This document is a federal guide specification for high performance coating application on steel structures, specifically Section 09 97 13.27, dated 7 November 2024. The specification provides comprehensive technical requirements for a three-coat coating system consisting of a zinc-rich epoxy primer, epoxy intermediate coat, and polyurethane topcoat. The detailed guide covers critical aspects of coating application including surface preparation, environmental conditions, quality control, inspection procedures, and specific performance standards for each coating layer.

The specification mandates strict requirements for contractor qualifications, including certification by AMPP (Association for Materials Protection and Performance), and defines precise technical parameters for coating application. Key technical specifications include maintaining surface temperatures between 16-38 degrees Celsius, achieving specific dry film thickness (75 microns for primer and intermediate coats, 50 microns for topcoat), and ensuring a surface profile of 50-75 microns. The document also provides detailed testing protocols, environmental monitoring requirements, and quality assurance measures to ensure coating system integrity, with specific reference to Military Specifications MIL-DTL-24441 and MIL-PRF-85285 for material performance standards.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FY25 FED GUIDE SPECIFICATIONS AS OF 7 NOVEMBER 2024

VARIOUS LOCATIONS, KOREA

USACE / NAVFAC / AFCEC UFGS- 09 97 13. 27 ( Febr uar y 2021)

Change 1 - 08/ 22

Pr epar i ng Act i v i t y: NAVFAC Superseding UFGS- 09 97 13. 27 ( Oct ober 2016)

UNI FI ED FACI LI TI ES GUI DE SPECI FI CATI ONS

Ref er ences ar e i n agr eement wi t h UMRL dat ed Apr i l 2024

SECTION TABLE OF CONTENTS

DIVISION 09 - FINISHES

SECTION 09 97 13.27

HIGH PERFORMANCE COATING FOR STEEL STRUCTURES

PART 1 GENERAL

1.1 REFERENCES

1.2 DEFINITIONS

1.3 SUBMITTALS

1.4 QUALITY ASSURANCE

1.4.1 Contract Errors, Omissions, and Other Discrepancies

1.4.2 Corrective Action (CA)

1.4.2.1 Corrective Action Procedures

1.4.2.2 Implement Corrective Action

1.4.3 Coating Work Plan

1.4.4 Design Data

1.4.4.1 Containment System

1.4.5 Test Reports

1.4.5.1 Joint Sealant Qualification Test Reports

1.4.5.2 Coatings Qualification Test Reports

1.4.5.3 Metallic Abrasive Qualification Test Reports

1.4.5.4 Recycled Metallic Abrasive Field Test Reports (Daily and

Weekly)

1.4.6 Qualifications

1.4.6.1 Qualifications of Certified Industrial Hygienist (CIH)

1.4.6.2 Qualifications of Certified Protective Coatings Specialist

(PCS)

