Appendix F - SOW DTA IGSA-CI 25-01 B229 PV Array.pdf
PDF 271 KB Posted
- Attached to
- B229 PV Array
- Solicitation number
- AEW-0170-0555
- Issued by
- Macomb County, Westland City, Michigan
About this file
This document is a Statement of Work (SOW) for an Inter-Governmental Service Agreement (IGSA) Capital Improvement Repair and Maintenance project between the City of Center Line and the United States Army Garrison - Detroit Arsenal. The project involves installing a roof-mounted photovoltaic (PV) array on Building 229 (B229), which is scheduled to have its roof replaced in spring 2025. The project is being solicited as Subject to the Availability of Funds (SAF), with proposals valid for 60 days from the opening date. The total project duration is estimated at 220 calendar days, with key milestones including project schedule submission within 5 days of Notice to Proceed (NTP), various plans submitted within 14 days of NTP, and construction substantially complete 30 days prior to final completion.
The project requires the contractor to provide all labor, materials, and equipment to install the PV array in coordination with the roof replacement, ensuring the roof warranty remains valid. Walkway mats compatible with the roof membrane must be installed. The project aims to assist the Army in meeting energy initiatives, with subcontractors required to have completed at least two similar projects. No government-furnished property is involved, and the contractor is responsible for providing all utilities, support services, and necessary permits. Environmental considerations include a requirement to recycle 60% of construction and demolition waste, comply with safety regulations, and prepare an Environmental Protection Plan. Specific safety training, including AT Level I awareness, iWATCH, and OPSEC training, is mandatory for all contractor employees.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFS CIRM 2025-01_ BLDG 229 PV ARRAY_DRAWINGS_BID ISSUE__250129.pdf | ||
| Appendix D - Asbestos Survey.pdf | ||
| Appendix G - ENG_FORM_4288-R.pdf | ||
| Appendix B - Rad Contractor Process.pdf | ||
| IMG_7927.JPG | JPG image | |
| IMG_7928.JPG | JPG image | |
| BLDG - 229 4TH FLR.pdf | ||
| IMG_7932.JPG | JPG image | |
| Appendix E - DTA-F-004-24_ClearancePermitRequest-v1.1 (new).pdf | ||
| BLDG - 229 3RD FLR.pdf | ||
| 00 20 00 - Request for Proposals.pdf | ||
| IMG_7925.MOV | MOV file | |
| Appendix C - Construction Impact Notification.pdf | ||
| IMG_7933.JPG | JPG image | |
| BLDG - 229 BASEMENT FLR.pdf | ||
| BLDG - 229 2ND FLR.pdf | ||
| IMG_7934.JPG | JPG image | |
| Appendix H - STA_Form17_FEB2024.v3.0_Single.pdf | ||
| 6-A Addenda #1_0170-0555_DTA B229_250218.pdf | ||
| IMG_7925.JPG | JPG image | |
| BLDG - 229 1ST FLR.pdf | ||
| IMG_7931.JPG | JPG image | |
| RFS CIRM 2025-01_ BLDG 229 PV ARRAY_SPEC_BID ISSUE__250129.pdf | ||
| IMG_7926.JPG | JPG image | |
| IMG_7930.JPG | JPG image | |
| IMG_7929.JPG | JPG image |
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 01 11 00
STATEMENT OF WORK
Version 1
Issued August 30, 2024
IGSA Capital Improvement Repair and Maintenance
Pre-RFP Draft Date: December 5, 2024
Revised: N/A
1. GENERAL DISCUSSION
1.1. Project Identification
1.1.1. Project Title: Install – B229 PV Array
1.1.2. Work Order Number(s): DTA001322
1.1.3. IGSA Order Number: IGSA-CI-25-01
1.1.4. IGSA Service Type: Bid-Build Service
1.2. Description of Work
1.2.1. The City of Center Line or its designated representative shall supply all supervision, labor, equipment, and materials to perform all work in strict accordance with IGSA-CI, this Statement of Work, and identified drawings and specifications to install a roof mounted PV array on building 229 as shown in the drawings and specifications (Reference: Appendix 3). The roof of B229 is being replaced in the spring of 2025 (schedule attached). Coordination with the roofing contractor and the Government is required prior to performing the installation of the PV array. The replacement of the roof is not included in this contract; however, walkway mats are required to be installed with mats that are compatible with the roof membrane. The warranty of the roof shall remain valid. The City of Center Line or its designated representative is responsible for maintaining the existing warranty. A schedule of the roof contract is included for reference with this RFP, the roof replacement is not included in this contract.
1.2.2. The proposals submitted from this RFP shall be valid for a duration of 60 days from the date of proposal opening. This project is being solicited as Subject to the Availability of Funds (SAF).
1.3. Area Description
1.3.1. Location: B229 Roof
1.3.2 Known Existing Site Conditions: The roof of B229 is being replaced in 2025, therefore in coordination with the roofing repair it is a good time to install a roof mounted PV array. The installation of a PV array on this roof will assist the Army in meeting energy initiatives.
2. PROJECT OBJECTIVES
2.1. Principal Items To Be Accomplished
2.1.1. Line Item 1 – Base Repair – Provide and install roof mounted PV Array on B229 as defined in the attached drawings and specifications (Reference: Appendix 3).
2.2 General Requirements:
The City of Center Line or its designated representative shall include all labor, materials, and equipment to perform all work in strict accordance with the umbrella contract specifications, this Statement of Work, and identified drawings to install a PV array system as shown in the drawings and specifications. The roof of building 229 is being replaced during the installation of the PV array system.
