This document is a Utility Work Schedule (UWS) for the Pinellas County project #004183O, involving signalization plans at Park Boulevard and Seminole Boulevard. The UWS includes work schedules and details for multiple utility agencies/owners: Crown Castle, Duke Energy Distribution, Frontier, Spectrum Sunshine State LLC, and TECO Peoples Gas. The document outlines each utility's planned activities, including installing new poles, adjusting aerial spans, relocating facilities, and protecting existing infrastructure in preparation for roadway improvements. The project involves signalization and intersection improvements, with each utility coordinating their work to support the county's construction timeline.
The utility work schedules detail specific constraints and requirements for each agency, such as normal business hours, emergency contact numbers, and coordination protocols. Most agencies require advance notice for work outside standard hours, with specific notification periods ranging from 48 to 72 hours. The project appears to be federally funded, potentially through FEMA, and involves improving intersections with new mast arms and associated infrastructure. Each utility's section includes estimated calendar days for preliminary work, material procurement, and construction activities, with careful consideration of simultaneous work activities and interdependencies between different utility operations.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Page 1 of 3 PINELLAS COUNTY 11/19//2019
UTILITY WORK SCHEDULE
COUNTY PROJECT #: 004183O PROJECT TITLE: Signalization Plans – Park Blvd and Seminole Blvd
UTILITY AGENCY/OWNER (UAO): Crown Castle
A. Summary of Utility Work and Execution
NON-CONSTRUCTION ITEMS ESTIMATED *CALENDAR
DAYS
CONSTRUCTION ITEMS ESTIMATED *CALENDAR
DAYS
Total Preliminary 5 Prior to Pinellas County Project Construction 0 Total Material Procurement 5 During Pinellas County Project Construction 10 Total Right-of-Way Permitting 30 Total NON-Construction Time 40 * Calendar Days = UAO Work Days x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule
This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Pinellas County, the roadway contractor and other right-of-way users, the location, relocation, adjustment, installation and/or protection of their facilities on this Pinellas County project.
The following data is based on Pinellas County final design phase construction plans dated 1/12/2022. Any deviation by Pinellas County or its contractor from the plans, as provided, may require assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond their control and that could not be reasonably anticipated and avoided with the exercise of due diligence. The UAO agrees to notify Pinellas County in writing prior to starting, stopping, resuming or completing work.
UAO Project Representative: Chris Perkins Telephone Number: 717-856-6486 UAO Field Representative: Marshall Hall Telephone Number: 863-698-0567
No changes to forms document.
Appendix “Changes to Forms Document” is attached. Number of Attachment Pages.
Authorized Utility Agent: Engineer of Record: Acceptance by Pinellas County:
(Signature) (Signature) (Signature)
Christopher Perkins Tim Messina (Printed Name) (Printed Name) (Printed Name)
Operations Manager Utility Coordinator (Title) (Title) (Title)
05/30/2022 (Date) (Date) (Date)
(Signature)
Authorized Utility Agent:
Joshua Reichert
Digitally signed by Joshua Reichert Date: 2022.07.14 22:41:03 -04'00'
Scott Baird
Digitally signed by Scott Baird Date:
2022.07.21 11:26:24 -04'00'
Page 2 of 3 PINELLAS COUNTY 11/19//2019
COUNTY PROJECT #: 004183O PROJECT TITLE: Signalization Plans – Park Blvd and Seminole Blvd
UTILITY AGENCY/OWNER (UAO): Crown Castle
B. Special Conditions / Constraints
1. Prior to construction or excavation around or near Crown Castle underground fiber optic facilities, call Sunshine State One Call of Florida dba Sunshine 811 at 1-800-432-4770 and Crown Castle Network Operations center at 866-553-4237.
2. Crown Castle requests a 5 day notice to be given prior to construction near Crown Castle assets. Please contact Chris Perkins 717-856-6486 Christopher.perkins@crowncastle.com
3. In case of emergency call Crown Castle Network Operations center at 866-553-4237.
Definitions:
Locating: The use of test holes by vacuum excavation or comparable non-destructive equipment at critical point along a subsurface utility facility’s path thus exposing the underground facility and allowing the precise measurements of the depth and horizontal position to be made.
