Appendix_6-UWS_(004183D).pdf
PDF 913 KB Posted
- Attached to
- Countywide Mast Arms - Group 3
- Solicitation number
- 23-0131-ITB CONSTRUCTION
- Issued by
- Pinellas County, Florida
About this file
The image is an Adobe PDF portfolio opening screen instructing users to open the document in Acrobat X or Adobe Reader X or later, with an Adobe PDF logo and a "Get Adobe Reader Now!" button. It appears to be a standard software compatibility prompt for viewing a PDF document.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
For the best experience, open this PDF portfolio in
Acrobat X or Adobe Reader X, or later.
Get Adobe Reader Now!
http://www.adobe.com/go/reader
Page 2 of 3 PINELLAS COUNTY 10/15//2019
UTILITY WORK SCHEDULE
COUNTY PROJECT #: 004183D PROJECT TITLE #: US 19 / E TARPON AVE
UTILITY AGENCY/OWNER (UAO): Knology Broadband of Florida D.B.A. WOW! (Wide Open West)
B. Special Conditions / Constraints
1: WOW! field inspector Dave Hamlin will be field point of contact for WOW! during construction duration of the project.
2: WOW! Working Days are during normal business hours, Monday – Friday, 7:30 am – 5:00 pm (excluding Holidays). WOW! will arrange any works after hour with an advance notice through WOW! field representative Dave Hamlin. Please call 48 hours prior to schedule any after hours work if needed. After hours emergency contact please call Richard LaGanga @ 727-422-8040 UAO project representative.
3: WOW! is to have access throughout the duration of the project to monitor and maintain WOW! facilities for the ability to provide service.
4: WOW! does not anticipate any prior to or during construction work at this time.
5: Where WOW is attached as joint user to Duke Energy poles, and the duct it leases with Frontier both have provided zero-day work schedules at the time of review and do not appear to have any conflicts.
Page 3 of 3 PINELLAS COUNTY 10/15//2019
COUNTY PROJECT #: 004183D PROJECT TITLE #: US 19 / E TARPON AVE
UTILITY AGENCY/OWNER (UAO): Knology Broadband of Florida D.B.A. WOW! (Wide Open West)
SECTION C: UAO’s WORK ACTIVITIES
Action
Utility Facility (Type, Size, Material, Status)
From Station/ Offset
To
Utility Work Description Dependent Activity TCP Phase
Consecutive Days
Prior To During
Summary of Utility Work and Execution
NON-CONSTRUCTION ITEMS
Prior to Pinellas County Project Construction
During Pinellas County Project Construction
Special Conditions / Constraints
2022-08-19T07:34:47-0400
Scott Baird
Page 1 of 3 PINELLAS COUNTY 07/20//2022
COUNTY PROJECT #: 004183D
PROJECT TITLE: COUNTRYWIDE MAST ARM SIGNAL HARDENING AND
INTERSECTION IMPROVEMENT - Intersection of E Tarpon Ave at US 19
UTILITY AGENCY/OWNER (UAO): DUKE DISTRIBUTION
A. Summary of Utility Work and Execution
NON-CONSTRUCTION ITEMS
ESTIMATED *CALENDAR
DAYS
CONSTRUCTION ITEMS
Total Preliminary 0 Prior to Pinellas County Project Construction 0
Total Material Procurement 0 During Pinellas County Project Construction 0
Total Right-of-Way Permitting 0
Total NON-Construction Time 0 * Calendar Days = UAO Work Days x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule
This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Pinellas County, the roadway contractor and other right-of-way users, the location, relocation, adjustment, installation and/or protection of their facilities on this Pinellas County project.
The following data is based on Pinellas County final design phase construction plans dated 12/2021 . Any deviation by Pinellas County or its contractor from the plans, as provided, may require assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond their control and that could not be reasonably anticipated and avoided with the exercise of due diligence. The UAO agrees to notify Pinellas County in writing prior to starting, stopping, resuming or completing work.
UAO Project Representative: Bill Ruland Telephone Number: 727-820-4641
UAO Field Representative: Bill Ruland Telephone Number: 727-820-4641
No changes to forms document.
Appendix “Changes to Forms Document” is attached. Number of Attachment Pages.
Authorized Utility Agent: Engineer of Record: Acceptance by Pinellas County:
(Signature) (Signature) (Signature)
William Ruland
(Printed Name) (Printed Name) (Printed Name)
Senior Engineering Technologist
(Title) (Title) (Title)
7/26/2022
(Date) (Date) (Date)
Benjamin Rodgers
Traffic Engineer
8/12/2022
Page 2 of 3 PINELLAS COUNTY 07/20//2022
• This is based on plans provided by the County dated 12/2021
• Any “Found Conflicts” during construction, or any modification to the plans provided by the County, will be addressed per the 2017 UAM section 5 and the 337.4 State Statute.
Page 3 of 3 PINELLAS COUNTY 07/20//2022
Material, Status)
Utility Work Description Dependent Activity
TCP
During
Overhead and underground
12.47kv distribution facilities along and across the right-of-way at various locations from begin to end project limits.
To remain in place and in service Duration of project construction N/A 0 0
2022-08-15T07:19:20-0400
Scott Baird
Page 1 of 3 PINELLAS COUNTY 07/20//2022
COUNTY PROJECT #: PROJECT TITLE: 004183D - Countywide Mast Arm Hardening U.S. 19 at Tarpon Avenue
UTILITY AGENCY/OWNER (UAO):
A. Summary of Utility Work and Execution
NON-CONSTRUCTION ITEMS
CONSTRUCTION ITEMS
Total Preliminary 0 Prior to Pinellas County Project Construction 0
Total Material Procurement 0 During Pinellas County Project Construction 0
Total Right-of-Way Permitting 0
Total NON-Construction Time 0 * Calendar Days = UAO Work Days x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule
This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Pinellas County, the roadway contractor and other right-of-way users, the location, relocation, adjustment, installation and/or protection of their facilities on this Pinellas County project.
The following data is based on Pinellas County final design phase construction plans dated . Any deviation by Pinellas County or its contractor from the plans, as provided, may require assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond their control and that could not be reasonably anticipated and avoided with the exercise of due diligence. The UAO agrees to notify Pinellas County in writing prior to starting, stopping, resuming or completing work.
UAO Project Representative: Kyle Perkins Telephone Number: 727-313-6167
UAO Field Representative: Seve Theodosis (Vince) Telephone Number: 727-9428326
No changes to forms document.
Appendix “Changes to Forms Document” is attached. Number of Attachment Pages.
Authorized Utility Agent: Engineer of Record: Acceptance by Pinellas County:
(Signature) (Signature) (Signature)
Kyle Perkins
(Printed Name) (Printed Name) (Printed Name)
Engineer
(Title) (Title) (Title)
8-8-2022
(Date) (Date) (Date)
Frontier
004183D
Traffic Engineer
Benjamin Rodgers
8/12/2022
Page 2 of 3 PINELLAS COUNTY 07/20//2022
Page 3 of 3 PINELLAS COUNTY 07/20//2022
Material, Status)
Utility Work Description Dependent Activity
TCP
During
2022-08-15T07:19:52-0400
Scott Baird
File details come from the government source that posted it. Updated .