The contractor shall coordinate the installation with the roof replacement schedule for this building (B229). All roof penetrations and roof mat installation shall be performed by the roofing contractor to ensure the warranty of the roof remains in full effect. The roof assembly is Holcim Elevate 90 mil. For warranty purposes the installing contractor of the roof is Jason Prieskorn at 586-256-1356 or by email at jason@kjproofing.com.
2. PROJECT OBJECTIVES
2.1. General Notes:
2.1.2. The construction shall meet all the performance objectives listed in this IGSA request. The City of Center Line or its designated representative shall use record drawings, field investigations, and other pertinent data to determine existing conditions, demolition, and new work required to accomplish the work for this project.
2.2. Deliverables:
2.2.2. A submittal register using ENG4288 form or similar shall be maintained for the duration of the project in accordance with Unified Facilities Guide Specifications (01 33 00).
2.2.3. The City of Center Line or its designated representative shall provide a completed DD 1354 Transfer of Real Property for review by Master Planning. This form itemizes the types, quantities and costs of various equipment and systems that comprise the project, for the purpose of transferring the new project to the Installation's inventory of real property. A FINAL DD 1354 will be completed with final quantities and amounts prepared by the City of Center Line or its designated representative.
2.3. Field Inspection: The City of Center Line or its designated representative shall verify field conditions which are significant to design, by field inspection, researching, and obtaining all necessary existing facility as-built drawings.
2.4. Conferences: After contract award, the City of Center Line or its designated representative and the construction representatives shall attend the Preconstruction Conference at the Detroit Arsenal (DTA) Directorate of Public Works (DPW). The City of Center Line or its designated representative is responsible for ensuring that design review conferences can be attended virtually as well as in-person.
3. DESIGN
3.1. Designer of Record: Reserved.
mailto:jason@kjproofing.com
3.2. Constructor’s Role During Design: Reserved.
3.3. Review Comments: Reserved.
3.4. Released for Construction (RFC) Design: Reserved.
4. PERFORMANCE AND SCHEDULING
4.1. Performance Period Requirements
4.1.1. The performance periods and submission schedules for construction are indicated below. The Contactor shall furnish sufficient technical, supervisory, and administrative personnel to ensure the prosecution of the work in accordance with the submittal schedule. Days as mentioned shall be calendar days. The City of Center Line or its designated representative may choose to perform design work, at its own risk, during the Government review and comment resolution period.
However, comments resulting from that review must be incorporated into the design prior to the next submittal. In the event a subsequent design phase is not authorized, the City of Center Line or it’s designated representative shall incorporate all available review comments into the design to complete the current phase.
4.1.2. The time stated for construction completion includes final cleanup of the premises and submission of all required close-out documentation.
Schedule Requirements
Milestone Schedule Longest Path
Project Schedule 5 days after NTP -
Contractor Quality Control Plan 14 days after NTP -
Accident Prevention Plan 14 days after NTP -
Environmental Protection Plan (EPP) 14 days after NTP -
Schedule of Values 14 days after NTP -
Construction Substantially Complete 30 days prior to Construction Complete 190
Construction Complete 220 days from NTP 220
Total: 220 estimated calendar days 220
4.1.3. Prepare Project Schedule in accordance with Unified Facility Guide Specifications (UFGS) 01
32.01.00 10.
4.2. Award of Options
4.2.1. Award of Option Item(s): Reserved.
4.2.2. Duration of Option Items: Reserved.
4.3. Construction Phasing Requirement
4.3.1. During the performance of onsite construction activities, the contractor is permitted to work during the hours of 06:00 to 18:00 (6:00am to 6:00pm). Additional compensation for overtime will not be considered by the Government.
4.3.2. Work by other contractors is anticipated within the facility and the grounds of Detroit Arsenal. The contractor is required to coordinate work schedules with other contractors performing work within and around the building.
4.4 Government Incentives and Remedies
4.4.1 The City of Center Line or its designated representative shall perform all work in accordance with the requirements specified within this SOW. This section is in addition to any of the rights and remedies available to the Government under statute or law.
4.4.2. Remedies: In accordance with the IGSA-CIRM agreement.
5. APPENDICIES
5.1. All applicable appendices are listed in the table below. This list constitutes the entirety of this task order. Note that all specifications, codes, standards, and requirements listed within these documents are also applicable to this SOW.
Ref . Appendix Dated Notes
1 IGSA - CIRM 21-May-2024 Agreement provided to City of Center Line, listed here for reference only. No separate document provided.
2 01 11 00 Statement of Work 05-Dec-2024
3 Design Package 05-Dec-2024
A Installation Design Guide Rev. 3 30-Oct-2023 B Reserved
C Construction Impact Notification (CIN) 11-Dec-2023
D Asbestos Survey Spring 2019 Asbestos Survey
E Reserved
6. SPECIFICATIONS AND CODES
6.1. Codes
6.1.2. The most recent edition, at time of solicitation, of all pertinent Local, State, and Federal building and life/health/safety codes shall be used.
6.2. Specifications
6.2.2. The City of Center Line or its designated representative shall comply with all relevant specification sections.
6.2.3. The following UFC Specifications are considered particularly relevant to this project and shall be considered governing documents unless otherwise noted.
