About this file

Aggregate - Natick Campground - Item 3

View the file

Other files

File Type Posted
SF 30 AMEND 3.PDF PDF
Amend 3 Questions and Answers.pdf PDF
Seed and Mulch natick cg.doc DOC document
DefBidItemsScott Tower Maint.doc DOC document
Camping Spurs and Pads Bessey Complex RSI.doc DOC document
SummaryOfWorkBessey complex rsi.doc DOC document
CompositeRd Natick CG.doc DOC document
SteelScott Tower Maint.doc DOC document
Scope of Work Pool.doc DOC document
BidItems Pool.doc DOC document
Submittals Pool.doc DOC document
SF 30 AMEND 2.PDF PDF
submittalsScott Tower Maint.doc DOC document
Asphalt ShinglesScott Tower Maint.doc DOC document
bid items natick.doc DOC document
DefBidItemsBessey complex rsi.doc DOC document
ScopeOfWorkScott Tower Maint.doc DOC document
scopeOfWorkNatick campground.doc DOC document
EarthworkBessey Complex RSI.doc DOC document
DrawingsBessey Complex RSI.pdf PDF
Rough CarpentryScott Tower Maint.doc DOC document
PaintingScott Tower Maint.doc DOC document
Selective DemolitionScott Tower Maint.doc DOC document
defofbiditems natic cg.doc DOC document
HandrailsScott Tower Maint.doc DOC document
Submittals Natick CG.doc DOC document
AWellAbandonment Pool.doc DOC document
Drawings Scott Tower Maint.pdf PDF
Earthwork Pool.doc DOC document
GFMBessey Complex RSI.doc DOC document
PoolDrawings.pdf PDF
SubmittalsBessey complex rsi.doc DOC document
SF 30 AMEND 1.PDF PDF
PoolDrawings.pdf PDF
02822_02Sod.doc DOC document
01732Selective Demolition.doc DOC document
experience questionnaire.pdf PDF
01330_02Submittals.doc DOC document
submittal procedures.doc DOC document
02525_02AWellAbandonment.doc DOC document
02616_02Aggregate.doc DOC document
01550_02GFM.doc DOC document
AG-82B1-S-10-0244.pdf PDF
NatickDrawings.pdf PDF
summary of work.doc DOC document
06100Rough Carpentry.doc DOC document
02300_02Earthwork.doc DOC document
02106_02CompositeRd.doc DOC document
Drawings.pdf PDF
05120Steel.doc DOC document
Show 40 more

Latest 50 of 63 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 02616

ROADWAY AGGREGATE SURFACING

PART 1 - GENERAL

1.1 SUMMARY

A. Place aggregate surfacing on campground road and campsite turnouts constructed under these specifications.

B. Supply and install aggregate in rock crossing.

C. Contractor shall submit to the Contracting Officer (CO) for approval aggregate source and certified sieve analysis. Approval shall be given prior to placing aggregate surfacing.

D. Contractor must receive subgrade approval from the CO before beginning aggregate placement.

PART 2 - PRODUCTS

1.2 gravel (bid items 10 and 12)

A. Surfacing material shall be composed of 80% aggregate and 20% clay.

B. Aggregate gradation shall fall within the following limits.

Sieve Designation
Percentages by Weight Passing Square

Mesh Seives (AASHTO T-27)

1 inch
95-100
¾ inch
90-100
No. 4
70-80
No. 10
45-55
No. 40
21-29
No. 100
1-9

C. Clay shall be pulverized to the extent that 90% will pass the ½ inch sieve and 60% will pass the No. 10 sieve.

D. The aggregate/clay shall be uniformly mixed.

Crushed Aggregate (bid items 10A and 12A) E. Aggregate shall be crushed and have the grading limits as shown on Table 1033.08 of the Standard Specifications for Highway Construction, Nebraska Department of Roads, 1997 English Units Edition:

Table 1033.08

Crushed Rock for Surfacing Gradation Limits

Percent Passing

Sieve Size

Target Value

Tolerance

1 inch

No. 4

+20

No. 10

+15

No. 50

No. 200

+5

F. Chemical additives shall not be used without the CO's written approval.

1.3 rock crossing aggregate

A. Aggregate shall be 3” minus crushed. Fifty percent of the aggregate shall be larger than 2” by weight.

PART 3 – EXECUTION

1.4 GENERAL

A. No surfacing shall be started until all excavation and embankments within the designated roadway is complete, including backfill and compaction to the required subgrade.

B. In no case shall any surfacing material be placed on a frozen, muddy, or unstable subgrade or until the subgrade has been checked and approved by the CO.

1.5 AGGREGATE SURFACING

A. Aggregate surfacing shall be uniformly placed over the entire prepared subgrade and compacted with a minimum of two passes of a steel drum or rubber tired roller.

B. If compaction water is included in this contract apply water as needed to aid in aggregate compaction.

END OF SECTION 02616

02616 - 1

ROADWAY AGGREGATE SURFACING