scopeOfWorkNatick campground.doc
DOC document 32 KB Posted
- Attached to
- RECOVERY - BESSEY COMPLEX REC SITE IMPROVEMENTS - BESSEY RANGE DISTRICT - NEBRASKA NATIONAL FOREST
- Solicitation number
- AG-82B1-S-10-0244
About this file
Summary of Work - Natick Campground ITEM 3
View the file
Other files
Show 40 more
Latest 50 of 63 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 01010
SUMMARY of work
PART 1 - GENERAL
1.1 summary
A. Construct new campground road in Natick Campground. Work includes clearing, grubbing, and disposal; constructing the road prism; installing drainage features; seeding; and installing erosion control.
B. Optional Bid Item work if funds are available includes:
1. Installing surfacing on the new campground road.
2. Construction of campsite turnouts along the new road.
3. Installation of surfacing on the campsite turnouts.
4. Lengthening existing North Natick Road turnouts.
C. This project is part of a larger solicitation. The solicitation also includes the Bessey Complex Recreation Site Improvements project, the Bessey Pool Demolition and New Showerhouse project, and the Scott Tower Maintenance Project.
D. The Forest Service has protocols that it must follow for the ABB beetle (ABB). Before any ground disturbance can occur in an area it must be cleared of ABB. ABB clearance can only be done during two periods and the clearance status for an area lasts only until the beginning of the next clearance period. Starting dates for the two clearance periods are June 7 and August 7. Natick Campground does not currently have ABB clearance. As a result, Notice To Proceed for this project will not be issured until after the area is cleared during the June 7 clearance period. If the contract ground disturbance work is not completed by August 7, a stop work order will be issued to stop work and contract time until the area is once again cleared of ABB.
1.2 location
A. This project at the Forest Service Natick Campground. The campground is located one mile west on US Highway 2 from Halsey, NE; ½ mile south and 1 ½ mile west on State Spur 86B; 5 miles west and 2 miles south on North Natick Road #212.
1.3 USE OF PREMISES
spec writer: Delete this Article if Owner places strict limitations on Contractor's use of premises, and use Division 1 Section "Work Restrictions" instead. Expand Article if Owner's restrictions are minor. See the Evaluations in Division 1 Section "Work Restrictions.”
spec writer: Retain paragraph below if Project is on a vacant site or in an unoccupied building being renovated and there are no Owner-occupancy requirements. Revise to suit Project.
A. General: Contractor shall have full use of the new road corridor and the existing Natick Campgroun roads shown on the drawings to be closed for construction operations, during the construction period. Contractor shall sign these roads as closed during the construction period. Contractor's use of premises is limited only by the Government's right to perform work or to retain other contractors on portions of Project. Natick Campground will be closed during the construction period.
B. Confine storage of materials to areas as approved by the CO.
C. Contractor shall provide adequate signing and barricades and take necessary safety measures to protect the public during all construction operations. Contractor shall minimize disturbance of all undisturbed areas.
D. Preservation of Natural Features: Confines all operations to work limits of the project. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
1. Provide temporary barriers to protect existing trees and plants and root zones.
2. Do not remove, injure, or destroy trees or other plants outside of the clearing limits without prior approval.
3. Do not fasten ropes, cables, or guys to existing trees.
4. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
E. Existing Utilities: Notify CO and utility companies of proposed locations and times for excavation.
1. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
spec writer Insert additional paragraphs to specify minor restrictions on Contractor's use of premises or to specify minor limitations because of Owner occupancy.
1.4 camping
A. The Contractor may camp at the closed Natick Campground during the construction period at no charge. The Contractor will be responsible for his own garbage disposal.
1.5 construction sequence
A. There is no specified construction sequence or season for this project.
B. Depending on conditions, normal fire restrictions may apply to activities associated with this project.
1.6 Field verification
A. Field verify all new and existing dimensions affecting the work of this contract before ordering products.
1.7 permits
A. Special permits for electrical work or any other permits required by County, State, or Federal laws or regulations shall be obtained by the Contractor.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01100
01010 - 1
SUMMARY OF WORK
File details come from the government source that posted it. Updated .