Section No. Specification Section Name
UFC 3-101-01 Architecture
UFC 1-200-
DoD Building Code
UFC 3-110-03 Roofing UFC 3-301-01 Structural Engineering UFC 3-501-01 Electrical Engineering
6.2.3 The below list of Technical Specification Sections (UFGS) that are anticipated to be applicable to this project and shall be included in the specifications for construction. An omission from this list does not relieve the City of Center Line or its designated representative from adhering to the specifications for that feature of work necessary to meet manufacturer's certification, the requirements of this SOW, and all applicable building codes. All specifications can be found on the Whole Building Design Guide website at www.wbdg.org. The Unified Facilities Guide Specifications (UFGS) are the Default Specifications for all designs. Specification paragraphs and subparagraphs shall not be rewritten by the City of Center Line or its designated representative which lessens the quality of the original technical specification sections, unless otherwise noted in the SOW. The UFGS specifications describe the type and quality of material and installation normally acceptable for United States Army construction and often represent specific agreement between the Government and the applicable industry. The provisions of the UFGS technical specifications shall not be changed without justification. If bracketed choices are not selected by the Government in the SOW, then the City of Center Line or its designated representative shall edit the choice as applicable by the guidance provided in the UFGS specification section. The City of Center Line or its designated representative editing of UFGS specifications shall not lessen the quality of the UFGS unless the City of Center Line or its designated representative provides the GPM documentation as to why the standards established by the UFGS sections cannot be met and the GPM approves. The technical specifications shall be complete and fully coordinated with the drawings. Special sections shall be prepared to cover those subjects for which no pattern guide specifications are available. This SOW shall be used in editing technical guide specifications. All specification indexes shall be completely edited to reflect the paragraphs retained in the body of the specification. All UFGS specifications shall be edited in accordance with the requirements stated here and with UFC 1-300-02 Unified Facilities Guide Specifications.
Section No. Specification Section Name
02 41 00 Demolition and Deconstruction 26 05 00 Common Work Results for Electrical http://www.wbdg.org/
26 05 19 Insulated Wire and Cable 26 05 26 Grounding and Bonding for Electrical Systems 26 05 71 Low Voltage Overcurrent Protective Devices 26 08 00 Apparatus Inspection and Testing 26 20 00 Interior Distribution System 26 24 13 Switchboards 26 24 16 Panelboards 26 27 13 Electric Meters 26 31 00 Facility Scale Solar Photovoltaic (PV) Systems
7. SUBMITTALS
7.1 Project Submittal Requirements: The design requirements shall be provided in accordance with this SOW. The Design Analysis Narrative shall list all conditions impacting safe work on the project for each of the sections listed above and be submitted with each design. Potentially hazardous conditions, such as, materials shall be identified. The basis and reasons for specific decisions, special features, and unusual requirements shall be explained or summarized. If it is necessary to deviate from criteria or standard practice, reasons shall be included. Design statements shall be provided in sufficient detail to enable the reviewer to get a clear picture and understanding of all included work. Narrative shall be complete relative to scope and design approaches. The design analysis shall carry a complete narrative for every item covered in the design.
The contractor shall also provide other submittals since it will be developing a complete list of submittals during design, which fully detail material or articles to be incorporated into the work, and that are required by the United Facilities Guide Specifications (UFGS) 01 33 00, Submittal Procedures. The City of Center Line or its designated representative shall obtain Government Project Manager (GPM) approval of these submittals. Approval does not remove the City of Center Line or its designated representative requirement to comply with contract requirements.
7.2. Close-out Submittal Requirements:
7.2.1. All closeout and O&M data requirements are listed in UFGS 01 78 00 and 01 78 23. The City of Center Line or its designated representative shall provide all required documents in accordance with these sections.
7.2.2. All piping, ductwork, and conduit, wiring, and cabling shall be As-Built surveyed and photographed by the Contractor and shall be inspected by the Contractor and GPM prior to burying, covering, or concealing. The Contractor shall provide all photographs to the GPM in electronic Portable Document Format (PDF) or JPEG format.
7.2.3. Pictures from different positions shall be taken as direction to show, as much as possible, work accomplished during the previous month. Photographs shall be at least 4 megapixels and shall be in JPEG format. Identify the date taken, contract title and number, location of work, and a brief description of the work depicted. No separate payment will be made for these services and all costs in connection thereto shall be considered a subsidiary obligation of the Contractor. Contractor is to use the Eng Form 4025 in accordance with section 01 33 00.
8. ENVIRONMENTAL
8.2. Asbestos Containing Material: The work has the potential to impact asbestos containing materials (ACMs), as indicated in the attached asbestos report. Contractor is responsible to ensure ACMs are treated in accordance with all Federal, State and local regulations, laws and guidelines, and the most current Detroit Arsenal Asbestos Operations and Maintenance Plan.
8.3. Construction and Demolition (C&D) Waste Planning and Reporting: C&D Reports shall be completed in compliance with specification section 01 74 19 Construction and Demolition and as follows:
- Construction and Demolition (C & D): Waste Disposal of solid waste, including construction and demolition (C&D) debris is the responsibility of the contractor. The Waste Management Plan shall be developed by the contractor and shall outline how all C&D materials generated will be handled for disposal and recycling. Section 01 74 19 paragraph 1.6 of the Unified Facilities Guide Specifications outlines the requirements of the Waste Management Plan.
- The contractor shall recycle sixty percent (60%) of all C&D waste generated from the project.
Cost effectiveness will need to be considered to meet these requirements. Documents must be submitted to the GPM support the finding if it is not cost effective to recycle this material. The documentation must be approved by the GPM prior to being waived.
- The contractor shall make an effort to deliver Non-Regulated Solid Waste materials to a commercial recycler and provide USAG - DTA with a summary of weights of materials recycled.
- By the 15th of each month following transportation and disposal of all non-regulated solid waste, the contractor shall provide the following information electronically to the POC within Environmental Division and a copy to the GPM:
- The weight and type of all solid waste material recycled. Quantities may be measured by weight or by volume but must be consistent throughout.
- The name and location of the landfill, recycling facility or waste processor receiving the waste or a description of the recycling disposition. Submit manifests, weight tickets, receipts, and invoices specifically identifying the project and waste material.
- Provide explanations for any waste not recycled or reused.
- Quantity of waste generated in cubic yards or tons.
