01732Selective Demolition.doc
DOC document 31 KB Posted
- Attached to
- RECOVERY - BESSEY COMPLEX REC SITE IMPROVEMENTS - BESSEY RANGE DISTRICT - NEBRASKA NATIONAL FOREST
- Solicitation number
- AG-82B1-S-10-0244
About this file
Scott tower - Demolition
View the file
Other files
Show 40 more
Latest 50 of 63 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 01732
SELECTIVE DEMOLITION
part 1 - GENERAL
1.1 SUMMARY
A. This Section includes demolition and removal of the following:
SPEC WRITER: ADJUST LIST BELOW TO SUIT PROJECT.
1. Timber stair treads and decking shown to be replaced.
2. Woven wire on stair, landing, and catwalk railings.
3. Shingles, underlayments, flashings, roof accessories, and shingle nails on all buildings to be reroofed.
4. Other miscellaneous items shown to be replaced.
1.2 DEFINITIONS
A. Remove: Detach items from existing construction and legally dispose of them off-site, unless indicated to be removed and salvaged or removed and reinstalled.
B. Remove and Reinstall: Detach items from existing construction, prepare them for reuse, and reinstall them where indicated.
C. Existing to Remain: Existing items of construction that are not to be removed and that are not otherwise indicated to be removed, removed and salvaged, or removed and reinstalled.
1.3 MATERIALS OWNERSHIP
A. Except for items or materials indicated to be reused, salvaged, reinstalled, or otherwise indicated to remain Government property, demolished materials shall become Contractor's property and shall be removed from Project site.
PART 2 – EXECUTION
1.4 EXAMINATION
A. Survey existing conditions and correlate with requirements indicated to determine extent of selective demolition required.
B. Inventory and record the condition of items to be removed and reinstalled and items to be removed and salvaged.
C. When unanticipated mechanical, electrical, or structural elements that conflict with intended function or design are encountered, investigate and measure the nature and extent of conflict. Promptly submit a written report to CO.
1.5 PREPARATION
A. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.
1. Do not close or obstruct streets, walks, walkways, or other adjacent occupied or used facilities without permission from CO and authorities having jurisdiction. Provide alternate routes around closed or obstructed traffic ways if required by governing regulations.
2. Erect temporary protection, such as walks, fences, railings, canopies, and covered passageways, where required by authorities having jurisdiction.
3. Protect existing site improvements, appurtenances, and landscaping to remain.
1.6 SELECTIVE DEMOLITION
A. Removed and Reinstalled Items:
1. Clean and repair items to functional condition adequate for intended reuse.
2. Protect items from damage during transport and storage.
3. Reinstall items in locations indicated. Comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make item functional for use indicated.
B. Existing Items to Remain: Protect construction to remain against damage and soiling during selective demolition.
1.7 DISPOSAL OF DEMOLISHED MATERIALS
A. General: Promptly dispose of demolished materials. Do not allow demolished materials to accumulate on-site.
B. Burning: Do not burn demolished materials.
C. Disposal: Transport demolished materials off Government property and legally dispose of them.
END OF SECTION 01732
01732 - 1
SELECTIVE DEMOLITION