01570_wt_10_06.doc

DOC document 38 KB Posted

Attached to
RECOVERY: Blacktop paving parking lots, Wayne NF
Solicitation number
AG-4419-S-10-0338
Issued by

About this file

Spec 15

View the file

Other files

File Type Posted
01200_LAG_02_27_09_amended 2-10-10.doc DOC document
SECTION M.docx DOCX document
01110_wt_06_06 amended 2-10-2010.doc DOC document
SF 30_amend02.pdf PDF
WNF Paving All Drawings.pdf PDF
Schedule ZONE_1_Amended 2-10-10.xlsx XLSX spreadsheet
01600_wt_06_06.doc DOC document
PAVING-Schedule_ZONE_2_edited.xlsx XLSX spreadsheet
01360_wt_06_06.doc DOC document
PAVING-Schedule_Items_ZONE_1_edited.xlsx XLSX spreadsheet
01430_wt_09_08.doc DOC document
01720_wt_10_06.doc DOC document
01560_wt_06_06.doc DOC document
01110_wt_06_06.doc DOC document
01270_wt_11_07.doc DOC document
01510_wt_06_06.doc DOC document
01330_CM16_02_23_07.DOC DOC document
01770_list_wt_09_06.doc DOC document
01420_wt_06_06.doc DOC document
01200_LAG_02_27_09.doc DOC document
Wayne NF Paving drawings.pdf PDF
01310_wt_10_06.doc DOC document
00-index_wt_06_06.doc DOC document
PAVING-Schedule_ZONE_3 Edited.xlsx XLSX spreadsheet
01323_wt_10_06.doc DOC document
01571_wt_06_06.doc DOC document
01330_wt_sublist_09_06.doc DOC document
Solicitation_01.pdf PDF
SF 1442.pdf PDF
DBA_WD.pdf PDF
Experience_Capability Statement.doc DOC document
SF 1442 Cont_0338.pdf PDF
Drawings.pdf PDF
Schedule of Items.pdf PDF
Paving Project Specs.pdf PDF
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 01570

TEMPORARY CONTROLS

PART 1

GENERAL

1 .1 DESCRIPTION

A. The work of this section consists of providing temporary controls.

1 .2 SUBMITTALS

A. The following general management and recycling procedures shall be adhered to:

1. Waste products and materials that are recycled shall be separated from trash and sorted into appropriately marked separate containers and then transported to the respective recycling facility for further processing;

2. Remove recycled waste materials from project site on a regular basis. Do not allow recycled materials to accumulate on site.

3.

Transport recycled material off of USDA Forest Service property and legally dispose off site.

PART 2

PRODUCTS

Not used.

PART 3

EXECUTION

3.1

HOUSEKEEPING

A.

Keep project neat, orderly, and in a safe condition at all times.

B. Provide enough containers for collecting construction debris and construction materials to be recycled.

C. Provide individually marked containers for recycling personal items, such as aluminum cans, newspapers, glass, plastic, corrugated cardboard. These items shall be recycled by the Contractor.

D. Wet down dry materials and rubbish to prevent blowing dust.

E. Keep volatile wastes in covered containers.

F. Utilize excavated material as soon as possible.

3.2

DISPOSAL

A.

Dispose of excess excavated material (including rocks and boulders) that cannot be used in construction off site at location as shown on map in solicitation or other non USDA Forest Service site if Contractor so chooses and complies with all laws.

B.

Unless otherwise specified, all removed material becomes the property of the Contractor and shall be disposed of outside the project site in legal manner.

C.

Immediately remove hazardous rubbish from project site. Place other construction debris in refuse containers at least daily. Dispose of refuse at least weekly, in a legal manner, at public or private dumping areas outside the project site off federal land. Burning or burying refuse inside of the project site is not permitted.

3.3

AIR AND WATER POLLUTION CONTROL

A.

Take all necessary reasonable measures to reduce air and water pollution by any material or equipment used during construction.

B.

Do not dispose of volatile wastes or oils on site.

C.

Do not allow waste materials to be washed into streams or bodies of water.

D.

Seed slopes, as specified in the State of Ohio Department of Transportation, Construction and Material Specifications, Item 207 Temporary Sediment and Erosion Control, and Item 659 Seeding and Mulching, as soon as possible to prevent erosion. If it is impossible to prevent erosion, the Contracting Officer may require construction of sedimentation basins to prevent water pollution.

E.

All seed mixes must be approved by the C.O.R. before any seed is applied. All seed must not be considered a Non-Native Invasive Species (NNIS) by the USDA Forest Service. All seed must be considered native.

END OF SECTION

WAYNE NATIONAL FOREST,

01570-1

ROAD IMPROVEMENT PROJECTS, PROJECT NO.

TEMPORARY CONTROLS