- Quantity of waste diverted through sale, reuse, or recycling in cubic yards or tons.
- Quantity of waste disposed by landfill or incineration in cubic yards or tons.
- The Government shall have 14 calendar days after date of receipt in which to approve or reject the submittals.
8.4. Excess soils shall become the property of the City of Center Line or its designated representative and shall be properly disposed off-site in Government approved Class II landfills or a Government approved alternate destination. The Government will not approve the following sites: Residential and agricultural sites, Schools, playgrounds or other childcare sites, Sites with drinking water or irrigation wells. The Government will approve non-residential sites not listed above with naturally occurring arsenic levels equal to or greater than DTA soils. In addition, written permission from the landowner is required. The written statement must include the site is not a wetland and is not the site of any known historical or archeological resources.
8.5. If hazardous chemicals or petroleum, oil or lubricant spills occur at the job site, the Fire Department and then the Directorate of Public Works (DPW) Environmental Division shall be notified immediately. The City of Center Line or its designated representative shall submit a spill plan which shall spell out their plan for handling spilling of fuel and/or hazardous materials.
8.6. The contractor shall prepare and maintain an Environmental Protection Plan (EPP) in accordance with 01 57 19 section 1.7 with focus to address the following sections:
1) 1.7.1 General Overview and Purpose.
2) 1.7.2 General Site Information.
3) 1.7.3 Management of Natural Resources, if applicable.
4) 1.7.5 Stormwater Management and Control, if applicable.
5) 1.7.6 Protection of the Environment from Waste Derived from Contractor Operations, if applicable.
6) 1.7.7 Prevention of Releases to the Environment, if applicable.
7) 1.7.8 Regulatory Notification and Permits, if applicable.
8) 1.7.9 Clean Air Act Compliance, if applicable.
Additionally, the plan shall include the following sections:
1) Cover Page
2) Signature sheet
a) Plan preparer(s) and date
b) Plan reviewer and date
c) Company authorized person approval and date.
3) Contact information/ responsible parties ((Name, Phone number and email)
a. Project Manager
b. Site Supervisor
c. Site QC
d. Site SSHO
e. Subcontractor(s)
f. Emergency 24-Hour Contact: Fire Department at DTA 586-282-7117
4) Training Records
5) Table of Contents with page numbers
6) Attachments
a. SESC (Soil Erosion/Sediment Control), if applicable
b. Drawings, if applicable
c. Certificates and licenses, if applicable
d. Correction action records
9. PAYMENT
9.2. Payment will be made in accordance with the terms of the IGSA-CIRM.
10. SPECIAL ACCESS REQUIREMENTS
10.2. Reserved.
11. OTHER CONDITIONS AFFECTING WORK
11.2. Work Coordination
11.2.1. The City of Center Line or its designated representative shall coordinate, through the GPM, with the proposed tenant for the placement, installation, finish selections, of tenant furnished material and equipment. The City of Center Line or its designated representative shall coordinate with other contractors to prevent interference with their work and to allow them access to the work areas in accordance with the IGSA-CIRM.
11.2.2. The limits of construction are limited to building 229 (B229).
11.2.3. Work in connection with this contract which requires utility outages (electrical, water, gas, steam,…) which will close down or limit (as determined by the GPM) normal activities in the building, construction area, or other affected areas, shall be performed by the Contractor at a time other than regular working hours of the organization occupying the facility. The contractor is responsible for providing standalone power to all buildings, structures, operations, etc. due to scheduled electrical shutdowns in conjunction with the work. Under no circumstances may the contractor rely upon the existing emergency generators to provide power during scheduled shutdowns. Work in connection with this contract which requires road closures shall be performed by the City of Center Line or its designated representative at a time other than regular working hours. Work required by the City of Center Line or its designated representative on non-standard basis or at premium pay shall be done at no additional cost to the Government. Request for utility outages and road closures shall be submitted to the GPM, in writing (Appendix C), fourteen (14) calendar days prior to commencing work and shall be subject to GPM approval.
11.2.4. The City of Center Line or its designated representative must obtain a "Dig Permit" from the Department of Public Works prior to any ground disturbing activities. The Dig Permit process includes and does not replace the requirement for contractors to contact the Michigan One Call System (MissDig811). As part of the Dig Permit process the NEC will locate and mark any telecommunication lines in the work area. The City of Center Line or its designated representative is responsible for locating all utilities (with the exception of telecommunications) prior to commencing excavation. Perform work adjacent to non-Government utilities as indicated in accordance with procedures outlined by utility company. City of Center Line or its designated representative shall provide locating services to locate all known Government underground pipes and utilities. The Government’s utility map is included with this SOW. Excavation made with power-driven equipment is not permitted within 2 feet of known Government-owned utility or subsurface construction. For work immediately adjacent to or for excavations exposing a utility or other buried obstruction, excavate by hand. Start hand excavation on each side of the indicated obstruction and continue until the obstruction is uncovered or until clearance for the work being performed is assured. Support uncovered lines or other existing work affected by the contract excavation. Report damage to utility lines or subsurface construction immediately to the Department of Public Works.
11.2.5. Prior to the start of construction, the City of Center Line or its designated representative shall submit a request in writing for any support needed from Base Operations. The request shall include the number of hours of support anticipated and the anticipated dates the support will be needed.
11.2.6. Pre-Construction Conference: The City of Center Line and its designated representative shall attend a pre-work meeting presided over by the GPM prior to commencing construction activities.
The Contractor shall contact the GPM within 5 days to establish a date and time for the preconstruction meeting. The Contractor shall submit a site-specific construction schedule and a site-specific Work Plan through the City of Center Line or its designated representative to the Government for approval. The schedule shall be in sufficient detail to identify all aspects of the work including all significant project tasks with durations and start and finish times.