Designating: Utilizing electromagnetic, magnetic, sonic, and other energy fields for determining the existence and approximate horizontal location of underground utility facilities. Underground facilities will be marked by stakes, flags, paint or other suitable materials in varying combinations dependent upon surface conditions using American Public Works Association Utility Location Coordination Council Color Codes.
Hold/Guard/Protect: Shall include, but not be limited to, permittee’s use of an onsite representative during active construction operations. During excavation operations, Representative may be required to physically expose underground facilities, provide any necessary support to the Facilities, and/or cover aerial facilities as deemed necessary to aid construction.
Page 3 of 3 PINELLAS COUNTY 11/19//2019
UTILITY AGENCY/OWNER (UAO): Crown Castle
SECTION C: UAO’s WORK ACTIVITIES
Action
Utility Facility (Type, Size, Material, Status)
From Station/ Offset
To Station/ Offset
Utility Work Description Dependent Activity TCP Phase
Consecutive Days
Prior To During
1 Stand and FOC 179+37 , 55 RT
179+37 , 55 RT Adjust and Attach to new Duke pole New Duke Pole Installation N/A 0 10
2 Strand and FOC 177+71 , 85 RT
177+71 , 85 RT Adjust and Attach to new Duke pole New Duke Pole Installation N/A 0 10
3 Strand and FOC 177+71 , 92 LT
177+71 , 92 LT Adjust and Attach to new Duke pole New Duke Pole Installation N/A 0 10
4 Strand and FOC 176+50 RT 179+50 RT Raise/ lower as needed during construction New Duke Pole Installation NA 0 5
Page 1 of 3 PINELLAS COUNTY 11/19//2019
UTILITY AGENCY/OWNER (UAO): Duke Energy Distribution
A. Summary of Utility Work and Execution
NON-CONSTRUCTION ITEMS
ESTIMATED *CALENDAR
DAYS
CONSTRUCTION ITEMS
ESTIMATED *CALENDAR
DAYS
Total Preliminary 10 Prior to Pinellas County Project Construction 18 Total Material Procurement 30 During Pinellas County Project Construction 26 Total Right-of-Way Permitting 30 Total NON-Construction Time 70 * Calendar Days = UAO Work Days x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule
This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Pinellas County, the roadway contractor and other right-of-way users, the location, relocation, adjustment, installation and/or protection of their facilities on this Pinellas County project.
The following data is based on Pinellas County final design phase construction plans dated 1/12/2022. Any deviation by Pinellas County or its contractor from the plans, as provided, may require assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond their control and that could not be reasonably anticipated and avoided with the exercise of due diligence. The UAO agrees to notify Pinellas County in writing prior to starting, stopping, resuming or completing work.
UAO Project Representative: Carter Williams Telephone Number: 727-348-8384 UAO Field Representative: Carter Williams Telephone Number: 727-348-8384
No changes to forms document.
Appendix “Changes to Forms Document” is attached. Number of Attachment Pages.
Authorized Utility Agent: Engineer of Record: Acceptance by Pinellas County:
(Signature) (Signature) (Signature)
Carter Williams
Joshua Reichert
Tim Messina
(Printed Name) (Printed Name) (Printed Name)
Engineer III
Engineer of Record
Utility Coordinator
(Title) (Title) (Title)
5/18/2022
7/14/2022
(Date) (Date) (Date)
Joshua Reichert Digitally signed by Joshua Reichert Date: 2022.07.14 22:50:03 -04'00'
Carter Williams Digitally signed by Carter Williams Date: 2022.07.25 09:32:32 -04'00' Scott Baird Digitally signed by Scott Baird
Date: 2022.07.26 08:54:58 -04'00'
Page 2 of 3 PINELLAS COUNTY 11/19//2019
1. Duke Energy and/or Duke Energy subcontractors normal work schedule is Monday through Friday from 7 a.m. to 5 p.m., excluding observed holiday's (New Year’s Day, Good Friday, Memorial Day, July 4th, Labor Day, Thanksgiving Day, the Friday after Thanksgiving, Christmas Eve Day, and Christmas Day).
2. Duke Energy line crew availability may be affected or limited due to our required response to emergency conditions. This limitation will be dependent upon the severity of the emergency.
