Appendix_4_-SPECIAL_NOTICES_-_Revised.pdf
PDF 87 KB Posted
- Attached to
- Countywide Mast Arms - Group 3
- Solicitation number
- 23-0131-ITB CONSTRUCTION
- Issued by
- Pinellas County, Florida
About this file
This document is a Special Notices Appendix for a federally funded project administered by Pinellas County, Florida, specifically for the Countywide Mast Arms - Group 3 project. The project involves replacement of existing signalization with mast arms at three intersections: US 19 at Tarpon Avenue, Lake St George Drive at Tampa Road, and West Lake Road at Tampa Road, with improvements designed to meet ADA guidelines. The project is funded through the Federal Emergency Management Administration (FEMA) and requires adherence to specific grant agreement terms and supplemental conditions outlined in the document's attachments.
The contract necessitates strict compliance with federal requirements, which may change due to updates in federal law, regulations, or the underlying agreement. Contractors are required to coordinate utility investigations and location prior to and during work, including directional drilling for conduit crossings. Additionally, the contractor must obtain and adhere to a construction agreement for work on state roadways, specifically coordinating with the Florida Department of Transportation Permitting. The document emphasizes that the contractor's superintendent must be an employee or contract employee of the prime contractor, and sub-contractors cannot serve as agents for the prime contractor.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
APPENDIX 4
SPECIAL NOTICES
P.I.D. NO. 004183A-3
Countywide Mast Arms – Group 3, PID Nos. 004183D, 004183E, 004183F
In Pinellas County, Florida
NOTICES TO CONTRACTOR
This is a federally funded project through the Federal Emergency Management Administration (FEMA) and administered by Pinellas County. The project requires adherence to the grant agreement in Attachment A and Supplemental Conditions contained in Attachment B this Appendix 4, the compliance and reporting of which are required by this contract. There are required forms contained in Attachment C this Appendix 4 that are due upon submittal of the Invitation to bid. Additionally, wherever a conflict occurs within the Invitation to Bid documents, the federal terms of which are contained in this Appendix 4 shall prevail as listed in Section I Agreement, subparagraph 4.
Changes In Requirements:
Federal requirements that apply to Pinellas County under the Underlying Agreement with FEMA and any Amendments thereto may change due to changes in federal law, regulation, other requirements, or guidance, or changes in the Underlying Agreement including any information incorporated by reference and made part of that Underlying Agreement. Any such changes will apply to this Construction Agreement and any sub-contractor agreements.
Section B, Part 21.E.2. Contractor’s Superintendent:
The Contractor’s Superintendent and agent are synonymous with regards to this section and shall be an employee or contract employee of the prime contractor. A sub-contractor shall not serve as an agent for the prime contractor.
Utility Coordination:
Utility coordination and investigations were performed during the design phase of this project and utility work schedules are provided. However, Contractor is fully responsible for coordinating with and locating all utilities prior to beginning and during work, including directional drilling operations for conduits crossing roadways.
State Roadways:
Pinellas County has obtained a construction agreement for work proposed on State roadways. The contractor must adhere to the construction agreement, a copy of which is included in Appendix 1. The Contractor must coordinate with the Florida Department of Transportation Permitting prior to beginning work on all State roadways (US 19) and keep them informed of all work activities involving their facility.