This is an Appendix containing a Performance Requirements Summary that outlines monitoring criteria and acceptable quality levels for contract performance across five main standards.
The document establishes performance objectives and acceptable quality levels (AQL) across five key areas: Cost, Schedule, Quality, Business Relations, and Staffing Management. Under Cost, the contractor must demonstrate cost control by explaining deviations in monthly progress reports (98% AQL) and justifying all deviations to the Government (100% AQL), while submitting invoices timely, accurately, and completely (92% AQL). For Schedule performance, the contractor must demonstrate monthly progress at 92% AQL and submit 95% of all contract deliverables/CDRLs by required due dates. Quality requirements mandate that contractor deliverables receive satisfactory ratings with no more than 2 unsatisfactory ratings annually (100% review standard), monthly progress reports address significant issues 100% of the time, and OPUS Suite Readiness Based Sparing Input Files and Results be accurate and complete 98% of the time as evaluated by Naval Sea Logistics Center through random sampling. Business Relations requires the contractor to respond to all Government requests within 2 business days at a 95% AQL. Staffing Management standards require the contractor to notify Government of personnel replacements within 5 business days (95% AQL), ensure replacements are qualified (100% notification AQL), and report labor disputes within 7 days of identification (100% reporting AQL). All performance areas are subject to positive/negative performance evaluation incentives.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Solicitation Amendment - N6572626R30000001.pdf | ||
| Solicitation Amendment N6572626R30000001 SF 30.pdf | ||
| Attachment 4_Personnel Qualifications.pdf | ||
| Attachment 3_Staffing_Plan.xlsx | XLSX spreadsheet | |
| Appendix C_Table of Deliverables.pdf | ||
| Appendix B_Non-Disclosure Summary.pdf | ||
| NAVSUPINST 4441.37A - NAVSEAINST 4441.12A - MARRC-RB (04 SEP 2020).pdf | ||
| Exhibit F_DD 1423_CDRL A006.pdf | ||
| Exhibit C_DD 1423_CDRL A003.pdf | ||
| Attachment 5_Past Performance Reference.docx | DOCX document | |
| Solicitation - N6572626R3000.pdf | ||
| Exhibit E_DD 1423_CDRL A005.pdf | ||
| Exhibit B_DD 1423_CDRL A002.pdf | ||
| Exhibit A_DD 1423_CDRL A001.pdf | ||
| Attachment 6_Cost_Proposal_Spreadsheet.xlsx | XLSX spreadsheet | |
| Attachment 2_Quality Assurance Surveillance Plan.pdf | ||
| Attachment 1_DD Form 254.pdf | ||
| Exhibit D_DD 1423_CDRL A004.pdf |
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
APPENDIX A: PERFORMANCE REQUIREMENTS SUMMARY
Standard Performance Objective
Performance Standard
Monitoring Method
Acceptable Quality Level
(AQL)
Incentiv e
1. Cost (a) Contractor shall demonstrate Cost Control.
Cost deviations from quotation are explained to the satisfactio n of the Government.
(a) Contractor monthly progress report addresses any cost deviations for the period.
(a) 100% review of contractor monthly progress reports.
(a) Any cost deviation details are delivered to the Government POC for the Contract 98% of the time with the monthly progress report for the period.
Contractor shall justify cost deviations to the satisfaction of the Government POC for the Contract 100% of the time.
Positive negative performa nce evaluati on
(b) Contractor invoices shall be timely, accurate, and complete.
(b) Accurate and complete invoices are submitted in accordance with the terms of the contract.
(b) 100% review of contractor invoices.
(b) Contractor shall submit 92% of all invoices in a timely manner, free of errors, and provide complete information without rework.
Positive negative performa nce evaluati on
2.
Schedule
(a)Contract or shall demonstrate schedule control through progress towards completion on a project level basis.
(a) Progress Demonstrated
(a) 100% review of contractor monthly progress reports.
(a) Contractor monthly reports clearly demonstrate project progress 92% of the time.
Positive negative performa nce evaluati on
(b) Contractor shall submit deliverable s/CDRLs by the required due date.
(b) On-Time Delivery
(b) 100% review of contractor deliverable receipt dates against due dates.
(b) Contractor shall submit 95% of all contract deliverables in accordance with the contract schedule.
Positive negative performa nce evaluati on
3.
Quality
(a) Contractor deliverable s/CDRLs are submitted in accordance with the terms of the contract and are of an acceptable quality level.
(a) Contractor Deliverables are rated Satisfactory
(a) 100% review and rating of contractor deliverables
(a) The average of all contractor deliverable ratings is satisfactory, with no more than 2 “final” unsatisfactor y deliverable ratings per year.
Positive negative performa nce evaluati on
(b) Monthly Progress Reports adequately
(b) Progress Reports address significant
(a) 100% Review of progress
(b) Monthly Reports address performance
Positive negative performa detail any significant discussions /issues related to performance issues identified.
reports. issues 100% of the time.
nce evaluati on
(c) Contractor shall deliver models with accurate OPUS Suite Readiness Based Sparing Input Files and Results aligned with configurati on, provisionin g, reliability block diagram, and system operational data elements.
(c) Models are submitted to Naval Sea Logistics Center and the customer of record.
(c) Random Sampling review of contractor models by Naval Sea Logistics Center
(c) Contractor will provide models, results, and deliverables which Naval Sea Logistics Center evaluates as accurate 98% of the time.
Positive negative performa nce
(d) Contractor shall deliver models with complete OPUS Suite Readiness Based Sparing Input files
(d) Models are submitted to Naval Sea Logistics Center and the customer of record.
(d) Random Sampling review of contractor models by Naval Sea Logistics Center
(d) Contractor will provide models, results, and deliverables Naval Sea Logistics Center evaluates as complete 98%
Positive negative performa nce and Results aligned with configurati on, provisionin g, reliability block diagram, and system operational data elements.
of the time.
4.
Business Relations
(a) Contractor is responsive to all Government phone calls and emails related to significant matters (Cost, Schedule, and Performance
(a) Contractor responds to Government requests within 2 business days.
(a) Tracking, logging, and review of contractor response to requests.
(a) Contractor responds to all requests within 2 business days 95% of the time.
(a) Positive negative performa nce evaluati on
5.
Staffing
Managemen t
(a) Contractor advises Government promptly when personnel shall require replacement
(a) Contractor notifies Government within 5 business days when personnel replacement is required.
(a) Review of personnel replacement requirement notification s
(a) Contractor advises Government within 5 business days 95% of the time.
Positive negative performa nce
(b) Contractor replaces personnel with personnel that meet contract requirement s.
(b) Personnel replacements are qualified for position
(b) Review of personnel replacement notification s
(b) Contractor notifies Government of replacements 100% of the time.
Positive negative performa nce evaluati on
(c) Contractor notifies Government promptly of any actual or potential Labor Disputes that may affect performance
(c) Labor Disputes are reported within 7 days of identificati on.
(c) Review of contractor notification of Labor Disputes.
(c) Labor Disputes are reported 100% of the time.
Positive negative performa nce