3. Emergency number for nights, weekends and Duke Energy Florida holidays is (800) 228-8485.
4. Bucket truck access must be maintained to all of this UAO’s facilities including: poles, pull boxes, transformers, and switchgear locations throughout the duration of the project construction for maintenance and outage restoration.
5. All NESC and OSHA required clearances from energized conductors and equipment should be maintained. Covering of conductors will not be provided by this UAO as this does not decrease the required code clearances.
6. Upon completion of any or all of relocations, as described in this approved Utility Work Schedule, any additional relocation of newly installed system that is required due to deviation by the County or its roadway contractor from the plans as provided to this UAO will be done at the expense of the County or its roadway contractor.
Upon notification of such change, UAO will proceed with the design and construction of the additional relocation within the standard work schedule of this UAO
7. De-energization of primary voltage (example: 12.47kV) power lines require coordination with multiple internal groups. Notify this UAO via email at least 20 business days before any de-energization is required at each mast arm location. Due to the existing circuit loadings, distribution conductors may require de-energizing and grounding during non-peak hours (may require night work by County contractor if circuit loading during daytime is not feasible).
8. Temporary removal of streetlight wire or secondary voltage conductors (example: 120/240V) requires coordination with multiple internal groups. Notify this UAO via email at least 20 business days before any temporary removal of wire is required at each location.
9. Temporary removed services or de-energizing conductors will result in loss of power. This UAO is not responsible for generators needed during power outage.
10. Any bracing or holding of this UAO’s poles will require 20 business days advance written notice via email to this UAO.
11. All new electrical services requested by Pinellas County, or its contractor will be required to conform to “Requirements for Electric Service and Meter Installations” latest edition.
12. To establish a new service account the responsible party for the new service must call 866-372-4663.
13. A Contribution in Aid to Construction (CIAC) will be required for underground riser/pedestal installations and any additional required line construction work that does not meet the required revenue ratio as specified in this UAO’s approved rates and tariffs.
14. Duke Energy Distribution cannot remove old facilities until new facilities are energized and existing customers services have been relocated.
Page 3 of 3 PINELLAS COUNTY 11/19//2019
Utility Facility (Type, Size, Material, Status)
From Station/ Offset
To Station/ Offset
Utility Work Description Dependent Activity TCP Phase
Consecutive Days
Prior To During
1 Wood Pole 179+37 , 55 RT
179+37 , 55 RT Install new wood switch pole for future de-energization. Prior to drill shaft installation N/A 6 0
2 In-line Switches 177+82 , 53 RT
177+82 , 53 RT Install In-line switches for future de-energization. Prior to drill shaft installation N/A 6 0
3 In-line Switches 177+71 , 56 RT
177+ 71 , 56 RT Install In-line switches for future de-energization. Prior to drill shaft installation N/A 6 0
4 In-line Switches 177+82 , 53 RT
177+82 , 53 RT Open fuse to de-energize overhead line. De-energization requested via email N/A 0 2
5 In-line Switches 177+71 , 56 RT
177+ 71 , 56 RT Open fuse to de-energize overhead line. De-energization requested via email N/A 0 2
6 Overhead Wire 179+42 , 55 RT
179+42 , 55 RT Remove overhead streetlight wire. De-energization requested via email N/A 0 2
7 Wood Pole 177+71 , 85 RT
177+71 , 85 RT Install new wood pole SW turn lane is permanently closed N/A 0 10
8 Wood Pole 177+71 , 92 LT
177+71 , 92 LT Install new wood pole NW turn lane is permanently closed N/A 0 10
For
Scott Baird Digitally signed by Scott Baird Date: 2022.07.26 07:41:28 -04'00'
COUNTY PROJECT #: 004183O PROJECT TITLE: Park Blvd and Seminole Blvd
UTILITY AGENCY/OWNER (UAO): Spectrum Sunshine State LLC.
A. Summary of Utility Work and Execution
NON-CONSTRUCTION ITEMS ESTIMATED *CALENDAR
DAYS
CONSTRUCTION ITEMS ESTIMATED *CALENDAR
DAYS
Total Preliminary 10 Prior to Pinellas County Project Construction 14 Total Material Procurement 30 During Pinellas County Project Construction 20 Total Right-of-Way Permitting 0 Total NON-Construction Time 0 * Calendar Days = UAO Work Days x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule
This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Pinellas County, the roadway contractor and other right-of-way users, the location, relocation, adjustment, installation and/or protection of their facilities on this Pinellas County project.
