Appendix C Cantilever Rack.pdf
PDF 718 KB Posted
- Attached to
- FA8604 Storage Aids System/JB Charleston, South Carolina MMHS Federal contract opportunity
- Solicitation number
- FA860424RB005
About this file
This document is an appendix establishing the minimum performance, design, fabrication, installation, and test requirements for a cantilever rack system at the Flight Line Support Facility at Joint Base Charleston, South Carolina. Key details include:
The cantilever rack system must meet specific requirements for the bases, uprights, bracing, arms, and connectors. The racks must be able to support a minimum load capacity of 8,000 pounds per upright and 2,000 pounds per arm, with a safety factor of 1.65 to 1. Detailed specifications are provided for the dimensions, spacing, and features of the rack components. Required inspections and tests are outlined, and the contractor must provide certifications that the design and construction meet the stated requirements. This appendix is referenced in the overall solicitation for the Storage Aids System at Joint Base Charleston.
View the file
Other files for this federal contract opportunity
Show all 34
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
APPENDIX C
FOR
CANTILEVER RACK
AT
JOINT BASE CHARLESTON, SOUTH CAROLINA
FLIGHT LINE SUPPORT FACILITY
CSN: BCH205
DATE: 20 DECEMBER 2023
PREPARED BY:
Ashley Ambrose
ASHLEY AMBROSE
PROJECT ENGINEER
AFLCMC/EZPAE
Ronald Parsons
RONALD PARSONS
REVIEWER
AFLCMC/EZPAE
FA860424RB005 ATTACHMENT 4
THIS PAGE LEFT BLANK INTENTIONALLY
Joint Base Charleston – App C – Page i
Table of Contents
1. SCOPE
1.1. GENERAL SCOPE
1.2. DEFINITIONS
2. APPLICABLE DOCUMENTS
3. REQUIREMENTS
3.1. SYSTEM DESCRIPTION
3.2. CHARACTERISTICS
3.2.1. CANTILEVER RACK DESIGN
3.2.2. BASES
3.2.3. UPRIGHTS
3.2.4. BRACING
3.2.4.1. HORIZONTAL BRACING
3.2.4.2. DIAGONAL BRACING
3.2.5. ARMS
3.2.5.1. CONNECTORS
3.2.5.2. SAFETY CATCH FEATURE
3.2.6. ROW MARKERS
4. QUALITY ASSURANCE PROVISIONS
4.1. INSPECTIONS
4.2. TESTS
4.3. CERTIFICATIONS
THIS PAGE LEFT BLANK INTENTIONALLY
Joint Base Charleston – App C – Page 1
1. SCOPE
1.1. GENERAL SCOPE
This appendix establishes the minimum performance, design, fabrication, installation, and test requirements for cantilever rack for the 628th Logistics Readiness Squadron (LRS) in the
Flight Line Support Facility (FLSF) at Joint Base Charleston, South Carolina. The work shall be completed in accordance with this appendix, the Cover PD, and Air Force (AF) Drawings BCH205-
01. This appendix covers all equipment, materials, and labor necessary to complete installation of the system.
1.2. DEFINITIONS
Arm - Horizontal load carrying member which locks to the upright.
Base - Horizontal load carrying member which rests on the floor and supports the upright.
Bracing - Steel bracing which is used to attach adjacent uprights to each other and space adjacent uprights from each other. Bracing prevents twisting and swaying.
Upright - Vertical load carrying member which supports the cantilever arms. Also known as column.
2. APPLICABLE DOCUMENTS
Applicable documents shall be per section 2 of the Cover PD.
3. REQUIREMENTS
3.1. SYSTEM DESCRIPTION
The cantilever racks covered by this appendix are intended for storing a variety of nonstandard sized items. Storage and retrieval operations within the cantilever rack will be performed with the use of a Government-furnished general purpose forklift or the rider-reach truck specified in Appendix G. The racks shall be installed as shown on AF Drawing BCH205-01. The cantilever rack shall consist of the following:
A. Bases
B. Uprights
Joint Base Charleston – App C – Page 2
C. Bracing (horizontal and diagonal)
D. Arms
E. Mechanical fasteners and all other items required to install the cantilever rack.
3.2. CHARACTERISTICS
3.2.1. CANTILEVER RACK DESIGN
All components shall be constructed to produce a rigid, stable rack. The design and construction of each load bearing component shall ensure that the component is capable of sustaining the maximum load with a safety factor of not less than 1.65 to 1. No component of the cantilever rack shall exhibit any plastic (permanent) deformation.
3.2.2. BASES
There shall be one base for each upright in the system which shall be used as a shelf. It shall provide support for the upright and shall prevent the racks from leaning or collapsing when the rack is loaded to capacity. The base shall be at least as long as the upright depth plus the length of the arms. At a minimum each base shall be anchored to the floor on each end to prevent the rack from being pushed over backwards when loading the upper arm levels. If leveling shims are necessary, they shall have a hole that corresponds to the hole in the base and shall be equal in width to the base.
3.2.3. UPRIGHTS
Uprights shall have an overall height of 14 feet and a minimum capacity of 8,000 pounds. They shall have a means for adjusting arms on nominal three-inch centers from 24 inches above the floor to six inches from the top of the upright. Uprights shall be spaced on 48-inch centers.
3.2.4. BRACING
Horizontal and diagonal bracing shall be used to maintain alignment of the cantilever racks under varying loads and horizontal stresses. The bracing shall hold the uprights vertical, maintaining the proper spacing between the uprights.
