01310_wt_10_06.doc

DOC document 35 KB Posted

Attached to
RECOVERY: Blacktop paving parking lots, Wayne NF
Solicitation number
AG-4419-S-10-0338
Issued by

About this file

Spec 10

View the file

Other files

File Type Posted
01200_LAG_02_27_09_amended 2-10-10.doc DOC document
SECTION M.docx DOCX document
01110_wt_06_06 amended 2-10-2010.doc DOC document
SF 30_amend02.pdf PDF
WNF Paving All Drawings.pdf PDF
Schedule ZONE_1_Amended 2-10-10.xlsx XLSX spreadsheet
01600_wt_06_06.doc DOC document
PAVING-Schedule_ZONE_2_edited.xlsx XLSX spreadsheet
01360_wt_06_06.doc DOC document
PAVING-Schedule_Items_ZONE_1_edited.xlsx XLSX spreadsheet
01430_wt_09_08.doc DOC document
01720_wt_10_06.doc DOC document
01560_wt_06_06.doc DOC document
01110_wt_06_06.doc DOC document
01270_wt_11_07.doc DOC document
01510_wt_06_06.doc DOC document
01330_CM16_02_23_07.DOC DOC document
01770_list_wt_09_06.doc DOC document
01420_wt_06_06.doc DOC document
01200_LAG_02_27_09.doc DOC document
Wayne NF Paving drawings.pdf PDF
00-index_wt_06_06.doc DOC document
PAVING-Schedule_ZONE_3 Edited.xlsx XLSX spreadsheet
01570_wt_10_06.doc DOC document
01323_wt_10_06.doc DOC document
01571_wt_06_06.doc DOC document
01330_wt_sublist_09_06.doc DOC document
Solicitation_01.pdf PDF
SF 1442.pdf PDF
DBA_WD.pdf PDF
Experience_Capability Statement.doc DOC document
SF 1442 Cont_0338.pdf PDF
Drawings.pdf PDF
Schedule of Items.pdf PDF
Paving Project Specs.pdf PDF
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 01310

PROJECT MEETINGS

PART 1

GENERAL

1 .1 PRECONSTRUCTION CONFERENCE

A. Before start of construction, Contracting Officer will arrange an on‑site meeting with Contractor. The meeting agenda will include the following as a minimum:

1. Rules and regulations

2. Authorized Representatives

3. Correspondence procedures

4. Labor standards provisions

5. Payroll reports

6. Modifications

7. Payments to Contractor

8. Acceptance/rejection

9. Construction progress

10. Subcontractors

11. Cultural resource studies

12.

Documents required under the contract

12. Submittal of shop drawings, project data, samples, and approved equals

13. As-constructed drawings/operation and maintenance (O&M) manuals (If applicable)

14. Saturday, Sunday, holiday and night work

15. Reference materials

16. Contractor quality control

17. Value engineering

18. Liquidated damages

19. Notice to proceed

20. Construction schedule

B. Submittals required prior to Preconstruction Conference – The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for the Preconstruction Conference.

1. Letter designating your Project Superintendent

2. Proposed Construction Progress Schedule

3. A comprehensive breakdown of the Schedule of Values

4. Accident Prevention Plan

5. A list of subcontractors for this project (must be same as in your proposal)

6. Written statements from your subcontractors certifying compliance with applicable labor standard clauses

7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contactor and all subcontractors

8. Waste and Recycling Plan

9. Quality Control Plan

10. Location of source for borrow material (if applicable)

11. Storm and Waste Water Pollution Prevention Plan

C. All items listed must be provided to the Contracting Officer before the Preconstruction Conference is held. If all of these documents have not been received one week prior to the scheduled Preconstruction Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.

1 .2 PROGRESS MEETINGS

A. The Contracting Officer will schedule weekly meetings with the Contractor.

B. The meeting agenda will include the following as a minimum:

1. Approval of minutes of previous meetings

2. Submittal status

3. Review of off‑site fabrication and delivery schedules

4. Requests for information (RFI) and other issues

5. Modifications

6. Work in progress and projected

7. Schedule update (provide updated CPM)

8. Status of Project Record Drawings and O&M manuals

9. Other business relating to work

PART 2

PRODUCTS

Not used.

PART 3

EXECUTION

Not used.

END OF SECTION

WAYNE NATIONAL FOREST,

01310-2

ROAD IMPROVEMENT PROJECTS, PROJECT NO.

PROJECT MEETINGS