The following data is based on Pinellas County final design phase construction plans dated 01/12/22 . Any deviation by Pinellas County or its contractor from the plans, as provided, may require assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond their control and that could not be reasonably anticipated and avoided with the exercise of due diligence. The UAO agrees to notify Pinellas County in writing prior to starting, stopping, resuming or completing work.
UAO Project Representative: Art Dubinas Telephone Number: 727-290-1509 UAO Field Representative: Art Dubinas Telephone Number: 727-290-1509
No changes to forms document.
Appendix “Changes to Forms Document” is attached. Number of Attachment Pages.
Authorized Utility Agent: Engineer of Record: Acceptance by Pinellas County:
(Signature) (Signature) (Signature)
Art Dubinas Tim Messina (Printed Name) (Printed Name) (Printed Name)
Construction Coordinator Utility Coordinator (Title) (Title) (Title)
07/21/2022 (Date) (Date) (Date)
Joshua Reichert Digitally signed by Joshua Reichert Date: 2022.08.01 09:00:27 -04'00' Scott Baird Digitally signed by Scott Baird
Date: 2022.08.10 13:15:03 -04'00'
Page 2 of 3 PINELLAS COUNTY 11/19//2019
COUNTY PROJECT #: 004183O PROJECT TITLE: Park Blvd and Seminole Blvd
UTILITY AGENCY/OWNER (UAO): Spectrum Sunshine State LLC.
1. Spectrum relocation activities will not commence until a signed UWS and approved permit are received.
2. Spectrums normal business hours are from 8am to 5pm, Monday through Friday (excluding Holidays).
3. Any work outside of normal business hours are to be scheduled a minimum of 72 hours in advance.
4. Spectrum is to have access throughout the duration of the project to monitor and maintain Spectrum facilities for the ability to provide service.
5. UAO Field Rep listed on page 1 will be point of contact for Spectrum during the entire duration of the construction project unless otherwise notified.
6. Extreme caution is to be used when excavating near or around Spectrum facilities.
7. Spectrums relocation work is contingent on securing an approved joint use agreement (JUA) with Duke-Energy to attach to their existing and proposed power-poles.
Page 3 of 3 PINELLAS COUNTY 11/19//2019
COUNTY PROJECT #: 004183O PROJECT TITLE: Park Blvd and Seminole Blvd
UTILITY AGENCY/OWNER (UAO): Spectrum Sunshine State LLC.
Utility Facility (Type, Size, Material, Status)
From Station/ Offset
To Station/ Offset
Utility Work Description Dependent Activity TCP Phase
Consecutive Days
Prior To During
1 New Duke pole 179+37 , 55 RT
179+37 , 55 RT Attaching Spectrum aerial span to new Duke pole Duke installing new pole N/A 14 0
2 New Duke pole 177+71 , 85 RT
177+71 , 85 RT Attaching Spectrum aerial span to new Duke pole Duke installing new pole N/A 0 10
3 New Duke pole 177+71 , 92 LT
177+71 , 92 LT Attaching Spectrum aerial span to new Duke pole Duke installing new pole N/A 0 10
4 Spectrum aerial span Throughout project location
Throughout project location
Raising aerial facilities throughout project location to accommodate clearances Duke installing new poles N/A 14 0
COUNTY PROJECT #: 004183AO PROJECT TITLE: CR 694 (PARK BLVD) AR US-19A (SEMINOLE BLVD)
UTILITY AGENCY/OWNER (UAO): TECO PEOPLES GAS
A. Summary of Utility Work and Execution
NON-CONSTRUCTION ITEMS ESTIMATED *CALENDAR
DAYS
CONSTRUCTION ITEMS ESTIMATED *CALENDAR
DAYS
Total Preliminary 0 Prior to Pinellas County Project Construction Total Material Procurement 0 During Pinellas County Project Construction Total Right-of-Way Permitting 0 Total NON-Construction Time 0 * Calendar Days = UAO Work Days x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule
This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Pinellas County, the roadway contractor and other right-of-way users, the location, relocation, adjustment, installation and/or protection of their facilities on this Pinellas County project.
