Annex K Heating and Cooling Services - 18 May 22.pdf

PDF 128 KB Posted

Attached to
Base Operations Support Services, Ft. Wainwright, AK
Solicitation number
W912CN22R0013
Issued by

About this file

This performance work statement and related solicitation provide details on base operations support services requirements at Fort Wainwright, Alaska. The performance work statement outlines the scope of heating and cooling services to be provided, including operating mechanical rooms and systems for steam, hot water, and chilled water production. It also covers inspection and maintenance requirements for boilers, furnaces, and air handling units. The related solicitation is a 100% small business set-aside seeking proposals for an IDIQ contract to provide base operations support services at Fort Wainwright and its area of responsibility, which includes facilities maintenance, fire protection, solid waste management, grounds maintenance, and other services. The solicitation notes a closing date for proposals and states the requirement is assigned NAICS code 561210 with a small business size standard of $41.5 million. The Department of the Army is listed as the contracting agency.

View the file

Other files

File Type Posted
Attachment 04 - Exhibit Line Item Number Sheet 7-26-2022.xlsx XLSX spreadsheet
TE 53 - PMO - WORKLOAD_DATA 07252022 - Final.pdf PDF
Attachment 03 - Personnel Qualifications.pdf PDF
TE 93 Seasonal Heat Shut-Down.pdf PDF
TE 92-Wash Water Recycle System.pdf PDF
TE 06 - Staffing Matrix_5 July 2022.pdf PDF
Technical Exhibit Libary 25 July 2022.pdf PDF
Annex H Facility Maintenance - 18 July 2022.pdf PDF
W912CN-22-R-0013-0002.pdf PDF
Attachment 05 - Question Submission Form Responses - 7-26-22.XLSX XLSX spreadsheet
TE 94 Lightning Protection.pdf PDF
Attachment 09 - Wage Determination 2015-5687.pdf PDF
Appendix D - Performance Assessment Questionnaire.docx DOCX document
TE 52 - DMO - WORKLOAD_DATA 072522 - Final (1).pdf PDF
TE 95 Dryer Vent Cleaning.pdf PDF
W912CN-22-R-0013-0001.pdf PDF
TE 55 - Tip Sheets.pdf PDF
TE 50 - Ammunition Bunkers.pdf PDF
TE 14 - Dumpster Tips Workload.pdf PDF
TE 42 - Light Poles.pdf PDF
TE 87 - USAG Alaska Policy 14 Energy Conservation (10jan20).pdf PDF
TE 78 - Generator PM Schedule.pdf PDF
TE 66 - FWA DPW Environmental Requirements.pdf PDF
TE 08 - Interior and Exterior Lighting Systems and Controls.pdf PDF
TE 80 - Snow Removal Services Roads 19 May 2022.pdf PDF
Annex C - RESERVED.pdf PDF
TE 59 - FWA Road Inventory.pdf PDF
TE 12 - High Occupancy Critical Facilities List - 12 May 22.pdf PDF
TE 67 - Sidewalk Snow Removal List.pdf PDF
TE 36 - Lift Stations.pdf PDF
TE 19 - Cooling Systems.pdf PDF
W912CN-22-R-0013.pdf PDF
Annex F Maintenance-Grounds - 26 Apr 22.pdf PDF
TE 20 - Boilers and Furnances.pdf PDF
TE 77- Generator PM Log.pdf PDF
TE 09 - Storm Water System.pdf PDF
TE 40 - Historic Properties on Fort Wainwright.pdf PDF
Attachment 07 - CBA_FJCC_05.01.19.pdf PDF
Annex A-Overarching PWS - 10 June 22.pdf PDF
TE 21 - Heating Systems.pdf PDF
TE 06 - Staffing Matrix.xlsx XLSX spreadsheet
TE 58 - Fort Wainwright List of Possible DMOs 26 April 2022.pdf PDF
TE 49 - Crosswalks.pdf PDF
TE 01 - Lists of Facilities and Roads.pdf PDF
TE 28 - HVAC.pdf PDF
TE 07 - Roof Gutters Drains and Downspouts.pdf PDF
TE 54 - Fort Wainwright Preventive Maintenance Plan - 08 Apr 22.pdf PDF
TE 82 - Snow Removal Org Parking 26 APR 22.pdf PDF
TE 18 - Pest Control Facilities List - 16 Mar 22.pdf PDF
TE 13 - Scheduled Pest Control Services - 15 Mar 22.pdf PDF
Show 40 more

