Appendix_5_-_004183P_UWS_Package.pdf

PDF 535 KB Posted

Attached to
Countywide Mast Arms - Group 3 (PID 004183A)
Solicitation number
23-1147-ITB-C
Issued by
Pinellas County, Florida

About this file

This document is a Utility Work Schedule (UWS) for the Pinellas County Countywide Mast Arms - Group 3 project (PID 004183P), involving multiple utility agencies including Duke Energy Distribution, Spectrum Sunshine State LLC, TECO Peoples Gas, Frontier, and Knology Broadband (WOW!). The project focuses on signalization improvements at the intersection of Park Boulevard and Johnson Boulevard, with utility work involving relocating, adjusting, and protecting various utility facilities. Each utility agency has submitted a detailed work schedule outlining their specific activities, including installing new poles, adjusting aerial spans, removing existing facilities, and coordinating with the county's road contractor. The work schedules specify estimated calendar days for preliminary tasks, material procurement, and construction activities, with each agency providing unique constraints and working conditions.

The project is federally funded through the Federal Emergency Management Administration (FEMA) and administered by Pinellas County. The utility work schedules are based on final design phase construction plans dated January 12, 2022, with each utility agency agreeing to notify Pinellas County in writing prior to starting, stopping, resuming, or completing work. The documents outline special conditions such as normal business hours, emergency contact numbers, access requirements, and coordination protocols. Each utility agency emphasizes the need for careful excavation near their facilities, coordination with the road contractor, and adherence to safety regulations. The utility work is contingent on various factors, including approved permits, joint use agreements, and potential revisions to design plans.

View the file

Other files

File Type Posted
Pricing_Proposal23-1147(reference_only)a.pdf PDF
Countywide_Mast_Arms_-_Group_3_(PID_004183A)_(Addendum_#3_Revision).pdf PDF
QUALIFICATION_SUBMITTAL_FORM.pdf PDF
APPENDIX_4_-SPECIAL_NOTICES_revised5.pdf PDF
Sample_Agreement-23-1147.pdf PDF
Appendix_6_-_004183M.Geotechnical_Report_54th_and_113th_REV_032822_SS.pdf PDF
Sample_Performance_and_Payment_Bonds.pdf PDF
Affdavit_of_Release_and_Guarantee_23-1147.pdf PDF
SBE_FORM.pdf PDF
Final_Plans_-_004183M,_004183N,_004183O,_004183P.pdf PDF
Final_Plans_-_004183D,_004183E,_004183F.pdf PDF
Affdavit_of_Release_and_Guarantee.pdf PDF
Appendix_5_-_004183N_UWS_Package.pdf PDF
Appendix_6_-_004183P.Geotechnical_Report_Park_Blvd_at_Johnson_Blvd_SS.pdf PDF
Appendix_6_-_004183_Geotechnical_Engineering_Services_Report.pdf PDF
Sample_Application_for_Payment.pdf PDF
APPENDIX_1-Permits.pdf PDF
Appendix_5_-_004183M_UWS_Package.pdf PDF
Florida_Trench_Safety_Form.pdf PDF
Specifications.pdf PDF
Airport_Security_Program.pdf PDF
Appendix_5_-_004183O_UWS_Package.pdf PDF
Appendix_6_-_004183N.Geotechnical_Report_Park_Blvd_and_Ridge_Rd_SS.pdf PDF
Appendix_6_-_004183O.Geotechnical_Report_Park_Blvd_and_Seminole_Blvd_SS.pdf PDF
E-Verify_Affidavit.pdf PDF
OpenGov_Fillable-_Final.pdf PDF
Appendix_5_-_004183D_UWS_Package.pdf PDF
Appendix_5_-_004183E_UWS_Package.pdf PDF
Appendix_5_-_004183F_UWS_Package.pdf PDF
Bid_Submittal_Form-JOC.pdf PDF
Sample_Change_Order.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Page 1 of 3 PINELLAS COUNTY 11/19//2019