1.4.6.3 Qualifications of Coating Inspection Company

1.4.6.4 Qualifications of QC Specialist Coating Inspector

1.4.6.5 Qualifications Of Individuals Performing Abrasive Blasting

1.4.6.6 Qualifications of Testing Laboratory for Coatings

1.4.6.7 Qualifications of Testing Laboratory for Abrasive

1.4.6.8 Qualifications of Coating Contractors

1.4.6.9 Joint Sealant Materials

1.4.6.10 Coating Materials

1.4.6.11 Coating System Component Compatibility

1.4.6.12 Non-metallic Abrasive

1.4.6.13 Metallic Abrasive

SECTION 09 97 13.27 Page 1

1.4.7 Protective Coating Specialist (PCS)

1.4.8 Pre-Application Meeting

1.5 PRODUCT DATA

1.5.1 Joint Sealant Instructions

1.5.2 Coating System Instructions

1.6 DELIVERY AND STORAGE

1.7 COATING HAZARDS

1.8 JOB SITE REFERENCES

PART 2 PRODUCTS

2.1 JOINT SEALANT

2.2 COATING SYSTEM

2.2.1 Zinc-Rich Epoxy Primer Coat

2.2.2 Epoxy Intermediate Coat

2.2.3 Polyurethane Topcoat

2.3 COLOR IDENTIFICATION OF FUEL HANDLING AND STORAGE FACILITIES

2.4 COATING SAMPLE COLLECTION AND SHIPPING KIT

2.5 ABRASIVE SAMPLE COLLECTION AND SHIPPING KIT

2.6 TEST KITS

2.6.1 Test Kit for Measuring Chloride, Sulfate and Nitrate Ions on

Steel and Coated Surfaces

2.6.2 Test Kit for Identifying Amine Blush on Epoxy Surfaces

2.7 ABRASIVE

2.7.1 Non-metallic Abrasive

2.7.2 Metallic Abrasive

2.7.2.1 New and Remanufactured Steel Grit

2.7.2.2 Recycled Steel Grit

2.8 WHITE ALUMINUM OXIDE NON-SKID GRIT

PART 3 EXECUTION

3.1 REMOVAL OF COATINGS CONTAINING HAZARDOUS MATERIALS

3.2 COATING AND ABRASIVE SAMPLE COLLECTION AND TESTING

3.2.1 Coating Sample Collection

3.2.2 Abrasive Sample Collection

3.2.3 Coating Sample Test Reports

3.2.4 Abrasive Sample Test Reports

3.3 SURFACES TO BE COATED

3.4 LIGHTING

3.5 ENVIRONMENTAL CONDITIONS

3.5.1 Containment

3.5.2 Automated Monitoring Requirements

3.6 SURFACE PREPARATION

3.6.1 Abrasive Blasting Equipment

3.6.2 Operational Evaluation of Abrasive

3.6.3 Surface Standard

3.6.4 Pre-Preparation Testing for Surface Contamination

3.6.4.1 Pre-Preparation Testing for Oil and Grease Contamination

3.6.4.2 Pre-Preparation Testing for Soluble Salts Contamination

3.6.5 Abrasive Blasting

3.6.6 Disposal of Used Abrasive

3.6.7 Pre-Application Testing For Surface Contamination

3.6.7.1 Pre-Application Testing for Oil and Grease Contamination

3.6.7.2 Pre-Application Testing for Soluble Salts Contamination

3.6.7.3 Pre-Application Testing for Surface Cleanliness

3.7 MIXING AND APPLICATION OF SEALANT AND COATING SYSTEM

3.7.1 Preparation of Sealant and Coating Materials for Application

3.7.1.1 Mixing Sealant, Primer and Intermediate Coat Materials

SECTION 09 97 13.27 Page 2

3.7.1.2 Mixing Topcoat Material

3.7.1.3 Pot Life

3.7.1.4 Application Conditions and Recoat Windows

3.7.2 Amine Blush Testing of Epoxy Coat Prior to Overcoating

3.7.3 Application of Coating System and Joint Sealant

3.7.3.1 Application of Primer

3.7.3.2 Application of Stripe Coat

3.7.3.3 Application of Intermediate Coat

3.7.3.4 Non-skid for Stairs and Top

3.7.3.5 Application of Topcoat

3.7.3.6 Application of Joint Sealant

3.7.3.7 Procedure for Holiday and Spot Repairs of Newly Applied

Coating

3.7.3.8 Structure Occupancy After Coating Application

3.8 PROJECT IDENTIFICATION

3.9 FIELD QUALITY CONTROL

3.9.1 Coating Inspector

3.9.2 Field Inspection

3.9.2.1 Inspection Requirements

3.9.2.2 Inspection Report Forms

3.9.2.3 Daily Inspection Reports

3.9.2.4 Inspection Logbook

3.9.2.5 Inspection Equipment

3.10 FINAL CLEANUP

-- End of Section Table of Contents --

SECTION 09 97 13.27 Page 3

USACE / NAVFAC / AFCEC UFGS- 09 97 13. 27 ( Febr uar y 2021)

Change 1 - 08/ 22

Pr epar i ng Act i v i t y: NAVFAC Superseding UFGS- 09 97 13. 27 ( Oct ober 2016)

UNI FI ED FACI LI TI ES GUI DE SPECI FI CATI ONS

Ref er ences ar e i n agr eement wi t h UMRL dat ed Apr i l 2024

SECTION 09 97 13.27

HIGH PERFORMANCE COATING FOR STEEL STRUCTURES

NOTE: Thi s gui de speci f i cat i on cover s t he r equi r ement s f or z i nc- r i ch epoxy/ epoxy/ pol yur et hane coat i ng syst ems f or t he f ol l owi ng:

1. New st eel component s i n at mospher i c ser vi ce ( non- i mmer si on) whi ch r equi r e t he hi ghest per f or mance avai l abl e t o addr ess sever e envi r onment s, or wher e l i f e- cycl e cost s ar e j ust i f i ed t o avoi d f aci l i t y shut downs f or f ut ur e r e- coat i ngs; or wher e f i ni sh appl i cat i on degr adat i on, such as peel i ng, whi ch j eopar di zes asset s wi t hi n a f aci l i t y . Thi s i ncl udes, but i s not l i mi t ed t o, abovegr ound f uel t anks, wat er t anks, and pi pi ng; component s i dent i f i ed i n UFC 4- 211- 01 Ai r cr af t Mai nt enance Hangar s, cr anes, and t ower s.

2. New st r uct ur es and coat i ng of exi st i ng st r uct ur es wher e al l exi st i ng coat i ng mat er i al i s bei ng r emoved t o bar e met al .

3. Repai r i ng and coat i ng of gal vani zed sur f aces.

Repai r gal vani z i ng wi t h t he z i nc- r i ch pr i mer , and appl y gener al coat s of i nt er medi at e and t opcoat t o al l sur f aces.

Coor di nat e sur f ace pr epar at i on and coat i ng syst ems wi t h appl i cabl e Di v i s i on 05 and Di vi s i on 08 UFGS Sections.

Adher e t o UFC 1-300-02 Uni f i ed Faci l i t i es Gui de Speci f i cat i ons ( UFGS) For mat St andar d when edi t i ng t hi s gui de speci f i cat i on or pr epar i ng new pr oj ect speci f i cat i on sect i ons. Edi t t hi s gui de speci f i cat i on f or pr oj ect speci f i c r equi r ement s by addi ng, del et i ng, or r evi s i ng t ext . For br acket ed i t ems, choose appl i cabl e i t em( s) or i nser t appr opr i at e i nf or mat i on.

Remove i nf or mat i on and r equi r ement s not r equi r ed i n

SECTION 09 97 13.27 Page 4 r espect i ve pr oj ect , whet her or not br acket s ar e present.

Comment s, suggest i ons and r ecommended changes f or t hi s gui de speci f i cat i on ar e wel come and shoul d be submi t t ed as a Criteria Change Request (CCR) .

NOTE: To det er mi ne t he r equi r ement s f or mai nt enance of an exi st i ng coat i ng, a coat i ng i nspect i on, or coat i ng condi t i on sur vey ( CCS) , as descr i bed her ei n, shoul d be accompl i shed pr i or t o desi gni ng t he coat i ng pr oj ect . Wi t hout a compet ent i nspect i on, t her e i s no r el i abl e way t o det er mi ne t he t ype or condi t i on of t he exi st i ng coat i ng syst em. Wi t hout knowi ng t he exi st i ng condi t i ons, pr oper ( ef f ect i ve and f i nanci al l y suppor t abl e) sur f ace pr epar at i on or coat i ng syst em sel ect i on cannot be made.

NOTE: Thi s speci f i cat i on shoul d be edi t ed by an SSPC cer t i f i ed Pr ot ect i ve Coat i ngs Speci al i st ( PCS) t hat has f i ve or mor e year s of exper i ence pr epar i ng coat i ng speci f i cat i ons.

The desi gner shoul d not al t er t he pr oduct s and pr ocesses speci f i ed her ei n wi t hout t hor ough knowl edge of t he need f or t he changes and t he i mpl i cat i ons of t hose changes.

NOTE: The met r i c st andar d f or measur i ng coat i ng t hi ckness i s mi cr ons ( 25. 4 mi cr ons=1 mi l - use nomi nal 25 mi cr ons=1 mi l ) .

NOTE: Thi s speci f i cat i on i s f or an i ndust r y st andar d, 3 Coat , t hi n f i l m, coat i ng syst em t hat i s compl i ant wi t h EPA VOC r egul at i ons as of June 2000:

- Epoxy coat s 350 g/ l max. VOC

- Pol yur et hane Topcoat 350 g/ l max. VOC

The desi gner shal l r evi ew st at e and l ocal , r egul at i ons and det er mi ne whet her t he coat i ng i n t hi s Sect i on compl i es wi t h r est r i ct i ons on vol at i l e or gani c component s ( VOC) and ot her chemi cal constituents.

NOTE: Pr evi ous ver si ons of t hi s speci f i cat i on have i ncl uded a r equi r ement f or sur f aces t o be abr asi ve bl ast ed t o SSPC 7/ NACE No. 4, i nspect ed, and r epai r ed, pr i or t o coat i ng. That r equi r ement has

SECTION 09 97 13.27 Page 5 been r emoved f r om t hi s speci f i cat i on, and i f r equi r ed f or a r epai r pr oj ect , i t shoul d be i ncl uded i n t he st r uct ur al r epai r Sect i on of t he pr oj ect speci f i cat i on. Tai l or t he par agr aph t o t he needs of c l eani ng t hat wi l l be r equi r ed i n pr epar at i on f or r epai r s, and not e t hat t he abr asi ve bl ast i ng f or i nspect i on shoul d be accompl i shed i n such a manner t hat i t does not conf l i c t wi t h any sur f ace condi t i on r equi r ement s i n t hi s Sect i on, such as cr eat i ng excessi ve sur f ace pr of i l e t hat may r equi r e excessi ve pr i mer t hi ckness. For r epai r pr oj ect s, speci f y appr opr i at e por t i ons of t he st eel sur f aci ng r equi r ement s ( accor di ng t o NACE RPO178) f r om Sect i on

33 56 21. 17 SI NGLE WALL ABOVE GROUND FI XED ROOF

STEEL POL STORAGE TANK.

