00 20 00 - Request for Proposals.pdf

PDF 56 KB Posted

Attached to
B229 PV Array
Solicitation number
AEW-0170-0555
Issued by
Macomb County, Westland City, Michigan

About this file

This Request for Proposal (RFP) is issued by the City of Center Line, Michigan, in collaboration with the U.S. Army Garrison - Detroit Arsenal, for the B229 PV Array project. The solicitation seeks a contractor to install a new photovoltaic (PV) array at the Detroit Arsenal, with proposals due on Wednesday, March 5, 2025, at 10:00 am local time. Plans and specifications will be available starting Monday, February 3, 2025, via BidNet Direct, and a mandatory pre-bid meeting is scheduled for Wednesday, February 12, 2025, at 10:00 am. Bidders must complete an STA form for base access and submit pre-bid questions by Tuesday, February 18, 2025, at noon.

The bid requires a 5% bid guarantee in the form of a certified check or bid bond, and the successful bidder will need to provide performance, maintenance, guarantee, and labor and material bonds. Bids cannot be withdrawn for 90 calendar days after submission, and the City of Center Line reserves the right to reject any or all proposals, waive irregularities, or negotiate with respondents to serve its best interests. The project will be awarded under the oversight of Dennis Champine, City Manager/Clerk, with the specific engineering and design work to be completed by Anderson, Eckstein & Westrick, Inc.

View the file

Other files

File Type Posted
RFS CIRM 2025-01_ BLDG 229 PV ARRAY_DRAWINGS_BID ISSUE__250129.pdf PDF
Appendix D - Asbestos Survey.pdf PDF
Appendix G - ENG_FORM_4288-R.pdf PDF
Appendix B - Rad Contractor Process.pdf PDF
IMG_7927.JPG JPG image
IMG_7928.JPG JPG image
BLDG - 229 4TH FLR.pdf PDF
IMG_7932.JPG JPG image
Appendix E - DTA-F-004-24_ClearancePermitRequest-v1.1 (new).pdf PDF
BLDG - 229 3RD FLR.pdf PDF
IMG_7925.MOV MOV file
Appendix C - Construction Impact Notification.pdf PDF
IMG_7933.JPG JPG image
BLDG - 229 BASEMENT FLR.pdf PDF
BLDG - 229 2ND FLR.pdf PDF
IMG_7934.JPG JPG image
Appendix H - STA_Form17_FEB2024.v3.0_Single.pdf PDF
6-A Addenda #1_0170-0555_DTA B229_250218.pdf PDF
IMG_7925.JPG JPG image
BLDG - 229 1ST FLR.pdf PDF
IMG_7931.JPG JPG image
RFS CIRM 2025-01_ BLDG 229 PV ARRAY_SPEC_BID ISSUE__250129.pdf PDF
IMG_7926.JPG JPG image
IMG_7930.JPG JPG image
Appendix F - SOW DTA IGSA-CI 25-01 B229 PV Array.pdf PDF
IMG_7929.JPG JPG image
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 00 20 00

REQUEST FOR PROPOSAL

PROJECT: OWNER:

City of Center Line City of Center Line

B229 PV Array 7070 E. 10 Mile Road

Center Line, Michigan 48015

AEW Project No. 0170-0555

RFS CIRM 2025-01

LOCATION: ARCHITECT/ENGINEER:

U.S. Army Garrison – Detroit Arsenal Anderson, Eckstein & Westrick, Inc.

6501 East 11 Mile Road 51301 Schoenherr Road

Detroit Arsenal, MI 48397-5000 Shelby Township, Michigan 48315

(586) 726-1234

DESCRIPTION:

The project consists of installing a new PV array

DOCUMENTS:

Plans and specifications will be available Monday, February 3, 2025 after 4 pm.

Plans and Specifications will be obtained at www.bidnetdirect.com, documents will only be available through the BidNet Direct site. Bids may be rejected unless made on the forms included with the bidding documents.

PRE-BID MEETING:

A pre-bid meeting will be held at the project location at 10:00 am, on Wednesday, February 12, 2025.

Fill out and return the attached STA form a minimum of three business days prior to pre-bid meeting for base access and email completed STA Form to:

brian.g.saintonge.civ@army.mil . On the day of the pre-bid meeting, go to the

Visitors Center on 11 Mile Road to pick up your pass. Processed through the main gate to building #205, DPW/Fire Station for meeting.

Pre-bid questions shall be submitted to the Architect no later than Tuesday, February 18, 2025 at Noon, local time. Email all questions to: skelley@aewinc.com;

and copy brian.g.saintonge.civ@army.mil . Please include the Project Name and

AEW Project Number in the Subject line of the email, “Project Name – Project

Number –Pre-Bid Questions” for example.

http://www.bidnetdirect.com/ mailto:brian.g.saintonge.civ@army.mil mailto:skelley@aewinc.com mailto:brian.g.saintonge.civ@army.mil

SECTION 00 20 00

REQUEST FOR PROPOSAL

SCOPE OF PROPOSAL:

Sealed proposals are invited for construction of the Project and will be received at the Office of the Center Line City Clerk until 10:00am, local time; Wednesday, March 5, 2025. Bids will be publicly opened and read aloud in the offices of the

City Clerk immediately thereafter.

BID GUARANTEE AND CONTRACT SECURITY:

Each bid proposal shall be accompanied by a certified check or satisfactory bid bond by an approved surety company in an amount not less than 5% of the bid amount. Checks shall be made payable to the Owner. Bids may not be withdrawn for a period of ninety (90) calendar days after receipt of bids. The successful bidder will be required to furnish a performance bond, maintenance and guarantee bond, labor and material bond, and insurance certificates.

RIGHTS OF THE OWNER:

The Owner reserves the right to reject any or all proposals and to waive irregularities in the proposal, or to accept the lowest responsible proposal or negotiate with respondents, in the opinion of the Owner, will serve his best interest.

DATED: February, 2025 CITY OF CENTER LINE

Dennis Champine, City Manager/Clerk

****END OF REQUEST FOR PROPOSAL****

File details come from the government source that posted it. Updated .