UTILITY WORK SCHEDULE

COUNTY PROJECT #: 004183P PROJECT TITLE: Signalization Plans – Park Blvd and Johnson Blvd

UTILITY AGENCY/OWNER (UAO): Duke Energy Distribution

A. Summary of Utility Work and Execution

NON-CONSTRUCTION ITEMS

ESTIMATED *CALENDAR

DAYS

CONSTRUCTION ITEMS

Total Preliminary 10 Prior to Pinellas County Project Construction 12 Total Material Procurement 30 During Pinellas County Project Construction 4 Total Right-of-Way Permitting 30 Total NON-Construction Time 70 * Calendar Days = UAO Work Days x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule

This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Pinellas County, the roadway contractor and other right-of-way users, the location, relocation, adjustment, installation and/or protection of their facilities on this Pinellas County project.

The following data is based on Pinellas County final design phase construction plans dated 1/12/2022. Any deviation by Pinellas County or its contractor from the plans, as provided, may require assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond their control and that could not be reasonably anticipated and avoided with the exercise of due diligence. The UAO agrees to notify Pinellas County in writing prior to starting, stopping, resuming or completing work.

UAO Project Representative: Carter Williams Telephone Number: 727-348-8384 UAO Field Representative: Carter Williams Telephone Number: 727-348-8384

No changes to forms document.

Appendix “Changes to Forms Document” is attached. Number of Attachment Pages.

Authorized Utility Agent: Engineer of Record: Acceptance by Pinellas County:

(Signature) (Signature) (Signature)

Carter Williams

Joshua Reichert

Tim Messina

(Printed Name) (Printed Name) (Printed Name)

Engineer III

Engineer of Record

Utility Coordinator

(Title) (Title) (Title)

4/27/2022

7/18/2022

(Date) (Date) (Date)

Joshua Reichert Digitally signed by Joshua Reichert Date: 2022.07.19 10:29:04 -04'00'Carter Williams Digitally signed by Carter Williams

Date: 2022.07.25 09:21:27 -04'00' Scott Baird Digitally signed by Scott Baird Date: 2022.07.26 08:56:11 -04'00'

Page 2 of 3 PINELLAS COUNTY 11/19//2019

B. Special Conditions / Constraints

1. Duke Energy and/or Duke Energy subcontractors normal work schedule is Monday through Friday from 7 a.m. to 5 p.m., excluding observed holiday's (New Years day, Good Friday, Memorial Day, July 4th, Labor day, Thanksgiving Day, the Friday after Thanksgiving, Christmas Eve Day and Christmas Day).

2. Duke Energy line crew availability may be affected or limited due to our required response to emergency conditions. This limitation will be dependent upon the severity of the emergency.

3. Emergency number for nights, weekends and Duke Energy Florida holidays is (800) 228-8485.

4. Bucket truck access must be maintained to all of this UAO’s facilities including: poles, pull boxes, transformers, and switchgear locations throughout the duration of the project construction for maintenance and outage restoration.

5. All NESC and OSHA required clearances from energized conductors and equipment should be maintained. Covering of conductors will not be provided by this UAO as this does not decrease the required code clearances.

6. Upon completion of any or all of relocations, as described in this approved Utility Work Schedule, any additional relocation of newly installed system that is required due to deviation by the County or its roadway contractor from the plans as provided to this UAO will be done at the expense of the County or its roadway contractor.

Upon notification of such change, UAO will proceed with the design and construction of the additional relocation within the standard work schedule of this UAO

7. De-energization of primary voltage (example: 12.47kV) power lines requires coordination with multiple internal groups. Notify this UAO via email at least 20 days before any de-energization is required at each mast arm location. Due to the existing circuit loadings, distribution conductors may require de-energizing and grounding during non-peak hours (may require night work by County contractor if circuit loading during daytime is not feasible).

8. Temporary removal of streetlight wire or secondary voltage conductors (example: 120/240V) requires coordination with multiple internal groups. Notify this UAO via email at least 20 days before any temporary removal of wire is required at each location.

9. Temporary removed services or de-energizing conductors will result in loss of power. This includes possible loss of power to the traffic signal cabinet and/or streetlight circuits and/or electric meters. This UAO is not responsible for generators needed during power outage.

10. Any bracing or holding of this UAO’s poles will require 20 days advance written notice via email to this UAO.

11. All new electrical services requested by Pinellas County, or its contractor will be required to conform to “Requirements for Electric Service and Meter Installations” latest edition.

12. To establish a new service account the responsible party for the new service must call 866-372-4663.

13. A Contribution in Aid to Construction (CIAC) will be required for underground riser/pedestal installations and any additional required line construction work that does not meet the required revenue ratio as specified in this UAO’s approved rates and tariffs.

14. Duke Energy Distribution cannot remove old facilities until new facilities are energized and existing customers services have been relocated.

Page 3 of 3 PINELLAS COUNTY 11/19//2019

SECTION C: UAO’s WORK ACTIVITIES

Action

Utility Facility (Type, Size, Material, Status)

From Station/ Offset

To Station/ Offset

Utility Work Description Dependent Activity TCP Phase

Consecutive Days

Prior To During

1 Concrete Pole 156+80 , 52 Lt

156+80 , 52 Lt

Install new concrete pole with fuse to raise line and for future de-energization. Prior to drill shaft installation N/A 6 0

2 Concrete Pole 156+80 , 52 Lt

156+80 , 52 Lt Open fuse to de-energize overhead line Prior to drill shaft installation N/A 0 2

3 Concrete Pole 155+30 , 52 Lt

155+30 , 52 Lt Install new concrete pole to raise line. Remove existing concrete pole Joint use to transfer before pole removal N/A 6 0

4 Concrete Pole 155+30 , 52 Lt

155+30 , 52 Lt Remove overhead streetlight wire Prior to drill shaft installation N/A 0 2

For

Scott Baird Digitally signed by Scott Baird Date: 2022.07.26 07:49:38 -04'00'

Page 1 of 3 PINELLAS COUNTY 11/19//2019

COUNTY PROJECT #: 004183P PROJECT TITLE: Park Blvd and Johnson Blvd

UTILITY AGENCY/OWNER (UAO): Spectrum Sunshine State LLC.

A. Summary of Utility Work and Execution

NON-CONSTRUCTION ITEMS ESTIMATED *CALENDAR

DAYS

CONSTRUCTION ITEMS ESTIMATED *CALENDAR

DAYS

Total Preliminary 10 Prior to Pinellas County Project Construction 0 Total Material Procurement 45 During Pinellas County Project Construction 1 Total Right-of-Way Permitting 0 Total NON-Construction Time 0 * Calendar Days = UAO Work Days x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule

This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Pinellas County, the roadway contractor and other right-of-way users, the location, relocation, adjustment, installation and/or protection of their facilities on this Pinellas County project.

The following data is based on Pinellas County final design phase construction plans dated 01/12/22. Any deviation by Pinellas County or its contractor from the plans, as provided, may require assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond their control and that could not be reasonably anticipated and avoided with the exercise of due diligence. The UAO agrees to notify Pinellas County in writing prior to starting, stopping, resuming or completing work.

UAO Project Representative: Art Dubinas Telephone Number: 727-290-1509 UAO Field Representative: Art Dubinas Telephone Number: 727-290-1509

No changes to forms document.

Appendix “Changes to Forms Document” is attached. Number of Attachment Pages.

Authorized Utility Agent: Engineer of Record: Acceptance by Pinellas County:

(Signature) (Signature) (Signature)

Art Dubinas Joshua Reichert Tim Messina (Printed Name) (Printed Name) (Printed Name)

Construction Coordinator Engineer of Record Utility Coordinator (Title) (Title) (Title)

06/02/2022 7/19/2022 (Date) (Date) (Date)

Joshua Reichert Digitally signed by Joshua Reichert Date: 2022.07.19 17:37:57 -04'00' Scott Baird Digitally signed by Scott Baird

Date: 2022.07.21 11:55:13 -04'00'

Page 2 of 3 PINELLAS COUNTY 11/19//2019

COUNTY PROJECT #: 004183P PROJECT TITLE: Park Blvd and Johnson Blvd

UTILITY AGENCY/OWNER (UAO): Spectrum Sunshine State LLC.

