DefBidItemsBessey complex rsi.doc
DOC document 42 KB Posted
- Attached to
- RECOVERY - BESSEY COMPLEX REC SITE IMPROVEMENTS - BESSEY RANGE DISTRICT - NEBRASKA NATIONAL FOREST
- Solicitation number
- AG-82B1-S-10-0244
About this file
Definition of Bid Items - Bessey Complex RSI ITEM 1
View the file
Other files
Show 40 more
Latest 50 of 63 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 01025
Definition of bid items and
MEASUREMENT AND PAYMENT
PART 1 - GENERAL
1.1 summary
A. The intent of this section is to explain, in general; what is and what is not included in a bid item; the limits or cut-off points where one bid item ends and another begins; and method of measurements and basis of payment for work items listed in the Bid Item Schedule.
B. Work:
1. Furnishing all labor, materials, equipment, and other incidentals necessary to successfully complete the project or any portion of it, and carrying out all duties and obligations imposed by the contract on the Contractor.
C. Payment:
1. For each individual item listed in the Schedule of Items, payment shall be full compensation for all work related to the particular item in accordance with these specifications, as shown on the drawings, and as staked in the field.
2. Measurement and payment for contract work shall be made only for and under those pay items included in the Schedule of Items. All other work and materials shall be considered incidental or as included in the payment for items shown.
1.2 DETERMINATION OF QUANTITIES
A. The contractor shall perform, or cause to be performed, all measurement of quantities of materials incorporated into the work processes that are to be measured under the provisions of the contract.
B. Quantity Measurements:
1. The Contractor shall make all measurements for computation of quantities for all work items except those specified for payment by Designed Quantity (DQ) or Lump Sum Quantity (LSQ).
2. The contractor shall compute the quantities for periodic progress payments; the Contracting Officer shall compute the quantities for the final payment based on measurements taken by the Contractor.
3. All Contractor measurements are subject to verification.
4. The Contractor shall submit all field notes, calculation sheets, and other data used to determine quantities.
5. The Contractor shall certify in writing as to the accuracy of the measurements and computations submitted.
C. The following measurements and calculations are used to determine contract quantities.
1. For individual construction items, longitudinal and lateral measurements for area computations shall be made horizontally or corrected to horizontal measurement unless otherwise specified. Measurements for geotextiles, netting and erosion control blankets shall be along slope lines.
2. The average end area method shall be used to compute volumes of excavation or embankment. However, if in the judgment of the Contracting Officer (CO), the average end area method is impractical, measurement shall be made by volume in hauling vehicles or by other three dimensional methods.
3. Structures shall be measured according to neat lines shown on the drawings or as altered by the CO, in writing, to fit field conditions.
4. For items that are measured by the linear foot, such as pipe culverts, fencing, guardrail, and underdrains, measurements shall be made parallel to the base or foundation upon which the structures are placed. Pipes shall be measured along center of invert.
5. For aggregates weighed for payment, the tonnage shall not be adjusted for moisture content, unless otherwise provided for.
6. For standard manufactured items--such as fence, wire, plates, rolled shapes, pipe conduits--identified by gauge, weight, section dimensions, and so forth, such identifications shall be considered the nominal weights or dimensions. Unless controlled by tolerances in cited specifications, manufacturer's tolerances shall be accepted.
1.3 UNITS OF MEASUREMENT
A. Payment shall be by units defined and determined according to U.S. Standard measure and by the following:
B. Cubic Yard: A measurement computed by one of the following methods:
1. Excavation, Embankment, or Borrow. The measurement computed by the average end area method from measurements made longitudinally along a centerline or reference line.
2. Material in Place or Stockpile. The measurement computed using the dimensions of the in-place material.
3. Material in the Delivery Vehicle. The measurement computed using measurements of material in the hauling vehicles at the point of delivery. Vehicles shall be loaded to at least their water level capacity. Leveling of the loads may be required when vehicles arrive at the delivery point.
