facilities such as work areas, structures, foundations or temporary structures, stock-piles of excess waste materials, or any other vestiges of construction as directed. Any spoil above grade around the crown of trees and shrubs shall be removed. The disturbed areas shall be graded and filled as required, and seeded as specified herein.

b. During the life of this contract, the Contractor shall maintain all facilities constructed for pollution control under this contract as long as the operations creating the particular pollutant are being carried out or until the material concerned has become stabilized to the extent that pollution is no longer being created.

During the construction period the Contractor should conduct frequent training courses for maintenance personnel. The curricula should include methods of detection of pollution, familiarity with pollution standards, and installation and care of vegetation covers, plants and other facilities to prevent and correct environmental pollution.

B. Land Resources Protection

1. The intent is that the land resources within the project boundaries and outside the limits of permanent work performed under this contract be preserved to present condition or be restored to a condition after completion of construction that will appear to be natural and not detract from the appearance of the project. Insofar as possible, the Contractor shall confine the construction activities to areas defined by the plans and specifications.

C. Noise Control

1. Contractor shall comply with all Federal, State, or Local laws and

0.5-3 regulations concerning noise control.

D. Dust Control

1. The Contractor will be required to maintain all work sites, excavations, embankments, stockpiles, haul roads, permanent access roads, plant sites, waste areas, borrow areas, and all other work areas within or without the project boundaries free from dust which would cause a hazard or nuisance to others. Approved temporary methods of stabilization consisting of sprinkling, chemical treatment, light bituminous treatment, or similar methods will be permitted to control dust. Sprinkling, to be approved, must be repeated at such intervals as to keep all parts of the disturbed area at least damp at all times, and the Contractor shall have sufficient competent equipment on the job to accomplish this. Dust control shall be performed as the work proceeds and whenever a dust nuisance or hazard occurs.

2. Calcium chloride shall not be used for dust control.

E. Debris…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .