Appendix_5_-_004183D_UWS_Package.pdf

PDF 775 KB Posted

Attached to
Countywide Mast Arms - Group 3 (PID 004183A)
Solicitation number
23-1147-ITB-C
Issued by
Pinellas County, Florida

About this file

This document is a Utility Work Schedule (UWS) for Pinellas County's Countywide Mast Arm Signal Hardening and Intersection Improvement project at the intersection of E Tarpon Ave and US 19, involving multiple utility agencies including Duke Distribution, Frontier, and WOW! (Wide Open West). The project is part of a larger infrastructure improvement initiative that includes replacing existing signalization with mast arms at seven intersections, with minor roadway improvements and ADA guideline compliance. The utility work schedules indicate zero estimated calendar days for non-construction and construction items, suggesting the utilities will maintain existing facilities in place during the project duration.

The project is federally funded through the Federal Emergency Management Administration (FEMA) and administered by Pinellas County. Each utility agency has provided detailed contact information and special conditions, with WOW! noting their working days are during normal business hours (Monday-Friday, 7:30 am - 5:00 pm) and that they do not anticipate any prior to or during construction work at this time. Duke Distribution has overhead and underground 12.47kV distribution facilities along the right-of-way that will remain in service throughout the project. The utility work schedules serve as a coordination mechanism to ensure utility facilities are protected and service continuity is maintained during the county's infrastructure improvements.

View the file

Other files

File Type Posted
Pricing_Proposal23-1147(reference_only)a.pdf PDF
Countywide_Mast_Arms_-_Group_3_(PID_004183A)_(Addendum_#3_Revision).pdf PDF
QUALIFICATION_SUBMITTAL_FORM.pdf PDF
APPENDIX_4_-SPECIAL_NOTICES_revised5.pdf PDF
Sample_Agreement-23-1147.pdf PDF
Appendix_6_-_004183M.Geotechnical_Report_54th_and_113th_REV_032822_SS.pdf PDF
Sample_Performance_and_Payment_Bonds.pdf PDF
Affdavit_of_Release_and_Guarantee_23-1147.pdf PDF
SBE_FORM.pdf PDF
Final_Plans_-_004183M,_004183N,_004183O,_004183P.pdf PDF
Final_Plans_-_004183D,_004183E,_004183F.pdf PDF
APPENDIX_1-Permits.pdf PDF
Appendix_5_-_004183M_UWS_Package.pdf PDF
Florida_Trench_Safety_Form.pdf PDF
Specifications.pdf PDF
Affdavit_of_Release_and_Guarantee.pdf PDF
Appendix_5_-_004183N_UWS_Package.pdf PDF
Appendix_6_-_004183P.Geotechnical_Report_Park_Blvd_at_Johnson_Blvd_SS.pdf PDF
Appendix_6_-_004183_Geotechnical_Engineering_Services_Report.pdf PDF
Sample_Application_for_Payment.pdf PDF
Airport_Security_Program.pdf PDF
Appendix_5_-_004183O_UWS_Package.pdf PDF
Appendix_5_-_004183P_UWS_Package.pdf PDF
Appendix_6_-_004183N.Geotechnical_Report_Park_Blvd_and_Ridge_Rd_SS.pdf PDF
Appendix_6_-_004183O.Geotechnical_Report_Park_Blvd_and_Seminole_Blvd_SS.pdf PDF
E-Verify_Affidavit.pdf PDF
OpenGov_Fillable-_Final.pdf PDF
Appendix_5_-_004183E_UWS_Package.pdf PDF
Appendix_5_-_004183F_UWS_Package.pdf PDF
Bid_Submittal_Form-JOC.pdf PDF
Sample_Change_Order.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Page 1 of 3 PINELLAS COUNTY 07/20//2022

UTILITY WORK SCHEDULE

COUNTY PROJECT #: 004183D

PROJECT TITLE: COUNTRYWIDE MAST ARM SIGNAL HARDENING AND

INTERSECTION IMPROVEMENT - Intersection of E Tarpon Ave at US 19

UTILITY AGENCY/OWNER (UAO): DUKE DISTRIBUTION

A. Summary of Utility Work and Execution

NON-CONSTRUCTION ITEMS

ESTIMATED *CALENDAR

DAYS

CONSTRUCTION ITEMS

Total Preliminary 0 Prior to Pinellas County Project Construction 0

Total Material Procurement 0 During Pinellas County Project Construction 0

Total Right-of-Way Permitting 0

Total NON-Construction Time 0 * Calendar Days = UAO Work Days x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule

This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Pinellas County, the roadway contractor and other right-of-way users, the location, relocation, adjustment, installation and/or protection of their facilities on this Pinellas County project.

The following data is based on Pinellas County final design phase construction plans dated 12/2021 . Any deviation by Pinellas County or its contractor from the plans, as provided, may require assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond their control and that could not be reasonably anticipated and avoided with the exercise of due diligence. The UAO agrees to notify Pinellas County in writing prior to starting, stopping, resuming or completing work.

UAO Project Representative: Bill Ruland Telephone Number: 727-820-4641

UAO Field Representative: Bill Ruland Telephone Number: 727-820-4641

No changes to forms document.

Appendix “Changes to Forms Document” is attached. Number of Attachment Pages.

Authorized Utility Agent: Engineer of Record: Acceptance by Pinellas County:

(Signature) (Signature) (Signature)

William Ruland

(Printed Name) (Printed Name) (Printed Name)

Senior Engineering Technologist

(Title) (Title) (Title)

7/26/2022

(Date) (Date) (Date)

Benjamin Rodgers

Traffic Engineer

8/12/2022

Page 2 of 3 PINELLAS COUNTY 07/20//2022

COUNTY PROJECT #: 004183D

PROJECT TITLE: COUNTRYWIDE MAST ARM SIGNAL HARDENING AND

B. Special Conditions / Constraints

• This is based on plans provided by the County dated 12/2021

• Any “Found Conflicts” during construction, or any modification to the plans provided by the County, will be addressed per the 2017 UAM section 5 and the 337.4 State Statute.

Page 3 of 3 PINELLAS COUNTY 07/20//2022

COUNTY PROJECT #: 004183D

PROJECT TITLE: COUNTRYWIDE MAST ARM SIGNAL HARDENING AND

SECTION C: UAO’s WORK ACTIVITIES

Action

Utility Facility

(Type, Size, Material, Status)

From

Station/

Offset

To

Station/

Offset

Utility Work Description Dependent Activity

TCP

Phase

Consecutive

Days

Prior

To During

Overhead and underground

12.47kv distribution facilities along and across the right-of-way at various locations from begin to end project limits.

To remain in place and in service Duration of project construction N/A 0 0

Page 1 of 3 PINELLAS COUNTY 07/20//2022

COUNTY PROJECT #: PROJECT TITLE: 004183D - Countywide Mast Arm Hardening U.S. 19 at Tarpon Avenue

UTILITY AGENCY/OWNER (UAO):

A. Summary of Utility Work and Execution

NON-CONSTRUCTION ITEMS

CONSTRUCTION ITEMS

Total Preliminary 0 Prior to Pinellas County Project Construction 0

Total Material Procurement 0 During Pinellas County Project Construction 0

Total Right-of-Way Permitting 0

Total NON-Construction Time 0 * Calendar Days = UAO Work Days x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule

This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Pinellas County, the roadway contractor and other right-of-way users, the location, relocation, adjustment, installation and/or protection of their facilities on this Pinellas County project.

The following data is based on Pinellas County final design phase construction plans dated . Any deviation by Pinellas County or its contractor from the plans, as provided, may require assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond their control and that could not be reasonably anticipated and avoided with the exercise of due diligence. The UAO agrees to notify Pinellas County in writing prior to starting, stopping, resuming or completing work.

UAO Project Representative: Kyle Perkins Telephone Number: 727-313-6167

UAO Field Representative: Seve Theodosis (Vince) Telephone Number: 727-9428326

No changes to forms document.

Appendix “Changes to Forms Document” is attached. Number of Attachment Pages.

Authorized Utility Agent: Engineer of Record: Acceptance by Pinellas County:

(Signature) (Signature) (Signature)

Kyle Perkins

(Printed Name) (Printed Name) (Printed Name)

Engineer

(Title) (Title) (Title)

8-8-2022

(Date) (Date) (Date)

Frontier

004183D

Traffic Engineer

Benjamin Rodgers

8/12/2022

Page 2 of 3 PINELLAS COUNTY 07/20//2022

Page 3 of 3 PINELLAS COUNTY 07/20//2022

Utility Facility

(Type, Size, Material, Status)

From

Station/

Offset

To

Station/

Offset

Utility Work Description Dependent Activity

TCP

Phase

Consecutive

Days

Prior

To During

Page 2 of 3 PINELLAS COUNTY 10/15//2019

COUNTY PROJECT #: 004183D PROJECT TITLE #: US 19 / E TARPON AVE

UTILITY AGENCY/OWNER (UAO): Knology Broadband of Florida D.B.A. WOW! (Wide Open West)

1: WOW! field inspector Dave Hamlin will be field point of contact for WOW! during construction duration of the project.

2: WOW! Working Days are during normal business hours, Monday – Friday, 7:30 am – 5:00 pm (excluding Holidays). WOW! will arrange any works after hour with an advance notice through WOW! field representative Dave Hamlin. Please call 48 hours prior to schedule any after hours work if needed. After hours emergency contact please call Richard LaGanga @ 727-422-8040 UAO project representative.

3: WOW! is to have access throughout the duration of the project to monitor and maintain WOW! facilities for the ability to provide service.

4: WOW! does not anticipate any prior to or during construction work at this time.

5: Where WOW is attached as joint user to Duke Energy poles, and the duct it leases with Frontier both have provided zero-day work schedules at the time of review and do not appear to have any conflicts.

Page 3 of 3 PINELLAS COUNTY 10/15//2019

COUNTY PROJECT #: 004183D PROJECT TITLE #: US 19 / E TARPON AVE

UTILITY AGENCY/OWNER (UAO): Knology Broadband of Florida D.B.A. WOW! (Wide Open West)

Utility Facility (Type, Size, Material, Status)

From Station/ Offset

To Station/ Offset

Utility Work Description Dependent Activity TCP Phase

Consecutive Days

Prior To During

004183D UWS Duke Distribution_Signed
004183D UWS Frontier_Signed
004183D UWS WOW_Signed
During Pinellas County Project Construction
Special Conditions / Constraints
2022-08-29T09:37:00-0400
Scott Baird

File details come from the government source that posted it. Updated .