11.2.7. Pre-Construction CQC Coordination Meeting: The City of Center Line or its designated representative shall attend a CQC Coordination meeting held in accordance with specification section titled QUALITY CONTROL.
11.2.8. All material deliveries shall only be via the designated construction gate. All personnel access to the site shall only be via the Main Gate. Entrance to the Site shall be restricted and require issuance of a security pass or badge subject to the requirements of Base Security. Individuals requiring passes or badges will be listed on the current Vetting Form and submitted to the GPM at least 14 days in advance of requested access date(s). All access will be in accordance with Annex 2:
Installation Security and Access Requirements.
11.2.9. The responsible USG POC for coordination of release and return of USG engineering drawings and information at the Detroit Arsenal is the DPW Engineering Services Division CAD Technician.
Coordination of release and return of USG engineering drawings shall be through the GPM.
Required Security Training AT Level I Training. The contractor shall ensure that all contractor employees, to include subcontractor employees, requiring access to Army installations, facilities and controlled access areas complete AT Level I awareness training within 30 calendar days after task order NTP. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the GPM within seven calendar days after completion of training.
AT level I awareness training is available at the following website:
https://jko.jten.mil/courses/atl1/launch.html iWATCH Training. This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area. The contractor shall ensure that all contractor employees and all associated sub-contractors are briefed on the local iWATCH program (training standards provided by the requiring activity ATO). This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the GPM. This training shall be completed within 30 calendar days of
NTP.
Per AR 530-1, Operations Security, the contractor shall ensure all contractor employees complete Level I OPSEC training within 30 calendar days of task order NTP. All contractor employees must complete annual OPSEC awareness training.
11.2.10. Monthly Progress Meetings: The contractor shall hold monthly (or as otherwise mutually agreed
to) progress meetings with the Government. At a minimum the agenda shall include review of the schedule with special focus on the work occurring within the next month. It shall also include discussion of any RFIs, modifications, quality issues, and safety. The City of Center Line or its designated representative shall provide brief meeting agenda prior to the meeting. Minutes shall be submitted no later than three (3) calendar days after the meeting occurs.
11.2.11. Requests for Information: All RFIs shall be submitted in accordance with to the Government via email to the GPM. The City of Center Line or its designated representative shall provide an index of each RFI, which documents the RFI number, the date the RFI was given to the Government, the date the RFI was answered by the Government, and the response provided by the Government. The Government will have fourteen (14) calendar days to respond to RFIs after date of receipt of the RFI. City of Center Line or its designated representative is to use the RFI Form provided by the Government when submitting RFIs to the Government. City of Center Line or its designated representative shall clearly state whether or not they see the RFI as potentially impacting the cost or schedule of the project. Whenever possible recommended solutions should be provided.
11.3. Contractor Management Personnel and Sub-Contractor Qualifications:
11.3.1. Ensure compliance with IGSA-CIRM requirements.
11.3.2. Subcontractors tasked with construction of the PV array shall have satisfactorily completed a minimum of two projects of similar nature, scope, and dollar value.
11.3.3. Storm water personnel requirement: Soil Erosion Sediment Control features must be inspected weekly and within 24 hours of a significant rain event by a Michigan Certified Construction Storm Water Operator employed by the Contractor. Certification materials and testing information are available at https://www.michigan.gov/egle/0,9429,7-135-3311_4113---,00.html.
https://www.michigan.gov/egle/0,9429,7-135-3311_4113---,00.html
11.4. Compliance with Rules, Regulations, and Statutes
11.4.1. All work shall comply with applicable Army, State, and Federal safety and health requirements.
The City of Center Line or its designated representatives shall comply with the requirements of OSHA (Occupational Safety and Health Association), MIOSH (Michigan Occupational Safety and Health Association, U.S. Army Safety Program (AR385-10), the Installation Safety Program (TACOM Supplement 385-10), and the U.S. Army Corps of Engineers Safety Manual EM-385-1-1.
Where there is a conflict between applicable regulations, the most stringent shall apply.
11.4.2. All work including the handling of hazardous materials or the disturbance or dismantling of structures containing hazardous materials shall comply with the applicable requirements of 29 CFR 1910/1926. Work involving the disturbance or dismantling of asbestos or asbestos-containing materials; the demolition of structures containing asbestos; and/or disposal and removal of asbestos, shall also comply with the requirement of 40 CFR, Part 61 Subpart M (The National Emission Standard for Asbestos) (ETL 1110-1-118 and DA Circular 40-83-4).
11.4.3. The contractor shall submit a Safety Data Sheet (SDS) for all hazardous materials to the GPM and have a SDS for all hazardous materials readily available for the entire duration of the project. When the contractor is working in buildings that are occupied by Government personnel, the contractor must provide a SDS for all hazardous materials to the GPM before they begin the work.
11.5. Site Utilities
11.5.1. No site utilities will be available. Contractor is responsible to provide power, water, and any support services necessary to perform the work included in this SOW.
11.6. Permits
11.6.1. The Contractor shall obtain and submit copies of ALL permits, unless otherwise specified. Each permit shall be obtained before starting the respective items of work. This includes, but is not limited to, permits necessary for decontaminating water and sewer systems, and digging permits.
11.6.2. Soil Erosion Sediment Control (SESC): A Macomb County Drain Permit and/or Soil Erosion Sediment Control permit is not required for this project. Information on how to apply for this permit can be found at https://publiworks.macombgov.org/PublicWorks- SoilErosionSedimentControl?
11.6.3. A National Pollutant Discharge Elimination System (NPDES) permit is not required for this project. Information on how to apply for this permit can be found at https://www.michigan.gov/egle/0,9429,7-135-3313_71618_3682_3713---,00.html .
