01270_wt_11_07.doc

DOC document 36 KB Posted

Attached to
RECOVERY: Blacktop paving parking lots, Wayne NF
Solicitation number
AG-4419-S-10-0338
Issued by

About this file

Spec 9

View the file

Other files

File Type Posted
01200_LAG_02_27_09_amended 2-10-10.doc DOC document
SECTION M.docx DOCX document
01110_wt_06_06 amended 2-10-2010.doc DOC document
SF 30_amend02.pdf PDF
WNF Paving All Drawings.pdf PDF
Schedule ZONE_1_Amended 2-10-10.xlsx XLSX spreadsheet
01600_wt_06_06.doc DOC document
PAVING-Schedule_ZONE_2_edited.xlsx XLSX spreadsheet
01360_wt_06_06.doc DOC document
PAVING-Schedule_Items_ZONE_1_edited.xlsx XLSX spreadsheet
01430_wt_09_08.doc DOC document
01720_wt_10_06.doc DOC document
01560_wt_06_06.doc DOC document
01110_wt_06_06.doc DOC document
01510_wt_06_06.doc DOC document
01330_CM16_02_23_07.DOC DOC document
01770_list_wt_09_06.doc DOC document
01420_wt_06_06.doc DOC document
01200_LAG_02_27_09.doc DOC document
Wayne NF Paving drawings.pdf PDF
01310_wt_10_06.doc DOC document
00-index_wt_06_06.doc DOC document
PAVING-Schedule_ZONE_3 Edited.xlsx XLSX spreadsheet
01570_wt_10_06.doc DOC document
01323_wt_10_06.doc DOC document
01571_wt_06_06.doc DOC document
01330_wt_sublist_09_06.doc DOC document
Solicitation_01.pdf PDF
SF 1442.pdf PDF
DBA_WD.pdf PDF
Experience_Capability Statement.doc DOC document
SF 1442 Cont_0338.pdf PDF
Drawings.pdf PDF
Schedule of Items.pdf PDF
Paving Project Specs.pdf PDF
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 01270

DEFINITION OF CONTRACT LINE ITEMS

PART 1

GENERAL

1.1

DESCRIPTION

A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut‑off points where one item ends and another begins.

B. If no contract line item exists for a portion of the work, include the costs in a related item

1.2

CONTRACT LINE ITEM NO.1 - GENERAL.

A.

The work of this contract consists of the general grading of existing aggregate road surface, compaction of graded surface, pavement replacement, asphalt pavement, asphalt sealing/chipping, traffic control marking and associated work.

B.

Measurement will be by the unit quantity per the Unit Price Bid Schedule.

C.

Payment will be made at the contract unit price per the Unit Price Bid Schedule.

PART 2

PRODUCTS

Not used.

PART 3

EXECUTION

Not used.

END OF SECTION