Latest 50 of 126 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Annex K (CLS 501 Heating/Cooling Services) FRAGO 1 to OPORD 18-011: IMCOM Enterprise Base Operations (BASOPS) Performance Work Statement (PWS) Templates (U)

Annex K

Heating/Services

18 May 2022

Table of Contents

1.0 GENERAL INFORMATION

1.1 Overview

1.2 Air Pollution Regulations

2.0 DESCRIPTION OF SERVICES

2.1 Scope

2.2 Heating and Boiler Plant Staffing

2.3 Operation of Mechanical rooms

2.3.1 Unattended Mechanical rooms

2.4 Central Boiler Plants

2.5 Summer Overhaul

2.6 Idle Standby Boilers

2.7 Monthly Inspections

2.8 Boiler/Heat Plant Shutdowns

2.9 Boiler Water Treatment Chemicals

2.10 Boiler Water Test Samples

2.11 Prepare Boilers and Coordinate Boiler Inspections

2.12 Boiler Plant Calibration

2.13 Emergencies

2.14 Operational Considerations

3.0 PURCHASE OF FUELS

3.1 Fuel Oil

3.2 Natural Gas Distribution System

3.3 Other Fuels

4.0 Air Handling Units and Ventilation Systems

4.1 Scope

4.2 Repair of Air Conditioning Systems

1.0 General Information.

1.1 Overview. Heating and Cooling Services provide steam, hot water, chilled water for heating, cooling, domestic hot water, and facility processes using Government-owned central heating and cooling plants, and distribution systems. The Fort Wainwright Heating Plant is operated through a privatized company and the contractor will have no responsibility for the heating plant.

1.2 Air Pollution Regulations. The Contractor shall operate all mechanical rooms in compliance with all Federal, State, and local air pollution regulations. The Contractor shall address all non-compliance issues immediately to the Contracting Officer’s Representative (COR) or Alternate Contracting Officer’s Representative (ACOR).

2.0 Description of Services.

2.1 Scope. The Contractor shall operate all mechanical rooms and systems (steam meters, automatic tank monitoring system, boilers, and furnaces) used in the production of domestic heat (including the provision of unscheduled services) as directed by the

COR/ACOR.

2.2 Heating and Boiler Plant Staffing. N/A

2.3 Operation of Mechanical rooms. The Contractor shall operate the steam/hot water mechanical rooms listed in TE 57. Operation of these plants includes start-up and shutdown of heating equipment; operator maintenance and inspection (maintenance required to operate mechanical rooms on a daily basis; e.g., during operational visits ensure the plant is operating properly). Operation also includes keeping required logs, correction of improper operating conditions, and making minor adjustments to the plant and equipment and keeping mechanical rooms clean.

2.3.1 Unattended Mechanical rooms. The Contractor shall operate all unattended mechanical rooms listed in TE 57. Operation of these plants shall include seasonal start-up and shut down of heating equipment.

2.4 Central Boiler Plants. N / A

2.5 Summer Overhaul. N / A

2.6 Idle Standby Boilers. N/A

2.7 Inspections. See TE 54.

2.8 Boiler/Furnaces/Water heaters. Boiler/Furnaces/Water heaters provide hot water and heat to the facilities. The contractor shall provide PM to this equipment IAW TE 54.

Corrective maintenance beyond minor corrective repairs conducted during PM will be conducted by DMOs.

2.9 Boiler Water Treatment Chemicals. N / A

2.10 Boiler Water Test Samples. N / A

2.11 Prepare Boilers and Coordinate Boiler Inspections. N/A

2.12 Boiler Plant Calibration. N/A

2.13 Emergencies. The Contractor shall inform the COR/ACOR within thirty (30) minutes of shutting down any boiler or furnace for repairs. The Contractor shall provide 72 hour advance notice of planned repairs that require the shutdown of any boiler or furnace. If permanent repairs cannot be completed within 24 hours, the Contractor shall analyze the occupancy, use of facility and provide temporary hot water, when needed and directed by the COR. Contractor shall provide the COR with daily updates on the status of water heater, furnace, or boiler failures until temporary hot water has been provided or the system is fully operational again.

2.14 Operational Considerations. N/A

3.0 Purchase of Fuels.

3.1 Fuel Oil. N/A

3.2 Natural Gas Distribution System. N/A

3.3 Other Fuels. N/A

4.0 Air Handling Units and Ventilation Systems. See Annex H Facility Maintenance, paragraph 2.3 and subparagraphs.

4.1 Scope.

4.2 Repair of Air Conditioning Systems. See Annex H Facility Maintenance, paragraph

2.3 and subparagraphs.

2.3.1 Unattended Mechanical rooms 1