NOTE: For pur poses of t hi s speci f i cat i on, t he t er m " mai nt enance coat i ng" r ef er s t o mai nt enance over coat i ng as opposed t o compl et e r emoval of coat i ngs and r ecoat i ng. For mai nt enance coat i ng desi gns, or t o det er mi ne i f mai nt enance over coat i ng i s appr opr i at e, a coat i ng condi t i on sur vey ( CCS) shoul d be accompl i shed. The CCS shoul d be accompl i shed by per sonnel f r om a busi ness t hat r out i nel y per f or ms coat i ng eval uat i ons, and t he i ndi v i dual i nvest i gat or shoul d be Cer t i f i ed by SSPC as a Pr ot ect i ve Coat i ngs Speci al i st . The CCS shoul d be suf f i c i ent l y det ai l ed t o pr ovi de al l t echni cal i nf or mat i on about t he coat i ngs, and st r uct ur es t o be coat ed, r equi r ed t o pr oper l y desi gn t he pr oj ect . At a mi ni mum, t he CCS shoul d pr ovi de a det ai l ed r epor t of:

1. Exi st i ng coat i ng condi t i ons, i ncl udi ng condi t i on of coat i ng f i l m, and t he exi st ence of pot ent i al l y hazar dous subst ances t hat may i mpact coat i ng management ( i . e. l ead, cadmi um, chr omi um) ;

2. Anal ysi s of r emai ni ng coat i ng l i f e, sui t abi l i t y of over coat i ng, and t echni cal r equi r ement s f or overcoating;

3. Techni cal r ecommendat i ons f or t he most cost ef f ect i ve management of exi st i ng coat i ng syst ems, i ncl udi ng any hazar dous mat er i al s pr esent i n pai nt f i l m; and

4. Any ot her i nf or mat i on of i nt er est t o t he coat i ng syst em management t hat shoul d be i dent i f i abl e by an i ndi v i dual t r ai ned and exper i enced i n t he f i el d of coat i ng anal ysi s, coat i ng f ai l ur e anal ysi s, and coat i ng desi gn.

The scope of t he CCS shoul d be t ai l or ed t o t he speci f i c pr oj ect , and i t shoul d be r ecogni zed t hat whi l e mul t i pl e coat i ng f ai l ur es or def i c i enci es may l ook s i mi l ar t o t he unt r ai ned eye, t he r i sks of

SECTION 09 97 13.27 Page 6 gener al i z i ng t o save eval uat i on cost s ar e pot ent i al l y ver y hi gh. The cost of l ar ge- scal e f ai l ur e of t he over coat i ng, and compl et e r epl acement of t he coat i ng syst em, i s f ar mor e t han t he cost of a CCS f or al l but t he smal l est pr oj ect s.

The r i sks of over coat i ng can usual l y be avoi ded by desi gni ng pr oj ect t o r emove al l exi st i ng coat i ngs t o bar e met al , t hen pr ovi di ng appr opr i at e sur f ace pr epar at i on and coat i ng appl i cat i on. However , t he ext r a cost s of t he coat i ng r emoval , especi al l y i f cont ai ni ng hazar dous mat er i al , al ong wi t h t he cost of sur f ace pr epar at i on t o SSPC SP 10 Abr asi ve Bl ast t o Near - Whi t e Met al , may be exor bi t ant compar ed t o t he cost s of mai nt enance over coat i ng wher e t he exi st i ng coat i ng syst em i s i n f ai r - t o- good condi t i on.

Addi t i onal l y, NAVFAC Desi gn Pol i cy Let t er DPL- 09B- 0001, Lead- cont ai ni ng Pai nt on Non- r esi dent i al St r uct ur es of 26 Mar 92 pr ovi des gui dance f or managi ng pai nt s cont ai ni ng l ead and ot her hazar dous mat er i al s i n pl ace. The f act t hat l ead was hi ghl y used as a pr i mer i s i ndi cat i ve of i t s val ue t o t he cor r osi on cont r ol i ndust r y.

Pr emat ur e r emoval of sound l ead pr i mer i s not consi der ed t o be a good management pr act i ce.

Act i v i t i es shoul d consi der an annual CCS t o sur vey al l st r uct ur es t o be aut hor i zed f or desi gn i n t he comi ng year . When accompl i shed f or mul t i pl e pr oj ect s, t he per - st r uct ur e cost wi l l decr ease. By accompl i shi ng t hi s sur vey pr i or t o desi gn, t he basi s f or desi gn i s f ul l y i dent i f i ed.

The CCS can al so be a ver y usef ul t ool when used t o scr een st r uct ur es f or mai nt enance pai nt i ng r equi r ement s. A CCS can be scoped t o pr ovi de a gener al i nspect i on of many st r uct ur es t o scr een f or near - t er m over coat i ng or r ecoat i ng r equi r ement s, and subsequent i nvest i gat i on can be made t o pr ovi de appr opr i at e det ai l s f or pr oj ect pl anni ng and desi gn.

I t shoul d be poi nt ed out t hat t he aest het i c f eat ur es of a coat i ng do not def i ne t he coat i ng condi t i on;

t hey onl y descr i be how t he coat i ng l ooks. Many coat i ng syst ems have been r epl aced when onl y t he t opcoat i s i n need of " r ef ur bi shment . " Li kewi se, many st r uct ur es such as wat er t anks and f uel t anks have had compl et e coat i ng r epl acement when onl y t he r oof coat i ng needed r epl acement . A CCS can i dent i f y t he weak component s as wel l as t he sat i sf act or y component s, and pr opose sol ut i ons t o make maxi mum use of exi st i ng r esour ces.

SSPC: The Soci et y f or Pr ot ect i ve Coat i ngs ( SSPC) , has publ i shed a Technol ogy Updat e t i t l ed SSPC TU 3 Mai nt enance Over coat i ng. Thi s document shoul d be used as a gui de f or scopi ng t he CCS, f or accompl i shi ng t he CCS, and f or desi gni ng t he coat i ng

SECTION 09 97 13.27 Page 7 work.

NOTE: Desi gner s ar e encour aged t o cont act Rober t Jamond ( r ober t . j amond@navy. mi l ) pr i or t o begi nni ng a new Navy desi gn.