1. Spectrum relocation activities will not commence until a signed UWS and approved permit are received.

2. Spectrums normal business hours are from 8am to 5pm, Monday through Friday (excluding Holidays).

3. Any work outside of normal business hours are to be scheduled a minimum of 72 hours in advance.

4. Spectrum is to have access throughout the duration of the project to monitor and maintain Spectrum facilities for the ability to provide service.

5. UAO Field Rep listed on page 1 will be point of contact for Spectrum during the entire duration of the construction project unless otherwise notified.

6. Extreme caution is to be used when excavating near or around Spectrum facilities.

7. Spectrums relocation work is contingent on securing an approved joint use agreement (JUA) with Duke-Energy to attach to their existing and proposed power-poles.

Page 3 of 3 PINELLAS COUNTY 11/19//2019

COUNTY PROJECT #: 004183P PROJECT TITLE: Park Blvd and Johnson Blvd

UTILITY AGENCY/OWNER (UAO): Spectrum Sunshine State LLC.

Utility Facility (Type, Size, Material, Status)

From Station/ Offset

To Station/ Offset

Utility Work Description Dependent Activity TCP Phase

Consecutive Days

Prior To During

1 Coax in 2” conduit 156+30 54LT 156+28 56LT Protect and adjust if needed Ped. Signal installation 1 0 1

Page 1 of 3 PINELLAS COUNTY 11/19//2019

COUNTY PROJECT #: 004183AP PROJECT TITLE: CR 694 (PARK BLVD) AT JOHNSON BLVD

UTILITY AGENCY/OWNER (UAO): TECO PEOPLES GAS

A. Summary of Utility Work and Execution

NON-CONSTRUCTION ITEMS

CONSTRUCTION ITEMS

Total Preliminary Prior to Pinellas County Project Construction Total Material Procurement During Pinellas County Project Construction 2 Total Right-of-Way Permitting Total NON-Construction Time * Calendar Days = UAO Work Days x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule

This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Pinellas County, the roadway contractor and other right-of-way users, the location, relocation, adjustment, installation and/or protection of their facilities on this Pinellas County project.

The following data is based on Pinellas County final design phase construction plans dated 01/12/2022 . Any deviation by Pinellas County or its contractor from the plans, as provided, may require assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond their control and that could not be reasonably anticipated and avoided with the exercise of due diligence. The UAO agrees to notify Pinellas County in writing prior to starting, stopping, resuming or completing work.

UAO Project Representative: Bolivar A. Feliz Nunez Telephone Number: 813-275-3712 UAO Field Representative: Raymond Zwissler Telephone Number: 727-423-7124

No changes to forms document.

Appendix “Changes to Forms Document” is attached. 2 Number of Attachment Pages.

Authorized Utility Agent: Engineer of Record: Acceptance by Pinellas County:

(Signature) (Signature) (Signature)

Bolivar A. Feliz Nunez

Tim Messina

(Printed Name) (Printed Name) (Printed Name)

Gas Design Tech I

Utility Coordinator

(Title) (Title) (Title)

03/25/2022

(Date) (Date) (Date)

Digitally signed by Bolivar Feliz Nunez Date: 2022.03.25 08:18:03 -04'00' Joshua Reichert Digitally signed by Joshua Reichert

Date: 2022.07.14 23:05:22 -04'00' Scott Baird Digitally signed by Scott Baird Date: 2022.07.21 14:37:25 -04'00'

Page 2 of 3 PINELLAS COUNTY 11/19//2019

1. TECO/PEOPLE GAS REQUEST A COPY OF THE CONTRACTOR’S APROVED CPM SCHEDULE WITHING 5 DAYS OF

APPROVAL.