Joint Base Charleston – App C – Page 3
3.2.4.1. HORIZONTAL BRACING
A minimum of three horizontal braces are required between every two uprights. These braces shall be evenly spaced along the upright.
3.2.4.2. DIAGONAL BRACING
A minimum of one diagonal, X-type brace is required between every other set of uprights (i.e., between uprights 1 and 2, 3 and 4, 5 and 6, etc.). They shall also be installed at each end of every row.
3.2.5. ARMS
Arms shall be provided and installed at levels as shown on AF
Drawing BCH205-01. Each arm shall be capable of supporting
2,000 pounds. The arms shall be 48 inches long and shall fasten securely to the uprights by use of a connector. The arms shall have an upward pitch between 1/4 inch per foot and 3/4 inch per foot to compensate for any deflection under full rated load. No arm, when loaded to capacity, shall deflect below the horizontal plane. Arms shall have removable end stops to prevent loose materials from falling off the arms. Arm capacity labels shall be applied to all arms. The labels shall be approximately 2” x
4” with the font size easy enough to read from a few feet away.
3.2.5.1. CONNECTORS
The connector shall be capable of transferring all loads and external forces of the arm to the column without failure of the connection, or damage to the column or connector. The connectors shall ensure a snug, metal-to-metal fit between the horizontal and vertical load carrying members.
3.2.5.2. SAFETY CATCH FEATURE
If adjustable connectors are used, a safety catch feature shall be provided on each arm to securely lock the arm to the column.
Design of the catch feature shall preclude the arm from dislodging due to impact or movement of the racks.
3.2.6. ROW MARKERS
Card holders shall be installed on the end of each rack section for row identification. One card holder shall be mounted on each end of every row. The card holders shall be large enough
Joint Base Charleston – App C – Page 4 for a minimum 8 inch by 8-inch card to be displayed. The card holders shall be mounted between 7 feet and 10 feet from the floor. Row identification cards will be made up by the warehouse personnel according to their established location assignment practices. A blank card will be provided by the contractor for each card holder. Card holders and cards shall be constructed of plastic.
4. QUALITY ASSURANCE PROVISIONS
4.1. INSPECTIONS
The cantilever rack shall be inspected to verify that it meets all the requirements of sections 1, 2, and 3 of this appendix and the Cover PD. These inspections shall be completed as part of the system checkout test and again as a part of the quality conformance test.
4.2. TESTS
The following tests shall be performed on the system as part of the system checkout test and again as a part of the quality conformance test.
No. Paragraph Description
1. 3.2.1. Maximum loads shall be placed randomly in the cantilever rack system. After not less than four hours, the test loads shall be removed, and the rack examined for signs of deformation. If any component of the system exhibits plastic deformation, the system fails the test.
2. 3.2.5. Maximum loads shall be placed randomly in the cantilever rack system. After not less than four hours, the system will be examined for signs of deformation. If any arm deflects below the horizontal plane, the system fails the test.
4.3. CERTIFICATIONS
The Contractor shall provide certification that the following requirements have been met. All certifications shall be provided in accordance with the Contract Data Requirements List.
Joint Base Charleston – App C – Page 5
No. Paragraph Certifications
1. 3.2.1. The design and construction of each load bearing component ensures that the component is capable of sustaining the maximum load with a safety factor of not less than 1.65 to 1.
Joint Base Charleston – App C – Page 6
THIS AREA LEFT BLANK INTENTIONALLY
TECHNICAL PROPOSAL QUESTIONNAIRE
FOR
Joint Base Charleston – Cantilever Rack TPQ - Page 1 of 2
CANTILEVER RACK
Solicitation Number: FA8604- -R-
Project Title: Storage Aids System
Base: Joint Base Charleston, SC CSN: BCH205
Appendix C – Cantilever Rack, 20 December 2023
This questionnaire shall be completed by the Offeror. All entries to this questionnaire shall be typed. The questionnaire will be used to determine the Offeror's understanding of the requirements and acceptability of the proposed equipment.
Please attach product literature/cut sheets for all equipment detailed in this questionnaire and attach any exceptions to the
Purchase Description Appendix as detailed below.
Cantilever Rack Manufacturer:
Paragraph Characteristics
3.2.1. Safety factor: _________________________________
3.2.2. Base length: ______________________________ inches
Anchor bolt diameter: _____________________ inches
Anchor bolt length: _______________________ inches
Number of anchors per base: _______________
3.2.3. Number of uprights provided: ______________
Upright capacity: _________________________ pounds
Upright model number: _____________________
Column spacing: ___________________________ inches
3.2.4.1. Number of horizontal braces between every two
uprights: ________________________________________
3.2.4.2. Number of diagonal braces between every other set
of uprights: _____________________________________
Solicitation Number: FA8604- -R-
Joint Base Charleston - Cantilever Rack TPQ – Page 2 of 2
3.2.5. Total number of arms provided: ___________________
Arm capacity: _____________________________ pounds
Arm length: _______________________________ inches
Upward pitch of arms: ____________ inches per foot
Arm model number: ________________________________
Will capacity labels be provided for each arm?
YES NO
3.2.6. Will row markers be provided as specified?
YES NO
EXCEPTIONS
Attach any exceptions taken to the Purchase Description
Appendix. Please outline those concerns in detail. Your exceptions will be reviewed to determine acceptability.
Are exceptions taken? YES NO
Number of pages attached: ____________________________________
File details come from the government source that posted it. Updated .