NOTE: Desi gner s ar e encour aged t o cont act t he Ai r For ce Ci vi l Engi neer Reachback Cent er ( af cec. r bc@us. af . mi l ) pr i or t o begi nni ng a new Ai r For ce desi gn.

PART 1 GENERAL

1.1 REFERENCES

NOTE: Thi s par agr aph i s used t o l i s t t he publ i cat i ons c i t ed i n t he t ext of t he gui de speci f i cat i on. The publ i cat i ons ar e r ef er r ed t o i n t he t ext by basi c desi gnat i on onl y and l i s t ed i n t hi s par agr aph by or gani zat i on, desi gnat i on, dat e, and t i t l e.

Use t he Ref er ence Wi zar d' s Check Ref er ence f eat ur e when you add a Ref er ence I dent i f i er ( RI D) out si de of t he Sect i on' s Ref er ence Ar t i c l e t o aut omat i cal l y pl ace t he r ef er ence i n t he Ref er ence Ar t i c l e. Al so use t he Ref er ence Wi zar d' s Check Ref er ence f eat ur e t o updat e t he i ssue dat es.

Ref er ences not used i n t he t ext wi l l aut omat i cal l y be del et ed f r om t hi s sect i on of t he pr oj ect speci f i cat i on when you choose t o r econci l e r ef er ences i n t he publ i sh pr i nt pr ocess.

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM C920 (2018) Standard Specification for Elastomeric Joint Sealants

ASTM D1200 (2010; R 2014) Viscosity by Ford Viscosity Cup

ASTM D1640/D1640M (2014) Standard Test Methods for Drying, Curing, or Film Formation of Organic Coatings

ASTM D3276 (2015; E 2016) Standard Guide for Painting

SECTION 09 97 13.27 Page 8

Inspectors (Metal Substrates)

ASTM D3925 (2002; R 2015) Sampling Liquid Paints and Related Pigmented Coatings

ASTM D4285 (1983; R 2018) Indicating Oil or Water in Compressed Air

ASTM D7127 (2017) Standard Test Method for Measurement of Surface Roughness of Abrasive Blast Cleaned Metal Surfaces using a Portable Stylus Instrument

ASTM E11 (2022) Standard Specification for Woven Wire Test Sieve Cloth and Test Sieves

INTERNATIONAL ORGANIZATION FOR STANDARDIZATION (ISO)

ISO 9001 (2015) Quality Management Systems- Requirements

SOCIETY FOR PROTECTIVE COATINGS (SSPC)

SSPC 7/NACE No.4 (2007) Brush-Off Blast Cleaning

SSPC AB 2 (2015; E 2016) Cleanliness of Recycled Ferrous Metallic Abrasive

SSPC AB 3 (2023; R 2023) Ferrous Metallic Abrasive

SSPC Guide 6 (2021) Guide for Containing Surface Preparation Debris Generated During Paint Removal Operations

SSPC Guide 12 (2023) Guide for Illumination of Industrial Painting Projects

SSPC PA 1 (2016) Shop, Field, and Maintenance Coating of Metals

SSPC PA 2 (2015; E 2018) Procedure for Determining Conformance to Dry Coating Thickness Requirements

SSPC QP 1 (2019) Standard Procedure for Evaluating the Qualifications of Industrial/Marine Painting Contractors (Field Application to Complex Industrial Steel Structures and Other Metal Components)

SSPC QP 5 (2022) Standard Procedure for Evaluating the Qualifications of Coating and Lining Inspection Companies

SSPC QS 1 (2015) Standard Procedure for Evaluating a Contractor's Advanced Quality Management System

SSPC SP 1 (2015) Solvent Cleaning

SECTION 09 97 13.27 Page 9

SSPC SP 10/NACE No. 2 (2015) Near-White Blast Cleaning

SSPC SP COM (2016; E 2017) Surface Preparation Commentary for Steel and Concrete Substrates

SSPC VIS 1 (2002; E 2004) Guide and Reference Photographs for Steel Surfaces Prepared by Dry Abrasive Blast Cleaning

SOCIETY OF AUTOMOTIVE ENGINEERS INTERNATIONAL (SAE)

SAE AMS-STD-595A (2017) Colors used in Government Procurement

U.S. DEPARTMENT OF DEFENSE (DOD)

MIL-A-22262 (1993; Rev B; Am 1 1994; Am 2 1996; Notice 1 2021) Abrasive Blasting Media Ship Hull Blast Cleaning

MIL-DTL-24441 (2009; Rev D; Notice 1 2021) Paint, Epoxy-Polyamide, General Specification for

MIL-DTL-24441/19 (2009; Rev C; Notice 1 2023) Paint, Epoxy-Polyamide, Zinc Primer, Formula 159, Type III

MIL-DTL-24441/31 (2009; Rev B; Notice 1 2021) Paint, Epoxy-Polyamide, White, Formula 152, Type

IV

MIL-PRF-85285 (2022; Rev F) Topcoat, Aircraft and Support Equipment

MIL-STD-161H (2005; Rev H) Identification Methods for Bulk Petroleum Products Systems Including Hydrocarbon Missile Fuels

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

29 CFR 1910-SUBPART Z Toxic and Hazardous Substances

29 CFR 1910.134 Respiratory Protection

29 CFR 1910.1000 Air Contaminants

29 CFR 1926.59 Hazard Communication

KOREAN INDUSTRIAL STANDARDS (KS)

KS F 4910 (2021) Sealants for Sealing and Glazing in Buildings

1.2 DEFINITIONS

Definitions are provided throughout this Section, generally in the paragraph where used, and denoted by capital letters.

SECTION 09 97 13.27 Page 10

1.3 SUBMITTALS

NOTE: Revi ew Submi t t al Descr i pt i on ( SD) def i ni t i ons i n Sect i on 01 33 00 SUBMI TTAL PROCEDURES and edi t t he f ol l owi ng l i s t , and cor r espondi ng submi t t al i t ems i n t he t ext , t o r ef l ect onl y t he submi t t al s r equi r ed f or t he pr oj ect . The Gui de Speci f i cat i on t echni cal edi t or s have cl assi f i ed t hose i t ems t hat r equi r e Gover nment appr oval , due t o t hei r compl exi t y or cr i t i cal i t y, wi t h a " G. " Gener al l y, ot her submi t t al i t ems can be r evi ewed by t he Cont r act or ' s Qual i t y Cont r ol Syst em. Onl y add a " G" t o an i t em i f t he submi t t al i s suf f i c i ent l y i mpor t ant or compl ex i n cont ext of t he pr oj ect .

For Ar my pr oj ect s, f i l l i n t he empt y br acket s f ol l owi ng t he " G" c l assi f i cat i on, wi t h a code of up t o t hr ee char act er s t o i ndi cat e t he appr ovi ng aut hor i t y. Codes f or Ar my pr oj ect s usi ng t he Resi dent Management Syst em ( RMS) ar e: " AE" f or Ar chi t ect - Engi neer ; " DO" f or Di st r i ct Of f i ce ( Engi neer i ng Di v i s i on or ot her or gani zat i on i n t he Di st r i ct Of f i ce) ; " AO" f or Ar ea Of f i ce; " RO" f or Resi dent Of f i ce; and " PO" f or Pr oj ect Of f i ce. Codes f ol l owi ng t he " G" t ypi cal l y ar e not used f or Navy and Ai r For ce pr oj ect s.

The " S" c l assi f i cat i on i ndi cat es submi t t al s r equi r ed as pr oof of compl i ance f or sust ai nabi l i t y Gui di ng Pr i nci pl es Val i dat i on or Thi r d Par t y Cer t i f i cat i on and as descr i bed i n Sect i on 01 33 00 SUBMI TTAL

PROCEDURES.

Choose t he f i r st br acket ed i t em f or Navy and Ai r For ce pr oj ect s, or choose t he second br acket ed i t em f or Ar my pr oj ect s.

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-05, Design Data

Containment System

SD-06 Test Reports

Joint Sealant Qualification Test Reports

Coatings Qualification Test Reports

Metallic Abrasive Qualification Test Reports

SECTION 09 97 13.27 Page 11

Coating Sample Test Reports

Abrasive Sample Test Reports

Inspection Report Forms

Daily Inspection Reports

Recycled Metallic Abrasive Field Test Reports (Daily and Weekly)

SD-07 Certificates

Contract Errors, Omissions, and Other Discrepancies

Corrective Action Procedures

Coating Work Plan

Qualifications of Certified Industrial Hygienist (CIH)

Qualifications Of Individuals Performing Abrasive Blasting

Qualifications of Certified Protective Coatings Specialist (PCS)

Qualifications of Coating Inspection Company

Qualifications of QC Specialist Coating Inspector

Qualifications of Testing Laboratory for Coatings

Qualifications of Testing Laboratory for Abrasive

Qualifications of Coating Contractors

Joint Sealant Materials

Coating Materials

Coating System Component Compatibility

Non-metallic Abrasive

Metallic Abrasive

SD-08 Manufacturer's Instructions

Joint Sealant Instructions

Coating System Instructions

SD-11 Closeout Submittals

Disposal of Used Abrasive

Inspection Logbook ; G

SECTION 09 97 13.27 Page 12

1.4 QUALITY ASSURANCE

1.4.1 Contract Errors, Omissions, and Other Discrepancies

Submit all errors, omissions, and other discrepancies in contract documents the Contracting Officer within 30 days of contract award for all work covered in this Section, other than the work that will not be uncovered until a later date. All such discrepancies shall be addressed and resolved, and the Coating Work Plan modified, prior to beginning the Initial and Follow-Up phases of work. Discrepancies that become apparent only after work is uncovered shall be identified at the earliest discoverable time and submitted for resolution. Schedule time (Float) should be built into the project schedule at those points where old work is to be uncovered or where access is not available during the first 30 days after award, to allow for resolution of contract discrepancies.

1.4.2 Corrective Action (CA)

CA shall be included in the Quality Control Plan.

1.4.2.1 Corrective Action Procedures

Develop procedures for determining the root cause of each non-compliance, developing a plan to eliminate the root cause so that the non-compliance does not recur, and following up to ensure that the root cause was eliminated. Develop Corrective Action Request (CAR) forms for initiating CA, and for tracking and documenting each step.

1.4.2.2 Implement Corrective Action

The Contractor shall take action to identify and eliminate the root cause of each non-compliance so as to prevent recurrence. These procedures shall apply to non-compliance in the work, and to non-compliance in the QC System. Corrective actions shall be appropriate to the effects of the non-compliance encountered. Each CAR shall be serialized, tracked in a Log to completion and acceptance by the Contracting Officer, and retained in project records. The Corrective Action Log, showing status of each CAR, shall be submitted to the Contracting Officer monthly. A CAR may be initiated by either the Contractor or the Contracting Officer. The Contracting Officer must approve each CAR at the root cause identification stage, the plan for elimination stage, and the close out stage after verification that the root cause has been eliminated.

1.4.3 Coating Work Plan

NOTE: For mai nt enance pai nt i ng, add r equi r ement f or pr e- wor k det er mi nat i on of t he exi st i ng sur f ace pr of i l e. I f pai nt r emoval i s speci f i ed i n anot her Sect i on, such as a bl ast c l eani ng pr i or t o i nspect i on or r epai r , or i n t he l ead r emoval Sect i on, i ncl ude t hi s eval uat i on of exi st i ng pr of i l e such t hat t he pai nt r emoval oper at i on does not cr eat e excessi ve pr of i l e.

This work plan shall be considered as part of the Quality Control Plan.

Provide procedures for reviewing contract documents immediately after

SECTION 09 97 13.27 Page 13 award to identify errors, omissions, and discrepancies so that any such issues can be resolved prior to project planning and development of detailed procedures.

Provide procedures for verification of key processes during Initial Phase to ensure that contract requirements can be met. Key processes shall include surface preparation, coating application and curing, inspection, and documentation, and any other process that might adversely impact orderly progression of work.

Provide procedures for all phases of coating operations, including planned work, rework, repair, inspection, and documentation. Address mobilization and setup, surface preparation, coating application, coating initial cure, tracking and correction of noncompliant work, and demobilization.

Coordinate work processes with health and safety plans and confined space entry plans. For each process, provide procedures that include appropriate work instructions, material and equipment requirements, personnel qualifications, controls, and process verification procedures.

Provide procedures for inspecting work to verify and document compliance with contract requirements, including inspection forms and checklists, and acceptance and rejection criteria.

[ Provide procedures for determining the existing surface profile under paint, and procedures for ensuring that the profile is not increased beyond the maximum profile specified herein.

] Provide procedures for correcting noncompliant work. Detailed procedures are required in advance to avoid delays in meeting overcoat windows as well as to avoid delays in production. Provide procedures for repairing defects in the coating film, such as runs, drips, sags, holidays, overspray, as well as how to handle correct coating thickness noncompliance, any other areas of repair or rework that might be adversely affected by delays in preparing and approving new procedures.

If a procedure is based on a proposed or approved request for deviation, the deviation shall be referenced. Changes to procedures shall be noted by submittal number and date approved, clearly delineating old requirements and new requirements, so that the records provide a continuous log of requirements and procedures.

1.4.4 Design Data

1.4.4.1 Containment System

Submit complete design drawings and calculations for the scaffolding and containment system, including an analysis of the loads which will be added to the structure by the containment system and waste materials. A registered engineer shall approve calculations and scaffold system design.

1.4.5 Test Reports

1.4.5.1 Joint Sealant Qualification Test Reports

Submit test results from independent laboratory of representative samples of joint sealant material. Samples must have been tested within the last three years. Submit results as required in ASTM C920 or KS F 4910 . Note that testing is a pre-qualification requirement.

SECTION 09 97 13.27 Page 14

1.4.5.2 Coatings Qualification Test Reports

Submit test results from independent laboratory of representative samples of each coating material. Samples must have been tested within the last three years. Submit results for epoxy materials as required in paragraph QUALIFICATION INSPECTION of MIL-DTL-24441 , and as revised by paragraph COATING SYSTEM herein. Submit results for polyurethane materials as required in paragraph QUALIFICATION INSPECTION of MIL-PRF-85285 , and as revised by paragraph COATING SYSTEM herein. Note that requirement for QUALIFICATION INSPECTION is a pre-qualification requirement, and involves the same testing required for listing in the Qualified Products List of the respective material. See appropriate Military Specification for specific test requirements.

1.4.5.3 Metallic Abrasive Qualification Test Reports

Submit results for abrasive as required in paragraph 4 REQUIREMENTS of SSPC AB 3 . Submit test results from independent laboratory of representative samples of each abrasive to be used on the jobsite.

Samples must have been tested within the last three years. Note that this testing is for the purpose of prequalifying the abrasive.

1.4.5.4 Recycled Metallic Abrasive Field Test Reports (Daily and Weekly)

Submit test results from independent laboratory of daily and weekly Quality Control testing required by SSPC AB 2 , as modified in paragraph

ABRASIVE.

1.4.6 Qualifications

1.4.6.1 Qualifications of Certified Industrial Hygienist (CIH)

Submit name, address, telephone number, FAX number, and e-mail address of the independent third party CIH. Submit documentation that hygienist is certified by the American Board of Industrial Hygiene or Ministry of Employment and Labor Republic of Korea in comprehensive practice, including certification number and date of certification/recertification.

Provide evidence of experience with hazards involved in industrial coating application work.

1.4.6.2 Qualifications of Certified Protective Coatings Specialist (PCS)

Submit name, address, telephone number, FAX number, and e-mail address of the independent third party PCS. Submit documentation that specialist is certified by the Association for Materials Protection and Performance (AMPP) (formerly SSPC: The Society for Protective Coatings (SSPC)) as a PCS, including certification number and date of certification/recertification. If the PCS is employed by the same coating inspection company to which the coating inspector is employed, this does not violate the independent third-party requirements. The PCS shall remain certified during the entire project, and the Contracting Officer shall be notified of any change in certification status within 10 days of the change. The PCS shall not be the designated coating inspector.

1.4.6.3 Qualifications of Coating Inspection Company

Submit documentation that the coating inspection company that will be performing all coating inspection functions is certified by AMPP to the requirements of SSPC QP 5 prior to contract award, and shall remain

SECTION 09 97 13.27 Page 15 certified while accomplishing any coating inspection functions. The coating inspection company must remain so certified for the duration of the project. If a coating inspection company's certification expires, the firm will not be allowed to perform any inspection functions, and all surface preparation and coating application work must stop, until the certification is reissued. Requests for extension of time for any delay to the completion of the project due to an inactive certification will not be considered and liquidated damages will apply. Notify the Contracting Officer of any change in coating inspection company certification status.

1.4.6.4 Qualifications of QC Specialist Coating Inspector

Submit documentation that each coating inspector is employed, and qualified to SSPC QP 5 , Level III, by the selected coating inspection company. Each inspector shall remain employed by the coating inspection company while performing any coating inspection functions.

1.4.6.5 Qualifications Of Individuals Performing Abrasive Blasting

Submit name, address, and telephone number of each person that will be performing abrasive blasting. Submit documentation that each blaster is qualified by AMPP to the C-7 Abrasive Blaster Certification. Each blaster shall remain qualified during the entire period of abrasive blasting, and the Contracting Officer shall be notified of any change in qualification status.

1.4.6.6 Qualifications of Testing Laboratory for Coatings

Submit name, address, telephone number, FAX number, and e-mail address of the independent third party laboratory selected to perform testing of coating samples for compliance with specification requirements. Submit documentation that laboratory is regularly engaged in testing of paint samples for conformance with specifications, and that persons performing analyses are qualified.

1.4.6.7 Qualifications of Testing Laboratory for Abrasive

Submit name, address, telephone number, FAX number, and e-mail address of the independent third party laboratory selected to perform testing of abrasive for compliance with specification requirements. Submit documentation that laboratory has experience in testing samples of abrasive for conformance with specifications, and that persons performing analyses are qualified.

1.4.6.8 Qualifications of Coating Contractors

NOTE: I f pr oj ect i nvol ves r emoval of pai nt cont ai ni ng hazar dous mat er i al s, add r equi r ement f or SSPC QP- 2 cer t i f i cat i on i n sect i on of speci f i cat i on wher e t he hazar dous pai nt r emoval i s speci f i ed, gener al l y Sect i on 02 83 00 LEAD REMEDI ATI ON.

NOTE: Sol i c i t at i ons r equi r i ng cer t i f i cat i on f or pr equal i f i cat i on shoul d poi nt out t he exi st ence and l ocat i on of t he cer t i f i cat i on r equi r ement on t he PROJECT I NFORMATI ON FORM. Thi s r equi r ement must be

SECTION 09 97 13.27 Page 16 poi nt ed out i n t he sol i c i t at i on document s f or t he " pr i or t o cont r act awar d" r equi r ement t o be enf or ceabl e. Cer t i f i cat i on i s a speci al r esponsi bi l i t y r equi r ement pur suant t o FAR 9. 104- 2 Speci al St andar ds. Thi s i s anal ogous t o r equi r i ng bi dder s t o have a speci f i ed l evel of exper i ence or exper t i se and GAO has sust ai ned t hese t ypes of speci al r equi r ement s.

All Contractors and Subcontractors that perform surface preparation or coating application shall be certified to either ISO 9001 or SSPC QP 1 and SSPC QS 1 prior to contract award, and shall remain certified while accomplishing any surface preparation or coating application. The painting Contractors and painting Subcontractors must remain so certified for the duration of the project. If a Contractor's or Subcontractor's certification expires, the firm will not be allowed to perform any work until the certification is reissued. Requests for extension of time for any delay to the completion of the project due to an inactive certification will not be considered and liquidated damages will apply.

Notify the Contracting Officer of any change in Contractor certification status.

1.4.6.9 Joint Sealant Materials

Provide manufacturer's certification of conformance to contract requirements.

1.4.6.10 Coating Materials

Provide manufacturer's certification of conformance to contract requirements.