11.7. Safety
11.7.1. USACE Safety and Health Requirements Manual (EM 385-1-1), available online at http://www.publications.usace.army.mil/USACEPublications/EngineerManuals.aspx, shall be considered to be a part of this work and will be enforced as such.
11.7.2. A site safety officer shall be assigned and shall be approved by the government. This person shall manage the safety program. This person can serve as the QC manager but cannot also serve as the project superintendent.
https://publiworks.macombgov.org/PublicWorks-SoilErosionSedimentControl?
https://publiworks.macombgov.org/PublicWorks-SoilErosionSedimentControl?
https://www.michigan.gov/egle/0,9429,7-135-3313_71618_3682_3713---,00.html http://www.publications.usace.army.mil/USACEPublications/EngineerManuals.aspx
11.7.3. The Contractor shall prepare an accident prevention plan in accordance with the most current version of EM 385-1-1 and section 01 35 26 GOVERNMENT SAFETY REQUIREMENTS. See EM 385-1-1 for Minimum Basic Outline for Accident Prevention Plans. The plans shall incorporate applicable requirements of the following specifications:
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 35 30 SAFETY, HEALTH, AND EMERGENCY RESPONSE (HTRW/UST)
01 35 29 SAFETY AND OCCUPATIONAL HEALTH REQUIREMENTS
02 82 14.00 10 ASBESTOS HAZARD CONTROL ACTIVITIES
02 82 33.13 20 REMOVAL/CONTROL AND DISPOSAL OF PAINT WITH LEAD
02 83 13.00 20 LEAD IN CONSTRUCTION
02 84 16 HANDLING OF LIGHTING BALLASTS AND LAMPS CONTAINING PCBS
AND MERCURY
02 84 33 REMOVAL AND DISPOSAL OF POLYCHLORINATED BIPHENYLS (PCBS)
31 21 13 RADON MITIGATION
11.7.4. If a Traffic Control Plan is determined to be necessary to perform the work included in this SOW.
The Traffic Control Plan shall be prepared in accordance with section 08 of the EM 385-1-1 and in accordance with the Manual on Uniform Traffic Control Devices.
11.7.5. If a Confined Space Plan is determined to be necessary to perform the work included in this SOW, the Confined Space Plan shall be prepared in accordance with EM 385-1-1 section 34. Approval of this plan is required prior to any work in a confined space.
11.8. Construction Facilities And Temporary Controls
11.8.1. A staging/laydown area may be available for use at the project site. A request for the use of a staging/laydown area may be requested through the Government. All areas shall be approved by Master Planning prior to use. All staging/laydown areas shall meet the requirements of the EM 385- 1-1.
11.8.2. Fencing and warning signs shall be provided in work areas in accordance with EM 385-1-1.
11.8.3. The Contractor is responsible for security of his own property and security of government property when construction activities affect existing security measures.
11.8.4. The Contractor shall provide and maintain portable toilet facilities at the site for the use of Contractor and subcontractor personnel, as required by the EM 385-1-1. The units shall be emptied and cleaned at least once a week, or more often if required by the GPM. The doors to the unit shall be self-closing. Additionally, the toilet units shall be located out of public view as the site allows.
12. GOVERNMENT FURNISHED MATERIAL/EQUIPMENT
12.2. There is no Government furnished property as part of this project.
| 1. GENERAL DISCUSSION |
| 1.1. Project Identification |
| 1.1.1. Project Title: Install – B229 PV Array |
| 1.1.2. Work Order Number(s): DTA001322 |
| 1.1.3. IGSA Order Number: IGSA-CI-25-01 |
| 1.1.4. IGSA Service Type: Bid-Build Service |
| 1.2. Description of Work |
| 1.2.1. The City of Center Line or its designated representative shall supply all supervision, labor, equipment, and materials to perform all work in strict accordance with IGSA-CI, this Statement of Work, and identified drawings and specifications to ... |
| 1.2.2. The proposals submitted from this RFP shall be valid for a duration of 60 days from the date of proposal opening. This project is being solicited as Subject to the Availability of Funds (SAF). |
| 1.3. Area Description |
| 1.3.1. Location: B229 Roof |
| 1.3.2 Known Existing Site Conditions: The roof of B229 is being replaced in 2025, therefore in coordination with the roofing repair it is a good time to install a roof mounted PV array. The installation of a PV array on this roof will assist the Army ... |
| 2. PROJECT OBJECTIVES |
| 2.1. Principal Items To Be Accomplished |
| 2.1.1. Line Item 1 – Base Repair – Provide and install roof mounted PV Array on B229 as defined in the attached drawings and specifications (Reference: Appendix 3). |
| The City of Center Line or its designated representative shall include all labor, materials, and equipment to perform all work in strict accordance with the umbrella contract specifications, this Statement of Work, and identified drawings to install a... |
| 2. PROJECT OBJECTIVES |
| 2.1. General Notes: |
| 2.1.2. The construction shall meet all the performance objectives listed in this IGSA request. The City of Center Line or its designated representative shall use record drawings, field investigations, and other pertinent data to determine existing con... |
| 2.2. Deliverables: |
| 2.2.2. A submittal register using ENG4288 form or similar shall be maintained for the duration of the project in accordance with Unified Facilities Guide Specifications (01 33 00). |
| 2.2.3. The City of Center Line or its designated representative shall provide a completed DD 1354 Transfer of Real Property for review by Master Planning. This form itemizes the types, quantities and costs of various equipment and systems that compris... |
| 2.3. Field Inspection: The City of Center Line or its designated representative shall verify field conditions which are significant to design, by field inspection, researching, and obtaining all necessary existing facility as-built drawings. |
| 2.4. Conferences: After contract award, the City of Center Line or its designated representative and the construction representatives shall attend the Preconstruction Conference at the Detroit Arsenal (DTA) Directorate of Public Works (DPW). The City ... |
| 3. DESIGN |
| 3.1. Designer of Record: Reserved. |
| 3.2. Constructor’s Role During Design: Reserved. |
| 3.3. Review Comments: Reserved. |
