Appendix B2-SBP-6.133 Unit Pricing.docx

DOCX document 42 KB Posted

Attached to
EM2624 Yaeger Structural Stabilization and Repairs
Solicitation number
IFB1 GJTA 2027000021 2
Issued by
Pueblo County, Colorado

About this file

This is a Unit Pricing Form from the State of Colorado Office of the State Architect State Buildings Program for the Yaeger Structural Stabilization and Repairs project (EM2624) at Colorado Northwestern Community College. The form establishes a framework for unit pricing that will be applied to determine adjustments to the contract sum should changes in the work become necessary during project execution. The unit prices are valid through the date of contract completion as established on the Notice to Proceed. Nine unit pricing line items (U1 through U9) are provided with blank fields for descriptions and corresponding unit prices, though the specific descriptions and quantities are not completed in this template document.

All unit prices submitted by bidders must include the pro-rata share of all costs associated with materials, equipment, and disposal required to complete each work item. Overhead, profit, and bond costs will be calculated separately on a Change Order Proposal form (SC-6.312) and are not included in the unit price submissions. This unit pricing structure allows the project to manage scope changes systematically while maintaining cost control through pre-established rates for anticipated modifications to the work.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATE OF COLORADO

OFFICE OF THE STATE ARCHITECT

STATE BUILDINGS PROGRAM

UNIT PRICING FORM

Institution or Agency: Colorado Northwestern Community College / GJTA Project No./Project Name: EM2624 / Yaeger Structural Stabilization and Repairs

INSTRUCTIONS:

The unit prices below shall be used to determine adjustment to the contract sum when changes in the work involving said items are deemed necessary.

Unit Prices shall apply until the date of contract completion established on the Notice to Proceed.

All unit prices shall include the pro-rata share of all costs of materials, equipment and disposal required to complete the work item. Overhead, profit and bond will be calculated on a Change Order Proposal (SC-6.312).

(Architect/Engineer should complete a brief description below based on their complete description provided in Division 01 of their specification before inserting into the solicitation)

UNIT PRICING

Number
Description

Unit of Measure

Unit Price

U1

U2

U3

U4

U5

U6

U7

U8

U9

THE BIDDER

BY_________________________________________________________________

Company Name

BY__________________________________________________________________

Signature Date

SBP-6.131

Rev 7/2025 image1.jpeg