1.4.6.11 Coating System Component Compatibility

Provide certification from each manufacturer of components of the coating system, epoxy primer, epoxy intermediate, and polyurethane topcoat, that the supplied coating material is suitable for use in the specified coating system. Each manufacturer shall identify the specific products, including manufacturer's name, which their product may be used with. The certification shall provide the name of the manufacturer that will provide technical support for the entire system. When all coating materials are manufactured by one manufacturer, this certification is not required.

1.4.6.12 Non-metallic Abrasive

Provide manufacturer's certification that the materials are currently approved by the Naval Sea Systems Command and listed on the Qualified Products Lists (QPL) for the specified materials.

1.4.6.13 Metallic Abrasive

Provide manufacturer's certification of conformance to contract requirements and provide copies of test results.

1.4.7 Protective Coating Specialist (PCS)

The PCS shall be considered a QC Specialist and shall report to the QC Manager, as specified in Section 01 45 00 QUALITY CONTROL. The PCS shall

SECTION 09 97 13.27 Page 17 approve all submittals prior to submission to the QC Manager for approval or submission to the government for approval.

1.4.8 Pre-Application Meeting

After approval of submittals but prior to the initiation of coating work, Contractor representatives, including at a minimum, project superintendent and QC manager, paint foreman, coating inspector, and PCS shall have a pre-application coating preparatory meeting. This meeting shall be in addition to the pre-construction conference. Specific items addressed shall include: corrective action requirements and procedures, coating work plan, safety plan, coordination with other Sections, inspection standards, inspection requirements and tools, test procedures, environmental control system, safety plan, and test logs. Notify Contracting Officer at least ten days prior to meeting.

1.5 PRODUCT DATA

1.5.1 Joint Sealant Instructions

Submit manufacturer's printed instructions including detailed application procedures, minimum and maximum application temperatures, and curing procedures. Include Safety Data Sheets (SDS) for materials to be used at the job site in accordance with 29 CFR 1926.59 .

1.5.2 Coating System Instructions

Submit manufacturer's printed instructions including detailed mixing and application procedures, number and types of coats required, minimum and maximum application temperatures, and curing procedures. Include Safety Data Sheets (SDS) for materials to be used at the job site in accordance with 29 CFR 1926.59 .

1.6 DELIVERY AND STORAGE

Ship, store, and handle materials in accordance with SSPC PA 1 , and as modified in this Section. Maintain temperature in storage spaces between 5 and 29 degrees C , and air temperature more than 3 degrees C above the dew-point at all times. Inspect materials for damage prior to use and return non-compliant materials to manufacturer. Remove materials with expired shelf life from government property immediately and notify the Contracting Officer.

If materials are approaching shelf life expiration and an extension is desired, samples may be sent to the manufacturer, along with complete records of storage conditions, with a request for shelf life extension.

If the manufacturer finds the samples and storage data suitable for shelf life extension, the manufacturer may issue an extension, referencing the product evaluation and the review of storage records. Products may not be extended longer than allowed in the product specification.

1.7 COATING HAZARDS

NOTE: Thi s speci f i cat i on Sect i on shoul d be used wi t h Sect i on 01 35 26 GOVERNMENTAL SAFETY

REQUIREMENTS".

Ensure that employees are trained in all aspects of the safety plan.

SECTION 09 97 13.27 Page 18

Specified coatings may have potential health hazards if ingested or improperly handled. The coating manufacturer's written safety precautions shall be followed throughout mixing, application, and curing of the coatings. During all cleaning, cleanup, surface preparation, and paint application phases, ensure that employees are protected from toxic and hazardous chemical agents which exceed concentrations in 29 CFR 1910.1000 .

Comply with respiratory protection requirements in 29 CFR 1910.134 . The CIH shall approve work procedures and personal protective equipment.

1.8 JOB SITE REFERENCES

NOTE: I ncl ude any ot her j obsi t e r el at ed r ef er ences t hat mi ght be added dur i ng desi gn.

Make available to the Contracting Officer at least one copy each of

ASTM D3276, ASTM D3925, ASTM D4285, ASTM D7127, SSPC SP COM, SSPC SP 1 ,

SSPC 7/NACE No.4 , SSPC SP 10/NACE No. 2 , SSPC PA 1 , SSPC PA 2 , SSPC Guide 6 , SSPC VIS 1 , SSPC QP 1 , SSPC QS 1 , and an SSPC Certified Contractor Evaluation Form at the job site.

PART 2 PRODUCTS

2.1 JOINT SEALANT

TT-S-00230, Type II, Class B

2.2 COATING SYSTEM

NOTE: Use t he f i r st br acket ed par agr aph f or ent i r el y f i el d appl i ed syst ems.

Use t he second br acket ed par agr aph opt i on f or appl i ed coat i ngs syst ems appl i ed ent i r el y i n t he shop, wher e r equi r ed such as, but not l i mi t ed t o, ext er i or and i nt er i or f er r ous met al component s i dent i f i ed i n UFC 4- 211- 01 Ai r cr af t Mai nt enance Hangars.

Ref er t o Par t 3 of t hi s Sect i on f or sur f ace preparation.

Coor di nat e wi t h appl i cabl e Di v i s i on 05 UFGS Sect i ons and Di vi s i on 08 UFGS Sect i ons.

Alternate systems or products will not be considered. Provide a complete system (primer, intermediate coat, top coat) material from one supplier.

[ Apply the entire coating system in the field. Remove all shop-applied primer prior to final field surface preparation and coating system application. Adjust all shop preparation to avoid conflicts with final surface preparation requirements.

][ Prepare surface and apply the complete coating system in the shop. Follow all temperature, humidity, and testing requirements listed herein.

SECTION 09 97 13.27 Page 19

] The Military specification epoxy and polyurethane products specified in this Section do not require approval for listing on the QPL prior to contract award, as indicated in paragraph 3.2 of MIL-DTL-24441 and paragraph 3.1 of MIL-PRF-85285 . Testing of products by an independent laboratory to the QUALIFICATION INSPECTION requirements of MIL-DTL-24441 and MIL-PRF-85285 prior to contract award is required. See specific submittal requirements in paragraph QUALITY ASSURANCE.

2.2.1 Zinc-Rich Epoxy Primer Coat

Epoxy polyamide, MIL-DTL-24441/19 (Formula 159, Type III).

2.2.2 Epoxy Intermediate Coat

Epoxy polyamide, MIL-DTL-24441/31 (Formula 152, Type IV, White (Tinted)).

Tint to approximately SAE AMS-STD-595A color number 27778 parchment using pigment dispersions prepared for epoxy paint tinting. Manufacturer shall tint material and appropriately label. All other requirements of this Military Specification apply.