2. THE TECO PEOPLES GAS 24-HOUR EMERGENCY NUMBER 1-877 TECO PGS (1-877-832- 6747).

3. TECO PEOPLES GAS CREW AVAILABILITY MAY BE AFFECTED OR LIMITED DUE TO OUR REQUIRED RESPONSE TO EMERGENCY CONDITIONS ELSEWHERE. THIS LIMITATION WILL BE DEPENDENT UPON THE SEVERITY AND LOCATION

OF THE EMERGENCY.

4. TECO PEOPLES GAS SUBCONTRACTORS NORMAL WORK SCHEDULE IS MONDAY THROUGH FRIDAY FROM 8 A.M. TO 5 P.M., EXCLUDING TECO PEOPLES GAS OBSERVED HOLIDAY'S (NEW YEARS DAY, GOOD FRIDAY, MEMORIAL DAY, JULY 4TH, LABOR DAY, THANKSGIVING DAY, THE FRIDAY AFTER THANKSGIVING DAY, CHRISTMAS EVE DAY AND CHRISTMAS DAY). ANY TECO PEOPLES GAS ASSISTANCE REQUESTED FROM THE FDOT, THEIR CONTRACTOR OR SUBCONTRACTOR OUTSIDE OF THESE NORMAL WORKING HOURS MUST BE SCHEDULED 48 HOURS IN ADVANCE. TECO PEOPLES GAS REQUIRES VERIFICATION THAT THE CREWS ARE STILL NEEDED ON THE ACTUAL WORKDAY (MONDAY THROUGH FRIDAY) THAT HAD PREVIOUSLY BEEN REQUESTED OR THE LAST BUSINESS DAY BEFORE THE REQUESTED

WEEKEND OR HOLIDAY.

Page 3 of 3 PINELLAS COUNTY 11/19//2019

Utility Facility (Type, Size, Material, Status)

From Station/ Offset

To Station/ Offset

Utility Work Description Dependent Activity TCP Phase

Consecutive Days

Prior To During

1 2” PE GAS MAIN 155+16.33

49.47’ LT

155+44.82

49.47’ LT

CUT & CAP, REMOVE ALL FACILITIES WHERE ACCESIBLE THAT

ARE IN CONFLICT WITH THE PROPOSED SIGNAL WHILE

COUNTY CONTRACTOR HAVE THE UTILITIES EXPOSED

PED. SIGNAL INSTALLATION TP-5 2

Page 1 of 3 PINELLAS COUNTY 10/15//2019

COUNTY PROJECT #: 004183P PROJECT TITLE #: Park Blvd. & Johnson Blvd

UTILITY AGENCY/OWNER (UAO): Knology Broadband of Florida D.B.A. WOW! (Wide Open West)

A. Summary of Utility Work and Execution

NON-CONSTRUCTION ITEMS ESTIMATED *CALENDAR

DAYS

CONSTRUCTION ITEMS ESTIMATED *CALENDAR

DAYS

Total Preliminary 14 Prior to Pinellas County Project Construction 5 Total Material Procurement 14 During Pinellas County Project Construction 4 Total Right-of-Way Permitting 0 Total NON-Construction Time 14 * Calendar Days = UAO Workdays x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule

This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Pinellas County, the roadway contractor and other right-of-way users, the location, relocation, adjustment, installation and/or protection of their facilities on this Pinellas County project. The following data is based on Pinellas County final design phase construction plans dated 1/2022. Any deviation by Pinellas County or its contractor from the plans, as provided, may require assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond their control and that could not be reasonably anticipated and avoided with the exercise of due diligence. The UAO agrees to notify Pinellas County in writing prior to starting, stopping, resuming or completing work.

UAO Project Representative: Dave Hamlin Telephone Number: 678-409-8721 UAO Field Representative: Dave Hamlin Telephone Number: 678-409-8721

No changes to forms document.