C. Each: One complete unit, which may consist of one or more parts.
D. Linear Foot: Linear feet measured horizontally.
1.4 deFINItion of bid items
A. Definition Bid Item No. M01
1. Description: Mobilization. All preparatory work and operations necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; all quality control testing; all construction signing; any other work and operations that must be incurred prior to the beginning of work; and demobilization at the completion of work.
a. Measurement and payment: Payment will be made at the contract lump sum price.
b. Progress payments shall be made as follows:
1) When 5 percent or more of the original contract amount is earned from other pay items, 50 percent of the amount of this pay item or 2.5 percent of the original contract amount will be paid, whichever is less.
2) When 10 percent or more of the original contract amount is earned from other pay items, 100 percent of the amount of this pay item or 5 percent of the original contract amount will be paid, whichever is less.
3) Upon completion of all work on the project any unpaid amount for this item will be paid.
4) The total of all payments, including bonding, shall not exceed the original contract amount for this item.
2. Measurements and Payment: LSQ
B. Definition of Bid Item No. D01
1. Description: Remove Tree. Remove tree with diameter measured 4’ above ground equal to or greater than 2 inches. Dispose of the tree in the designated tree disposal area shown on the drawings. Removal of trees smaller than 2 inch diameter measured 4 feet above the ground is included in Bid Item 11.
a. Measurement and payment: Each, Actual Quantity (AQ) C. Definition Bid Item No. D02
1. Description: Remove Tree Stump. Remove tree stump with cut off diameter equal to or greater than 3 inches. Dispose of the stumps in the designated tree disposal area shown on the drawings. Removal of stumps with cut off diameters of less than 3 inches is included in Bid Item 11.
2. Measurements and Payment: Each, Actual Quantity (AQ) D. Definition Bid Item No. D03
1. Description: Remove Post. Remove barricade post as shown on the drawings. The item once removed becomes property of the contractor and shall be properly disposed off of government property.
2. Measurements and Payment: Each, Actual Quantity (AQ)
E. Definition Bid Item No. D04
1. Description: Remove Picnic Table. Remove picnic table with concrete base. Remove the precast concrete base and the cast in place concrete around the precast bases to a depth of 1 foot below finish grade. The item once removed becomes property of the contractor and shall be properly disposed off of government property. Removal of picnic tables without concrete bases will be done by others.
2. Measurements and Payment: Each, Actual Quantity (AQ)
F. Definition Bid Item No. D05
1. Description: Remove Retaining Wall. Remove timber retaining wall or timber curbs. Each campsite that has a timber retaining wall or timber retaining wall shown to be removed will be counted as one unit for payment purposes. Double campsites will count as two units. The item once removed becomes property of the contractor and shall be properly disposed off of government property.
2. Measurements and Payment: Each, Design Quantity (DQ)
G. Definition Bid Item No. D06
1. Description: Remove Asphalt Pavement. Remove asphalt pavement and dispose of in the designated asphalt disposal site shown on the drawings. Saw cutting asphalt edges where shown on the drawings is incidental to this bid item.
2. Measurements and Payment: Square Yard, Actual Quantity (AQ)
H. Definition Bid Item No. D07
1. Description: Remove Concrete Slab. Remove concrete slabs and fire ring concrete bases. The item once removed becomes property of the contractor and shall be properly disposed off of government property.
2. Measurements and Payment: Square Foot, Actual Quantity (AQ)
I. Definition Bid Item No. 11
1. Description: Campsite Development. Work includes removal of trees and stumps that are smaller than those included in Bid Items D01 and D02; removal of brush; removal of duff and topsoil when indicated on the drawings; removal of sand and other debris from existing asphalt pads when indicated on drawings and shaping and compaction of the subgrade. Each single campsite will count as one unit for payment purposes. Each double campsite will count at two units for payment purposes. Additional earthwork needed to bring the campsite subgrade to the elevations indicated on the drawing is included in Bid Item 12.