2.2.3 Polyurethane Topcoat

NOTE: Check wi t h t he act i v i t y t o det er mi ne t he desi r ed t opcoat col or and f i ni sh. Gener al l y, use whi t e f or Navy pr oj ect s and bei ge f or Ai r For ce pr oj ect s. Col or number 17925 i s whi t e, and 27769 i s bei ge. FAA Saf et y col or s ar e Whi t e 17875 and Or ange 12197. Al ways speci f y cont r ast i ng col or s bet ween coat s. Fi ni sh schedul e must r ef l ect col or sel ect ed below.

Polyurethane coating topcoat of MIL-PRF-85285 , Type II, [White SAE AMS-STD-595A color number 17925][Beige SAE AMS-STD-595A color number 27769 in gloss][White SAE AMS-STD-595A color number 17875, and Orange SAE AMS-STD-595A color number 12197].

Modify paragraph 3.6.4 of MIL-PRF-85285 , Viscosity and Pot Life, as follows:

The viscosity of the admixed coating, when tested in accordance with ASTM D1200 through a No. 4 Ford cup, shall be as follows:

Time from mix (minimum) Maximum time through a No. 4 Ford cup

Initially 30 seconds

2 hours 60 seconds

4 hours No gel

Modify paragraph 3.7.1 of MIL-PRF-85285 , Drying Time, as follows:

When applied by spray techniques and when tested in accordance with ASTM D1640/D1640M , the coating shall be set-to-touch within four hours and dry-hard within eight hours (see 4.6 and table I).

SECTION 09 97 13.27 Page 20

[ 2.3 COLOR IDENTIFICATION OF FUEL HANDLING AND STORAGE FACILITIES

Piping, conduit, and tank identification shall be in accordance with MIL-STD-161H . Mark direction of fluids in accordance with MIL-STD-161H .

The NATO symbol for JP-8 is F-34.

] 2.4 COATING SAMPLE COLLECTION AND SHIPPING KIT

Provide a kit that contains one liter can for the base of each coating material, an appropriately sized can for each activator, dipping cups for each component to be sampled, a shipping box sized for the samples to to be shipped, and packing material. Mark cans for the appropriate component. Provide shipping documents, including either pre-paid shipping or a shipper number that can be used by the QC Manager to arrange pickup, addressed to the approved coating testing laboratory.

2.5 ABRASIVE SAMPLE COLLECTION AND SHIPPING KIT

Provide a kit that contains one suitable plastic bag or container for each sample to be collected. Mark containers for the appropriate component.

Provide shipping documents, including either pre-paid shipping or a shipper number that can be used by the QC Manager to arrange pickup, addressed to the approved coating testing laboratory.

2.6 TEST KITS

2.6.1 Test Kit for Measuring Chloride, Sulfate and Nitrate Ions on Steel and Coated Surfaces

Provide test kits that meet all of the following requirements:

a. Contains all materials,supplies, tools, and instructions for field testing and on-site quantitative evaluation of chloride, sulfate, and nitrate ions;

b. Extract solution is acidic, factory pre-measured, pre-packaged, and of uniform concentration;

c. Components and solutions are mercury free and environmentally friendly;

d. Contains new materials and solutions for each test extraction;

e. Contains an extraction test container (vessel, sleeve, cell) that creates a sealed, encapsulated environment during salt ion extraction;

f. Contains a test extract container suitable for testing the following steel surfaces: horizontal (up/down configuration), vertical, flat, curved, smooth, pitted, and rough;

g. All salt ion concentrations are directly measured in micrograms per square centimeter.

2.6.2 Test Kit for Identifying Amine Blush on Epoxy Surfaces

Provide test kits that meet all of the following requirements:

a. Is a completely self-contained field test kit with all materials, supplies, tools, and instructions to perform tests and indicate the presence of unreacted amines;

SECTION 09 97 13.27 Page 21

b. Uses an identifiable, consistent, uniform, pre-packaged, factory pre-measured indicating solution;

c. Contains no mercury or lead and is environmentally friendly;

d. Contains a solution of an unreacted amine for the purpose of "self checking" the indicator solution;

2.7 ABRASIVE

The referenced abrasive specifications have maximum limits for soluble salts contamination, however, this maximum level of contamination does not guarantee that contamination will not be transferred to the steel surface during abrasive blasting. Other factors such as on-site handling and recycling can allow contamination of abrasive. Contractors are cautioned to verify that the chosen abrasive, along with work and storage processes, allow the final surface cleanliness requirements to be achieved.

Successful testing of chlorides in abrasive does not negate the final acceptance testing of steel surfaces.

NOTE: The f ol l owi ng par agr aph i s mandat or y f or al l NAVFAC PAC pr oj ect s. Al l ot her agenci es may use i t af t er checki ng appl i cabi l i t y .

[ Interpret MIL-A-22262 to include the meaning that abrasive material contains a maximum one percent by weight of any toxic substance listed in either Table Z-1, Z-2, or Z-3 or 29 CFR 1910-SUBPART Z , with the exception of inert or nuisance dust materials, arsenic, beryllium, cadmium, cobalt, lead, mercury, rhodium, silver, tellurium, thallium, and uranium.

NOTE: Reduce al l owabl e gr oss gamma r adi oact i v i t y t o 5 pi cocur i es per gr am f or al l NAVFAC PAC pr oj ect s.

Reduce i n ot her ar eas i f st at es or l ocal i t i es require.

2.7.1 Non-metallic Abrasive

Conform to MIL-A-22262 , Type I (Inorganic materials)[ except that the gross gamma radioactivity shall not exceed 5 picocuries per gram].

Abrasive shall be approved by the Naval Sea Systems Command and listed on the appropriate Qualified Products List (QPL) for the specified materials. Use sampling procedures and testing frequencies as prescribed in MIL-A-22262 . Use abrasive that is specifically selected and graded to provide a sharp, angular profile to the specified depth. Do not use ungraded abrasive. Make adjustments to processes or abrasive gradation to achieve specified surface profile. Recycled non-metallic abrasive shall meet all requirements of the specification each time that it is placed in the blast pot.

2.7.2 Metallic Abrasive

2.7.2.1 New and Remanufactured Steel Grit

Conform to the chemical and physical properties of SSPC AB 3 Class 1

SECTION 09 97 13.27 Page 22

(Steel) only[, except that the gross gamma radioactivity shall not exceed 5 picocuries per gram]. Class 2 (Iron) abrasive shall not be used.

To develop a suitable work mix from new steel abrasive, a minimum of 200 - 400 recycles is required, therefore, it is advantageous for a Contractor to use remanufactured steel grit or grit reclaimed from a previous project. Such grit shall be considered to conform if it can be traced to new grit conforming to SSPC AB 3 Class 1 and it meets all cleanliness requirements of SSPC AB 3 Class 1 when brought to the current jobsite.

Submit one representative sample of this work mix to the laboratory for testing, along with samples of new material.