Apdx 6 - SOW PCN 99777.pdf
PDF 301 KB Posted
- Attached to
- KSC Electrical BPA Construction Services Federal contract opportunity
- Solicitation number
- 80KSC024R0005
About this file
This statement of work outlines electrical construction services required at Kennedy Space Center. The contractor will restore power to facility P6-1382 by installing new transformers and running buried feed to the building. Additionally, the contractor will remove an existing transformer and install a new higher-capacity transformer on pole 99-6. The work must be completed within 60 calendar days in accordance with safety and engineering standards specified. Daily coordination with the facility manager is required. Inspections will be conducted by the government. The related federal contract opportunity is a blanket purchase agreement for electrical construction services issued by NASA's Kennedy Space Center.
View the file
Other files for this federal contract opportunity
Show all 29
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
PCN PCN 99777 Restore power to P6-1382 and install 75KVA transformer to pole 99-6.
Reference: EWR 144340 EWR 174745
Date: 8/21/2023
SCOPE
Summary: The purpose of this project is to Restore power to P6-1382 and install 75KVA transformer to pole 99-6.
A. Restore Power to P6-1382
1. Remove existing 25 KVA transformer on pole 99-22.
2. Install new 240 V single phase 50 KVA transformer on pole 99-22.
3. Install new ECB or fused disconnect at pole 99-22 with appropriate riser and weather head.
4. Install buried feed from ECB or fused disconnect to building P6-1382. This will be direct buried in schedule 80 PVC conduit, approximately 250ft from disconnect to new panel at building P6- 1382.
5. Install new 200 Amp, stainless steel panel at facility P6-1382. Install new ground rod and connect new panel to existing facility power infrastructure. This panel will later be used to expand capacity of the park, adding new campsites.
B. Remove/Install new transformer on pole 99-6
1. Remove existing 25 KVA transformer
2. Replace line side jack connector
3. Install new 240 V single phase 75 KVA transformer
4. Adjust the setting on the main breaker in the panel on the load side of the transformer to
380A.
Clarification Notes: None
ENGINEERING
• Arc-Flash study to be submitted as a part of the closeout of this project.
• No special engineering required for this project. This is like-for-like replacement.
• This work maintains existing power sources (no upgrades needed) and repairs existing configurations.
• Field verify with local Facility Manager and COR the applicable power panels and circuits prior to commencement of field work and LOTO.
IMPLEMENTATION
• Work to be performed during standard hours of Operations, M-F 1st Shift. 7:30 AM to
3:30 PM
• Daily coordination required with Facility Manager.
SUBMITTALS
Preconstruction:
• Standard Lockout-Tagout scheduling/coordination.
• Contractor will submit adequate material list for PM/SME approval prior to project start.
• Provide Site Specific Safety & Health Plan for review and approval prior to commencement of services.
Closeout:
• As-built/redline drawings as required.
• Final punch list with all required signatures.
STANDARDS
• Work shall comply with standards provided in “Requirements for Low Voltage Electrical Work at KSC” located in base contract.
BADGING
• TAA (Temporary Area Access) is NOT required to access area. Daily coordination required with Facility Manager in case of hazardous operations at Pad-B. Work occurs outside of Pad-B perimeter fence in the parking lot.
• TAA is required to access VAB.
o VAB Perimeter access is required to access the light poles. All work outside of facility, but within perimeter fence.
INSPECTION
• Inspections shall be provided by the Government, in accordance with the Special Conditions of this contract. The Site Inspector may at any time review current work conditions and must approve of progress, milestones, daily logs, etc. The Contractor is to participate in the final acceptance walk down and complete any punch list items as required, to ensure a fully operational system.
PROJECT CLOSEOUT
• To be conducted per the Project closeout section of the base contract.
PROPOSAL/BID DEVELOPMENT
• To be submitted per the Bid Submission Guidelines found in Section _TBD (We need to update this before we send out with the base once I have the numbering done)___ of the base contract.
PERIOD OF PERFORMANCE: 60 calendar days from award date. Please submit schedule for long lead time items.
Attachment 01: Pictures, Drawings, and Sketches
File details come from the government source that posted it. Updated .