This document contains an amendment to a solicitation for multiple award electrical construction services blanket purchase agreements. The National Aeronautics and Space Administration Kennedy Space Center will award up to ten BPAs for responding to unforeseen electrical tasks at various government properties, establishing agreements for unknown work for minor electrical construction and facility maintenance for up to five years. The amendment provides answers to contractor questions on topics such as clarifying stainless steel requirements, panel types, and breaker settings for specific projects, as well as confirming electronic submission of proposals is required and no sealed bids are needed.

View the file

Other files for this federal contract opportunity

Other files attached to KSC Electrical BPA Construction Services, newest first.
File Type Posted
80KSC024R0005 Amnd 06.pdf PDF
Apd 6 - SOW PCN 99777 - v4.pdf PDF
Apdx 6 - SOW PCN 99777 - v3.pdf PDF
80KSC024R0005 Amnd 05.pdf PDF
80KSC024R0005 Amnd 03.pdf PDF
Apdx 5 - SOW PCN 99776 - v2 Redlined.pdf PDF
Apdx 6 - PCN 99777 - v2 Clean.pdf PDF
Amnd 02 80KSC024R0005.pdf PDF
Apdx 5 - SOW PCN 99776 - v2 Clean.pdf PDF
Apdx 6 - SOW PCN 99777 - v2 Redlined.pdf PDF
Amnd 01 80KSC024R0005.pdf PDF
Attch J-6 Control Log.pdf PDF
Attch J-7 KSC and CCAFS Map.pdf PDF
Apdx 9 - Site Visit Locations.pdf PDF
Attch J-1 Project Deliverables.pdf PDF
Attch J-2 KSC Project Specific Requirements.pdf PDF
Attch J-4 SSSP Template.docx DOCX document
Attch J-8 ASB Badge Request Form.docx DOCX document
Apdx 6 - SOW PCN 99777.pdf PDF
Apdx 1 - Site Visit Badge Request Form.docx DOCX document
Apdx 2 - Acceptable Identity Guide.docx DOCX document
Apdx 4 - Pre-Proposal Inquiry Form PCN 99777.xlsx XLSX spreadsheet
Apdx 7 - Technical Experience Summary.pdf PDF
Apdx 8 - Past Performance Questionnaire.pdf PDF
Solicitation 80KSC024R0005 eBPA.pdf PDF
Attch J-5 Lockout -Tagout.pdf PDF
Apdx 5 - SOW PCN 99776.pdf PDF
Attch J-3 Wage Determination10-20- 2023.pdf PDF
Apdx 3 - Pre-Proposal Inquiry Form PCN 99776.xlsx XLSX spreadsheet
Show all 29

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

OP-CS

Randall A. Gumke Lead Contracting Officer

The purpose of Amendment 0004 to the eBPA Solcitation is:

1. Incorporate "Answers to Contractors Questions 03" dated 01/10/2024, attached hereto.

2. Proposal due date remains unchanged and is 1/24/2024 at 2:00 PM EST.

OP-CS

JOHN F. KENNEDY SPACE CENTER, NASA

PROCUREMENT OFFICE CODE: OP-CS

KENNEDY SPACE CENTER, FL 32899

JOHN F. KENNEDY SPACE CENTER, NASA

JOHN F. KENNEDY SPACE CENTER, NASA

PROCUREMENT OFFICE CODE: OP-CS

KENNEDY SPACE CENTER, FL 32899

JOHN F. KENNEDY SPACE CENTER, NASA

TBD

N/A

80KSC024R0005

N/A

01/10/2024

11/30/2023

RANDALL GUMKE Digitally signed by RANDALL GUMKE Date: 2024.01.10 08:30:23 -05'00'

1/10/2024

Answers to Contractor Questions 03 01/10/2024

No. Reference (Section Paragraph/Page) Questions Responses

PCN 99777 Period of Performance Due to the long lead time of the pole mount transformers and the 200 amp stainless steel panel, a 60 day POP is not sufficient.

Please advise.

PoP for PCN 99777 will be extended to 180 days to account for stainless steel and transformer lead time hardware. Updated SOW will be provided in the next amendment.

PCN 99777 Scope of Work Section A.2.b. and A.2.d. Please clarify if the ECB or fused disconnect shall be stainless steel. Also, please clarify the stainless steel requirement for the 200 amp panel. Should these be 304 or 316 stainless steel?

Fused Disconnect and 200 amp panel shall be 316 Stainless Steel.

PCN 99777 Scope of Work Section A.2.d. Please clarify if the 200 amp panel is MCB or MLO. Please clarify if any branch circuit breakers are to be included for the future campsites. Also, is TVSS required? If so shall it be integral or external? None of this information is indicated in the

SOW.

200 amp panel is MCB.

TVSS is required, and external is acceptable. For the 200A panel, branch circuits should include:

Liftstation, Bathroom, and Spares: (4) 50A 2Pole &

(2) 20A 1Pole

PCN 99777 Scope of Work Section B.4. According to the manufacturer, the existing 400 amp ABB breaker is adjustable but only has three settings. They are 280- 340-400. If 380 amp is required, the breaker will need to be replaced with LSI. Please advise.

The 400 amp ABB breaker should be set to 340A, or medium setting.

Solicitation On page 36 of the solicitation PDF, it states that the offeror is required to submit a Technical Capability Volume.pdf and Price Volume.xlsx. Are there any additional Excel spreadsheets for pricing or price breakdowns that need to be included in the submitted documents, apart from the price sheet on page 3 of the solicitation?

No additional spreadsheets are required. Section 9.2 addressess what should be submitted.

Solicitation On page 36, it is mentioned that the offeror should submit all proposal files to the EFFS Box. Do we also need to send a sealed solicitation to you, or is electronic submission the only requirement?

No sealed soliciation is requred. Only electronic submissions.

PCN 99776 SOW; Remove existing light pole concrete base (total of 3) and perform basic grading to match existing area

Do the (3) concrete bases need to be fully removed or can it be cut to ground level?

At minimum, cut concrete base just below ground level to match existing pitch and complete local/surrounding grading. Ensure remaining base is not a protuding above ground or creating hazard.

Solicitation I cannot find the bid bond amount in the solicitation. Could you please provide me with the percentage of the bid bond and the amount of the liquidated damages?

The bid guarantee must be 20% of the bid price or $3M, whichever is less.

There are no liguidated damages for these two initial projects.

80KSC024R0005 Amend 004 Printed
Answers to Contractor Questions 03
Sheet1