This statement of work outlines a project to replace broken light poles and lights at a parking lot. Three existing concrete light pole bases will be removed and replaced with new 25-foot concrete light poles with LED quad lights that are sea turtle and wildlife safe. The contractor will install the new poles, lights, and all associated mounting hardware. They will also trace and secure existing wiring and install new handholes and grounding connections. The work must be performed during standard daytime hours on weekdays with daily coordination with the facility manager. The period of performance is 120 calendar days from award. The related federal contract opportunity is a multiple award blanket purchase agreement for unforeseen electrical construction and maintenance services with a potential term of five years to be performed at Kennedy Space Center, Merritt Island Wildlife Refuge, and Cape Canaveral Space Force Station for the National Aeronautics and Space Administration.

View the file

Other files for this federal contract opportunity

Other files attached to KSC Electrical BPA Construction Services, newest first.
File Type Posted
80KSC024R0005 Amnd 06.pdf PDF
Apd 6 - SOW PCN 99777 - v4.pdf PDF
Apdx 6 - SOW PCN 99777 - v3.pdf PDF
80KSC024R0005 Amnd 05.pdf PDF
80KSC024R0005 Amend 004.pdf PDF
80KSC024R0005 Amnd 03.pdf PDF
Apdx 5 - SOW PCN 99776 - v2 Redlined.pdf PDF
Apdx 6 - PCN 99777 - v2 Clean.pdf PDF
Amnd 02 80KSC024R0005.pdf PDF
Apdx 6 - SOW PCN 99777 - v2 Redlined.pdf PDF
Amnd 01 80KSC024R0005.pdf PDF
Apdx 1 - Site Visit Badge Request Form.docx DOCX document
Apdx 2 - Acceptable Identity Guide.docx DOCX document
Apdx 4 - Pre-Proposal Inquiry Form PCN 99777.xlsx XLSX spreadsheet
Apdx 7 - Technical Experience Summary.pdf PDF
Apdx 8 - Past Performance Questionnaire.pdf PDF
Attch J-6 Control Log.pdf PDF
Attch J-7 KSC and CCAFS Map.pdf PDF
Apdx 9 - Site Visit Locations.pdf PDF
Attch J-1 Project Deliverables.pdf PDF
Attch J-2 KSC Project Specific Requirements.pdf PDF
Attch J-4 SSSP Template.docx DOCX document
Attch J-8 ASB Badge Request Form.docx DOCX document
Apdx 6 - SOW PCN 99777.pdf PDF
Solicitation 80KSC024R0005 eBPA.pdf PDF
Attch J-5 Lockout -Tagout.pdf PDF
Apdx 5 - SOW PCN 99776.pdf PDF
Attch J-3 Wage Determination10-20- 2023.pdf PDF
Apdx 3 - Pre-Proposal Inquiry Form PCN 99776.xlsx XLSX spreadsheet
Show all 29

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

PCN99776: Replace Broken Lights and Poles VAB West Parking Lot (K6-0848)

Reference: EWR163381

Date: 12/19/2023

SCOPE

Summary: This project will replace broken utility light poles and LED lights at VAB West Parking Lot (K6- 0848). The poles were previously broken from 2022 Hurricane Ian.

VAB West Parking Lot (K6-0848):

The above strikethrough scope has been re-written based on the site review and discussion with Stakeholders. For simplistic clarity, new scope for the original outlined (3) poles is re-addressed below in red font.

• Install (3) new concrete light poles 25’ in length above grade. Utilize the provided pole specification or select an approved equivalent.

o D525XL-SG-EA-3T; Direct Burial 500 Series Concrete Pole or equivalent.

o 25' Above Ground, (minimum) 7' Burial o Neutral Gray or Tan Color o Etched Finish with Acrylic Sealer o Tenon that is compatible with fixture support hardware.

o Hurricane Rated o Light Pole #s: LGHT01751; LGHT01752; LGHT01753

• Contractor shall provide and install new quad style LED lights that are sea-turtle/wildlife safe amber spectrum. Utilize the provided light specification or select an approved equivalent.

o DSX Lithonia LED Fixture or equivalent.

o Sea coast environment resistant paint finish.

o 480V Rated Power Feed o Quad Style = 4 LED fixtures per light pole (total of 12 lights for 3 poles), 4 @ 90 o Photocell not required, existing circuit functions on a timer.

o Dimming option is acceptable, but not required.

o BAA Compliant o 125-150W fixture (each) o Photometric analysis of area not required. This is general lighting of area. Non-emergency or not security egress dependent.

o Contractor to provide and install all mounting hardware.

• Remove existing light pole concrete base (total of 3) and perform basic grading to match existing area. Area is mainly gravel/dirt/crushed rock base.

o Ensure existing power wiring is traced and safe prior to demo of base.

o Discuss drilling plan for placement of new light poles with COR, Facility Manager, and

Environmental Point of Contact (EPOC).

• KSC to provide utility locate service for tracing existing conductors from existing concrete pole base to new hand-hole and pole placement.

• Each pole shall have minimum one new hand-hole that intersects existing conductor feeds, utilizing waterproof/underground bonding connections and proper grounding.

o Additional hand-holes may be required pending on placement of the light pole.

• Contractor can use minor discretion to determine exact field location of new pole.

o Each new light pole shall be within proximity of the existing concrete bases.

• No bollards required.

• Mandatory Inspection Point: Pole auger depth and installation per manufacturer specification, by Construction Inspector.

• Lights will utilize existing circuit(s) and will require planned outage and circuit LOTO. Power outage scheduled through Construction Inspector. Verify zero energy prior to working.

ENGINEERING

• No special engineering required for this project. This is like-for-like replacement.

• This work maintains existing power sources (no upgrades needed) and repairs existing configurations.

• Field verify with local Facility Manager and COR the applicable power panels and circuits prior to commencement of field work and LOTO.

IMPLEMENTATION

• Work to be performed during standard hours of Operations, M-F 1st Shift.

• Daily coordination required with Facility Manager.

SUBMITTALS

Preconstruction:

• Standard Lockout-Tagout scheduling/coordination.

• Contractor will submit adequate material list for PM/SME approval prior to project start.

• Provide Site Specific Safety & Health Plan for review and approval prior to commencement of services.

Closeout:

• As-built/redline drawings as required.

• Final punch list with all required signatures.

STANDARDS

• Work shall comply with standards provided in “Requirements for Low Voltage Electrical Work at KSC” located in base contract.

BADGING

• TAA is required to access VAB.

o VAB Perimeter access is required to access the light poles. All work outside of facility, but within perimeter fence.

INSPECTION

• Inspections shall be provided by the Government, in accordance with the Special Conditions of this contract. The Site Inspector may at any time review current work conditions and must approve of progress, milestones, daily logs, etc. The Contractor is to participate in the final acceptance walk down and complete any punch list items as required, to ensure a fully operational system.

PROJECT CLOSEOUT

• To be conducted per the Project closeout section of the base contract

PERIOD OF PERFORMANCE: 120 calendar days from award date (includes time for lead-time hardware).

Attachment 01: Pictures, Drawings, and Sketches

VAB Exterior Lighting NW Side, Near High Bay 2&4 Roll Up Doors:

Light Pole 1753 – North of HB-4 Door

Light Pole 1752 & Light Pole 1751 – Between HB-2 & HB-4 doors.

Note: Long pole is eastern pedestal LGHT01751, short pole is western pedestal LGHT01752.