The following data is based on Pinellas County final design phase construction plans dated 01/12/2022 . Any deviation by Pinellas County or its contractor from the plans, as provided, may require assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond their control and that could not be reasonably anticipated and avoided with the exercise of due diligence. The UAO agrees to notify Pinellas County in writing prior to starting, stopping, resuming or completing work.
UAO Project Representative: Bolivar A. Feliz Nunez Telephone Number: 813-275-3712 UAO Field Representative: Raymond Zwissler Telephone Number: 727-423-7124
No changes to forms document.
Appendix “Changes to Forms Document” is attached. 2 Number of Attachment Pages.
Authorized Utility Agent: Engineer of Record: Acceptance by Pinellas County:
(Signature) (Signature) (Signature)
Bolivar A. Feliz Nunez Scott Baird (Printed Name) (Printed Name) (Printed Name)
Gas Design Tech I Project Coordinator (Title) (Title) (Title)
09/22/22 (Date) (Date) (Date) uthorized UtUUUUUUUUUU ility Agent:
(S(S(S(S(S(S(S(S(S(S(Siggggggggggnananananananannananan tututututututututututureeeeeeeeeeee))))))))))))
Bolivar rrrrrrrrr A. FFeleeeeeeeeee iz Nunez
Joshua Reichert
Digitally signed by Joshua Reichert Date: 2022.09.22 12:55:53 -04'00'
Scott Baird Digitally signed by Scott Baird Date: 2022.09.22 13:00:06 -04'00'
Page 2 of 3 PINELLAS COUNTY 11/19//2019
COUNTY PROJECT #: 004183AO PROJECT TITLE: CR 694 (PARK BLVD) AR US-19A (SEMINOLE BLVD)
UTILITY AGENCY/OWNER (UAO): TECO PEOPLES GAS
1. TECO/PEOPLE GAS REQUEST A COPY OF THE CONTRACTOR’S APROVED CPM SCHEDULE WITHING 5 DAYS OF
APPROVAL.
2. THE TECO PEOPLES GAS 24-HOUR EMERGENCY NUMBER 1-877 TECO PGS (1-877-832- 6747).
3. TECO PEOPLES GAS CREW AVAILABILITY MAY BE AFFECTED OR LIMITED DUE TO OUR REQUIRED RESPONSE TO EMERGENCY CONDITIONS ELSEWHERE. THIS LIMITATION WILL BE DEPENDENT UPON THE SEVERITY AND LOCATION
OF THE EMERGENCY.
4. TECO PEOPLES GAS SUBCONTRACTORS NORMAL WORK SCHEDULE IS MONDAY THROUGH FRIDAY FROM 8 A.M. TO 5 P.M., EXCLUDING TECO PEOPLES GAS OBSERVED HOLIDAY'S (NEW YEARS DAY, GOOD FRIDAY, MEMORIAL DAY, JULY 4TH, LABOR DAY, THANKSGIVING DAY, THE FRIDAY AFTER THANKSGIVING DAY, CHRISTMAS EVE DAY AND CHRISTMAS DAY). ANY TECO PEOPLES GAS ASSISTANCE REQUESTED FROM THE FDOT, THEIR CONTRACTOR OR SUBCONTRACTOR OUTSIDE OF THESE NORMAL WORKING HOURS MUST BE SCHEDULED 48 HOURS IN ADVANCE. TECO PEOPLES GAS REQUIRES VERIFICATION THAT THE CREWS ARE STILL NEEDED ON THE ACTUAL WORKDAY (MONDAY THROUGH FRIDAY) THAT HAD PREVIOUSLY BEEN REQUESTED OR THE LAST BUSINESS DAY BEFORE THE REQUESTED
WEEKEND OR HOLIDAY.
Page 3 of 3 PINELLAS COUNTY 11/19//2019
COUNTY PROJECT #: 004183AO PROJECT TITLE: CR 694 (PARK BLVD) AR US-19A (SEMINOLE BLVD)
UTILITY AGENCY/OWNER (UAO): TECO PEOPLES GAS
Utility Facility (Type, Size, Material, Status)
From Station/ Offset
To Station/ Offset
Utility Work Description Dependent Activity TCP Phase
Consecutive Days
Prior To During
1 6” CS GM 177 178 PROTECT OR ADJUST GAS MAIN IF NEEDED DRAINAGE INSTALLATION PH-I 0 15