EarthworkBessey Complex RSI.doc

DOC document 31 KB Posted

Attached to
RECOVERY - BESSEY COMPLEX REC SITE IMPROVEMENTS - BESSEY RANGE DISTRICT - NEBRASKA NATIONAL FOREST
Solicitation number
AG-82B1-S-10-0244
Issued by

About this file

EARTHWORK BESSEY COMPLEX RSI ITEM 1

View the file

Other files

File Type Posted
SF 30 AMEND 3.PDF PDF
Amend 3 Questions and Answers.pdf PDF
Seed and Mulch natick cg.doc DOC document
DefBidItemsScott Tower Maint.doc DOC document
Camping Spurs and Pads Bessey Complex RSI.doc DOC document
SummaryOfWorkBessey complex rsi.doc DOC document
CompositeRd Natick CG.doc DOC document
SteelScott Tower Maint.doc DOC document
Aggregate Natick CG.doc DOC document
Scope of Work Pool.doc DOC document
BidItems Pool.doc DOC document
Submittals Pool.doc DOC document
SF 30 AMEND 2.PDF PDF
submittalsScott Tower Maint.doc DOC document
Asphalt ShinglesScott Tower Maint.doc DOC document
bid items natick.doc DOC document
DefBidItemsBessey complex rsi.doc DOC document
ScopeOfWorkScott Tower Maint.doc DOC document
scopeOfWorkNatick campground.doc DOC document
DrawingsBessey Complex RSI.pdf PDF
Rough CarpentryScott Tower Maint.doc DOC document
PaintingScott Tower Maint.doc DOC document
Selective DemolitionScott Tower Maint.doc DOC document
defofbiditems natic cg.doc DOC document
HandrailsScott Tower Maint.doc DOC document
Submittals Natick CG.doc DOC document
AWellAbandonment Pool.doc DOC document
Drawings Scott Tower Maint.pdf PDF
Earthwork Pool.doc DOC document
GFMBessey Complex RSI.doc DOC document
PoolDrawings.pdf PDF
SubmittalsBessey complex rsi.doc DOC document
SF 30 AMEND 1.PDF PDF
PoolDrawings.pdf PDF
02822_02Sod.doc DOC document
01732Selective Demolition.doc DOC document
experience questionnaire.pdf PDF
01330_02Submittals.doc DOC document
submittal procedures.doc DOC document
02525_02AWellAbandonment.doc DOC document
02616_02Aggregate.doc DOC document
01550_02GFM.doc DOC document
AG-82B1-S-10-0244.pdf PDF
NatickDrawings.pdf PDF
summary of work.doc DOC document
06100Rough Carpentry.doc DOC document
02300_02Earthwork.doc DOC document
02106_02CompositeRd.doc DOC document
Drawings.pdf PDF
05120Steel.doc DOC document
Show 40 more

Latest 50 of 63 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 02225A

Earthwork

PART 1 - GENERAL

1.1 SUMMARY

A. Work shall include excavation, shaping, and compaction of campsites; borrow excavation; excavation of unsuitable material; and disposal of all excavated material necessary for the completion of campsite road spurs, living areas, and subsidiary work.

B. Embankment work includes placement and compaction of additional fill needed to raise campsite subgrades to elevations indicated on the drawings. Incidental embankment work includes the excavation and haul of borrow material from campsites where excess material needs to be removed in order to lower the subgrade to elevations indicated on the drawings and from designated borrow sources.

1.2 PAYMENT

A. The accepted quantities will be paid for at the contract unit price for each pay item shown in the BID SCHEDULE.

B. Water for compaction, if needed, will be paid for by Bid Item No. 21.

PART 2 – PRODUCTS NOT APPLICABLE

2. NOT APPLICABLE

PART 3 – EXECUTION

2.1 UTILIZATION OF EXCAVATED MATERIALS

A. All suitable, excavated material shall be used in the construction of campsite subgrades as SHOWN ON THE DRAWINGS.

1. Excavation of Unsuitable Material:

a. Unsuitable material shall be excavated. Disposal will be as SHOWN ON THE DRAWINGS. Excavated areas shall be backfilled with suitable material when necessary to complete the work. Frozen material shall not be placed in embankments.

2.2 FINISHING subgrades

A. The subgrade shall be visibly moist during shaping and compaction. Low sections, holes, or depressions shall be brought to grade with suitable material approved by the CO. Final compaction of the subgrade shall meet the requirements of the embankment placing method specified.

2.3 SNOW REMOVAL

A. Snow or ice shall not be incorporated in the embankment. Snow shall be removed in advance of the work and deposited beyond the roadway limits in a manner that will not cause resource damage or waste material.

2.4 EMBANKMENT PLACING METHOD

A. Specific Methods:

spec writer: edit method below

1. All embankments shall be placed by Method 3, except as specified in paragraph C below.

a. Method 3. Layer Placement (Roller Compaction): Embankment shall be layer placed. Each embankment layer shall be leveled, smoothed, and compacted before placement of subsequent layers.

1) Placement shall be in horizontal layers not exceeding 6 inches prior to compaction. Compaction equipment shall be operated over the full width of each layer until visible deformation of the layer ceases or in the case of the sheepfoot roller, the roller "walks out" of the layer. At least three complete passes shall be made.

2) Compaction equipment shall be capable of obtaining compaction requirements without detrimentally affecting the compacted material. The compacting units may be of any type, provided they are capable of compacting each lift of material as specified and meet the minimum requirements contained herein. Minimum requirements for rollers are as follows:

3) Tamping or sheepsfoot rollers shall meet the following minimum requirements:

4) Diameter - 40"

5) Completely filled with liquid.

b. Vibratory steel-wheel rollers shall have a minimum weight of 6 tons. The compactor shall be equipped with amplitude and frequency controls and specifically designed to compact the material on which it is used.

c. Pneumatic-tire rollers shall have smooth tread tires of equal size that provide a uniform compacting pressure for the full width of the roller and shall meet the following minimum requirements:

d. Towed rollers:

1) Ballast density shall exceed 100 pounds per cubic foot

2) Volume of ballast shall exceed 7 cubic feet per tire

3) Tire pressure shall exceed 45 pounds per square inch

e. Self propelled rollers:

1) Shall exert a force that exceeds 200 pounds per linear inch of rolling width.

B. Compact backfill in holes where tree stumps are removed under this contract or were removed by others prior to this contract in the same manner as specified in paragraph A above.

C. Compaction next to retaining walls shall be done with smaller mechanical equipment in order to avoid deflection of the retaining walls.

END OF SECTION 02225A