SECTION 01310
PROJECT MEETINGS
PART 1
GENERAL
1 .1 PRECONSTRUCTION CONFERENCE
A. Before start of construction, Contracting Officer will arrange an on‑site meeting with Contractor. The meeting agenda will include the following as a minimum:
1. Rules and regulations
2. Authorized Representatives
3. Correspondence procedures
4. Labor standards provisions
5. Payroll reports
6. Modifications
7. Payments to Contractor
8. Acceptance/rejection
9. Construction progress
10. Subcontractors
11. Cultural resource studies
12.
Documents required under the contract
12. Submittal of shop drawings, project data, samples, and approved equals
13. As-constructed drawings/operation and maintenance (O&M) manuals (If applicable)
14. Saturday, Sunday, holiday and night work
15. Reference materials
16. Contractor quality control
17. Value engineering
18. Liquidated damages
19. Notice to proceed
20. Construction schedule
B. Submittals required prior to Preconstruction Conference – The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for the Preconstruction Conference.
1. Letter designating your Project Superintendent
2. Proposed Construction Progress Schedule
3. A comprehensive breakdown of the Schedule of Values
4. Accident Prevention Plan
5. A list of subcontractors for this project (must be same as in your proposal)
6. Written statements from your subcontractors certifying compliance with applicable labor standard clauses
7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contactor and all subcontractors
8. Waste and Recycling Plan
9. Quality Control Plan
10. Location of source for borrow material (if applicable)
11. Storm and Waste Water Pollution Prevention Plan
C. All items listed must be provided to the Contracting Officer before the Preconstruction Conference is held. If all of these documents have not been received one week prior to the scheduled Preconstruction Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.
1 .2 PROGRESS MEETINGS
A. The Contracting Officer will schedule weekly meetings with the Contractor.
B. The meeting agenda will include the following as a minimum:
1. Approval of minutes of previous meetings
2. Submittal status
3. Review of off‑site fabrication and delivery schedules
4. Requests for information (RFI) and other issues
5. Modifications
6. Work in progress and projected
7. Schedule update (provide updated CPM)
8. Status of Project Record Drawings and O&M manuals
9. Other business relating to work
PART 2
PRODUCTS
Not used.
PART 3
EXECUTION
Not used.
END OF SECTION