2. Measurements and Payment: Each, Actual Quantity (AQ)
J. Definition Bid Item No. 12
1. Description: Embankment. Work includes placement and compaction of additional fill needed to raise campsite subgrades to the elevations indicated on the drawings. Incidental work includes excavation and haul of borrow material from campsites where excess material needs to be removed in order to lower subgrade to elevations indicated on the drawings and from designated borrow sources.
2. Measurements and Payment: Compacted Cubic Yard, Design Quantity (DQ)
K. Definition Bid Item No. 13
1. Description: Aggregate Surfacing. Supply and install crushed aggregate surfacing, 4” compacted depth, as shown on the drawings.
2. Measurements and Payment: Tons, Actual Quantity (AQ)
L. Definition Bid Item No. 14
1. Description: Tent Pad Aggregate. Install aggregate, 2” depth, on new tent pad subgrades. Aggregate source is from existing aggregate on Road #265 north of campsite 27. Work includes skimming the top loose layer of aggregate off of the road surface, loading, hauling and placement on the tent pad subgrades. Each 16’x16’ tent pad counts as one unit for payment purposes.
2. Measurements and Payment: Each, Actual Quantity (AQ)
M. Definition Bid Item No. 15
1. Description: Erosion Control Rock. Supply and install crushed erosion control rock, 4” compacted depth, as shown on the drawings.
2. Measurements and Payment: Tons, Actual Quantity (AQ)
N. Definition Bid Item No. 16
1. Description: Wheel Stops. Supply and install wheel stops as shown on the drawings.
2. Measurements and Payment: Each, Actual Quantity (AQ)
O. Definition Bid Item No. 17
1. Description: Fire Ring and Base. Install government supplied fire rings. Work includes modifying the fire rings and supplying and installing a concrete base as shown on the drawings.
2. Measurements and Payment: Each, Actual Quantity (AQ)
P. Definition Bid Item No. 18
1. Description: Retaining Wall, 0.5’ Height. Supply and install a nominal 0.5’ high retaining wall as shown on the drawings. Work includes excavation and backfill as needed to install the wall to established grades.
2. Measurements and Payment: Lineal Foot, Actual Quantity (AQ)
Q. Definition Bid Item No. 19
1. Description: Retaining Wall, 1.0’ Height. Supply and install a nominal 1.0’ high retaining wall as shown on the drawings. Work includes excavation and backfill as needed to install the wall to established grades.
2. Measurements and Payment: Lineal Foot, Actual Quantity (AQ)
R. Definition Bid Item No. 20
1. Description: Retaining Wall, 1.5’ Height. Supply and install a nominal 1.5’ high retaining wall as shown on the drawings. Work includes excavation and backfill as needed to install the wall to established grades.
2. Measurements and Payment: Lineal Foot, Actual Quantity (AQ)
S. Definition Bid Item No. 21
1. Description: Compaction Water. Haul water from Forest Service source and apply to subgrades and aggregate surfacing as determined by the CO to aid in compaction.
2. Measurements and Payment: Mgal (1000 gallons), Actual Quantity (AQ)
PART 2 - METHOD OF MEASUREMENT
1.5 GENERAL
A. One of the following methods of measurement for determining final payment is designated on the Schedule of Items for each pay item:
B. DESIGNED QUANTITIES (DQ)
1. These quantities denote the final number or units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units shown in the Schedule of Items may be authorized under any of the following conditions:
a. As a result of changes in the work authorized by the CO.
b. As a result of the CO determining that errors exist in the original design that cause a pay item quantity to change by 15 percent or more.
c. As a result of the Contractor submitting to the CO a written request showing evidence of errors in the original design that cause a pay item quantity to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.
C. ACTUAL QUANTITIES (AQ)
1. These estimated quantities which are determined from actual measurements of completed work.
D. LUMP SUM QUANTITIES (LSQ)
1. These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They shall not be measured.
END OF SECTION 01025
01025-1
DEFINITION OF BID ITEMS &
MEASUREMENT AND PAYMENT