| 3.4. Released for Construction (RFC) Design: Reserved. |
| 4. PERFORMANCE AND SCHEDULING |
| 4.1. Performance Period Requirements |
| 4.1.1. The performance periods and submission schedules for construction are indicated below. The Contactor shall furnish sufficient technical, supervisory, and administrative personnel to ensure the prosecution of the work in accordance with the sub... |
| 4.1.2. The time stated for construction completion includes final cleanup of the premises and submission of all required close-out documentation. |
| 4.1.3. Prepare Project Schedule in accordance with Unified Facility Guide Specifications (UFGS) 01 32.01.00 10. |
| 4.2. Award of Options |
| 4.2.1. Award of Option Item(s): Reserved. |
| 4.2.2. Duration of Option Items: Reserved. |
| 4.3. Construction Phasing Requirement |
| 4.3.1. During the performance of onsite construction activities, the contractor is permitted to work during the hours of 06:00 to 18:00 (6:00am to 6:00pm). Additional compensation for overtime will not be considered by the Government. |
| 4.3.2. Work by other contractors is anticipated within the facility and the grounds of Detroit Arsenal. The contractor is required to coordinate work schedules with other contractors performing work within and around the building. |
| 4.4 Government Incentives and Remedies |
| 4.4.1 The City of Center Line or its designated representative shall perform all work in accordance with the requirements specified within this SOW. This section is in addition to any of the rights and remedies available to the Government under statut... |
| 4.4.2. Remedies: In accordance with the IGSA-CIRM agreement. |
| 5. APPENDICIES |
| 5.1. All applicable appendices are listed in the table below. This list constitutes the entirety of this task order. Note that all specifications, codes, standards, and requirements listed within these documents are also applicable to this SOW. |
| 6. SPECIFICATIONS AND CODES |
| 6.1. Codes |
| 6.1.2. The most recent edition, at time of solicitation, of all pertinent Local, State, and Federal building and life/health/safety codes shall be used. |
| 6.2. Specifications |
| 6.2.2. The City of Center Line or its designated representative shall comply with all relevant specification sections. |
| 6.2.3. The following UFC Specifications are considered particularly relevant to this project and shall be considered governing documents unless otherwise noted. |
| 7. SUBMITTALS |
| The contractor shall also provide other submittals since it will be developing a complete list of submittals during design, which fully detail material or articles to be incorporated into the work, and that are required by the United Facilities Guide ... |
| 7.2. Close-out Submittal Requirements: |
| 7.2.1. All closeout and O&M data requirements are listed in UFGS 01 78 00 and 01 78 23. The City of Center Line or its designated representative shall provide all required documents in accordance with these sections. |
| 7.2.2. All piping, ductwork, and conduit, wiring, and cabling shall be As-Built surveyed and photographed by the Contractor and shall be inspected by the Contractor and GPM prior to burying, covering, or concealing. The Contractor shall provide all p... |
| 7.2.3. Pictures from different positions shall be taken as direction to show, as much as possible, work accomplished during the previous month. Photographs shall be at least 4 megapixels and shall be in JPEG format. Identify the date taken, contract... |
| 8. ENVIRONMENTAL |
| 8.2. Asbestos Containing Material: The work has the potential to impact asbestos containing materials (ACMs), as indicated in the attached asbestos report. Contractor is responsible to ensure ACMs are treated in accordance with all Federal, State and ... |
| 8.3. Construction and Demolition (C&D) Waste Planning and Reporting: C&D Reports shall be completed in compliance with specification section 01 74 19 Construction and Demolition and as follows: |
| 8.4. Excess soils shall become the property of the City of Center Line or its designated representative and shall be properly disposed off-site in Government approved Class II landfills or a Government approved alternate destination. The Government w... |
| 8.5. If hazardous chemicals or petroleum, oil or lubricant spills occur at the job site, the Fire Department and then the Directorate of Public Works (DPW) Environmental Division shall be notified immediately. The City of Center Line or its designated... |
| 8.6. The contractor shall prepare and maintain an Environmental Protection Plan (EPP) in accordance with 01 57 19 section 1.7 with focus to address the following sections: |
| 1) 1.7.1 General Overview and Purpose. |
| d. Correction action records |
| 9. PAYMENT |
| 9.2. Payment will be made in accordance with the terms of the IGSA-CIRM. |
| 10. SPECIAL ACCESS REQUIREMENTS |
| 10.2. Reserved. |
| 11. OTHER CONDITIONS AFFECTING WORK |
| 11.2. Work Coordination |
| 11.2.1. The City of Center Line or its designated representative shall coordinate, through the GPM, with the proposed tenant for the placement, installation, finish selections, of tenant furnished material and equipment. The City of Center Line or it... |
| 11.2.2. The limits of construction are limited to building 229 (B229). |
| 11.2.3. Work in connection with this contract which requires utility outages (electrical, water, gas, steam,…) which will close down or limit (as determined by the GPM) normal activities in the building, construction area, or other affected areas, sha... |
| 11.2.4. The City of Center Line or its designated representative must obtain a "Dig Permit" from the Department of Public Works prior to any ground disturbing activities. The Dig Permit process includes and does not replace the requirement for contrac... |
| 11.2.5. Prior to the start of construction, the City of Center Line or its designated representative shall submit a request in writing for any support needed from Base Operations. The request shall include the number of hours of support anticipated an... |
| 11.2.6. Pre-Construction Conference: The City of Center Line and its designated representative shall attend a pre-work meeting presided over by the GPM prior to commencing construction activities. The Contractor shall contact the GPM within 5 days to... |