Appendix “Changes to Forms Document” is attached. Number of Attachment Pages.

Authorized Utility Agent: Engineer of Record: Acceptance by Pinellas County:

(Signature) (Signature) (Signature)

Dave Hamlin Tim Messina (Printed Name) (Printed Name) (Printed Name)

Construction Coordinator Utility Coordinator (Title) (Title) (Title)

6/3/22 (Date) (Date) (Date)

(Signattture) uththhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhorororooooororororoooooooorooooroo iziziziiziiiziiziziiiziziziiiiiiiiiiiiziiiiiiiiiiiiiiiiiiiiiiiiiziiiiiiii edeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeee Utiliiiiitytytytytytytyttttttttttttttttyttttyttyttttytytytytytytttytyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy Agegggggggggggggggggggggggggggggggggggggggggggggggggggggggggggggggggggggggggggggggggggggggggggg Joshua Reichert Digitally signed by Joshua Reichert

Date: 2022.07.15 09:26:42 -04'00' Scott Baird Digitally signed by Scott Baird Date: 2022.07.21 14:21:35 -04'00'

Page 2 of 3 PINELLAS COUNTY 10/15//2019

COUNTY PROJECT #: 004183P PROJECT TITLE #: Park Blvd. & Johnson Blvd

UTILITY AGENCY/OWNER (UAO): Knology Broadband of Florida D.B.A. WOW! (Wide Open West)

1: WOW! field inspector Dave Hamlin will be field point of contact for WOW! during construction duration of the project.

2: WOW! Working Days are during normal business hours, Monday – Friday, 7:30 am – 5:00 pm (excluding Holidays). WOW! will arrange any works after hour with an advance notice through WOW! field representative Dave Hamlin. Please call 48 hours prior to schedule any after hours work if needed. After hours emergency contact please call Richard LaGanga @ 727-422-8040 UAO project representative.

3: WOW! is to have access throughout the duration of the project to monitor and maintain WOW! facilities for the ability to provide service.

4: Any changes to Duke Energy RGB & UWS design plans submitted to Pinellas County will require reviewing by WOW!

5: WOW! requests coordination with road contractor to arrange for WOW! to adjust aerial span (raise/lower) for the mast arm installation during construction. Seven day notice prior to the Mast Arm #1 installation would be preferred so WOW! can arrange for it’s contractor to be onsite and make the nessary adjustments.

6: WOW! requests Pinellas County to notifiy WOW! of project letting date and anticipated project start date.

7: WOW! requests in person meeting with road contractor prior to the start of construction to go over any concerns.

Page 3 of 3 PINELLAS COUNTY 10/15//2019

COUNTY PROJECT #: 004183P PROJECT TITLE #: Park Blvd. & Johnson Blvd

UTILITY AGENCY/OWNER (UAO): Knology Broadband of Florida D.B.A. WOW! (Wide Open West)

Action # Utility Facility (Type, Size, Material, Status)

From Station/ Offset

To Station/ Offset Utility Work Description Dependent Activity TCP

Phase

Consecutive Days

Prior To During

1 WOW! OTV 155+38,

54’LT

155+38, 54’LT ADJUST TO NEW POLE DUKE ENERGY POLE

PLACEMENT

PRIOR

TO

CONST

2 0

2 WOW! OTV 156+54,

55’LT

156+54, 55’LT ADJUST TO NEW POLE DUKE ENERGY POLE

PLACEMENT

PRIOR

TO

CONST

2 0

3 WOW! OTV 155+44,

55’LT

155+44, 55’LT TO BE REMOVED DUKE PROPOSED POLES

INSTALLED.

PRIOR

TO

CONST

1 0

4 WOW! OTV 155+38,

54’LT

158+20, 51’LT TO BE ADJUSTED RAISE/LOWER MAST ARM #1 INSTALLATION DURING

CONST. 0 4

TOTAL: TOTAL:

5 4

004183P UWS 1
004183P UWS 2
004183P UWS 3
004183P UWS 4
004183P UWS 5