| 11.2.7. Pre-Construction CQC Coordination Meeting: The City of Center Line or its designated representative shall attend a CQC Coordination meeting held in accordance with specification section titled QUALITY CONTROL. |
| 11.2.8. All material deliveries shall only be via the designated construction gate. All personnel access to the site shall only be via the Main Gate. Entrance to the Site shall be restricted and require issuance of a security pass or badge subject to ... |
| 11.2.9. The responsible USG POC for coordination of release and return of USG engineering drawings and information at the Detroit Arsenal is the DPW Engineering Services Division CAD Technician. Coordination of release and return of USG engineering dr... |
| 11.2.10. Monthly Progress Meetings: The contractor shall hold monthly (or as otherwise mutually agreed to) progress meetings with the Government. At a minimum the agenda shall include review of the schedule with special focus on the work occurring wi... |
| 11.2.11. Requests for Information: All RFIs shall be submitted in accordance with to the Government via email to the GPM. The City of Center Line or its designated representative shall provide an index of each RFI, which documents the RFI number, the ... |
| 11.3. Contractor Management Personnel and Sub-Contractor Qualifications: |
| 11.3.1. Ensure compliance with IGSA-CIRM requirements. |
| 11.3.2. Subcontractors tasked with construction of the PV array shall have satisfactorily completed a minimum of two projects of similar nature, scope, and dollar value. |
| 11.3.3. Storm water personnel requirement: Soil Erosion Sediment Control features must be inspected weekly and within 24 hours of a significant rain event by a Michigan Certified Construction Storm Water Operator employed by the Contractor. Certificat... |
| 11.4. Compliance with Rules, Regulations, and Statutes |
| 11.4.1. All work shall comply with applicable Army, State, and Federal safety and health requirements. The City of Center Line or its designated representatives shall comply with the requirements of OSHA (Occupational Safety and Health Association), M... |
| 11.4.2. All work including the handling of hazardous materials or the disturbance or dismantling of structures containing hazardous materials shall comply with the applicable requirements of 29 CFR 1910/1926. Work involving the disturbance or dismantl... |
| 11.4.3. The contractor shall submit a Safety Data Sheet (SDS) for all hazardous materials to the GPM and have a SDS for all hazardous materials readily available for the entire duration of the project. When the contractor is working in buildings that ... |
| 11.5. Site Utilities |
| 11.5.1. No site utilities will be available. Contractor is responsible to provide power, water, and any support services necessary to perform the work included in this SOW. |
| 11.6. Permits |
| 11.6.1. The Contractor shall obtain and submit copies of ALL permits, unless otherwise specified. Each permit shall be obtained before starting the respective items of work. This includes, but is not limited to, permits necessary for decontaminating... |
| 11.6.2. Soil Erosion Sediment Control (SESC): A Macomb County Drain Permit and/or Soil Erosion Sediment Control permit is not required for this project. Information on how to apply for this permit can be found at https://publiworks.macombgov.org/Publi... |
| 11.6.3. A National Pollutant Discharge Elimination System (NPDES) permit is not required for this project. Information on how to apply for this permit can be found at https://www.michigan.gov/egle/0,9429,7-135-3313_71618_3682_3713---,00.html . |
| 11.7. Safety |
| 11.7.1. USACE Safety and Health Requirements Manual (EM 385-1-1), available online at http://www.publications.usace.army.mil/USACEPublications/EngineerManuals.aspx, shall be considered to be a part of this work and will be enforced as such. |
| 11.7.2. A site safety officer shall be assigned and shall be approved by the government. This person shall manage the safety program. This person can serve as the QC manager but cannot also serve as the project superintendent. |
| 11.7.3. The Contractor shall prepare an accident prevention plan in accordance with the most current version of EM 385-1-1 and section 01 35 26 GOVERNMENT SAFETY REQUIREMENTS. See EM 385-1-1 for Minimum Basic Outline for Accident Prevention Plans. The... |
| 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS 01 35 30 SAFETY, HEALTH, AND EMERGENCY RESPONSE (HTRW/UST) 01 35 29 SAFETY AND OCCUPATIONAL HEALTH REQUIREMENTS 02 82 14.00 10 ASBESTOS HAZARD CONTROL ACTIVITIES 02 82 33.... |
| 11.7.4. If a Traffic Control Plan is determined to be necessary to perform the work included in this SOW. The Traffic Control Plan shall be prepared in accordance with section 08 of the EM 385-1-1 and in accordance with the Manual on Uniform Traffic C... |
| 11.7.5. If a Confined Space Plan is determined to be necessary to perform the work included in this SOW, the Confined Space Plan shall be prepared in accordance with EM 385-1-1 section 34. Approval of this plan is required prior to any work in a confi... |
| 11.8. Construction Facilities And Temporary Controls |
| 11.8.1. A staging/laydown area may be available for use at the project site. A request for the use of a staging/laydown area may be requested through the Government. All areas shall be approved by Master Planning prior to use. All staging/laydown area... |
| 11.8.2. Fencing and warning signs shall be provided in work areas in accordance with EM 385-1-1. |
| 11.8.3. The Contractor is responsible for security of his own property and security of government property when construction activities affect existing security measures. |
| 11.8.4. The Contractor shall provide and maintain portable toilet facilities at the site for the use of Contractor and subcontractor personnel, as required by the EM 385-1-1. The units shall be emptied and cleaned at least once a week, or more often ... |
| 12. GOVERNMENT FURNISHED MATERIAL/EQUIPMENT |
| 12.2. There is no Government furnished property as part of this project. |