SECTION 01510
TEMPORARY SERVICES
PART 1
GENERAL
1 .1 DESCRIPTION
A. The work of this section consists of providing temporary services required for Contractor's performance of the work of this contract.
1 .2 RELATED REQUIREMENTS
A. Section 01520 - Field Offices and Sheds. (None Required for these Contract) B. Section 01570 - Temporary Controls.
PART 2
PRODUCTS
2.1
GENERAL
A.
Temporary materials may be new or used, but must be adequate in capacity for the required usage, must not create unsafe conditions, and must not violate requirements of applicable codes and standards.
2.2
SANITARY FACILITIES
A.
Provide and maintain temporary toilet facilities in accordance with State Health Department and USDA Forest Service requirements.
2.3
FIRE PROTECTION EQUIPMENT
A.
Extinguisher shall have a minimum UL rating of 2-A:10-B:C.
PART 3
EXECUTION
3.1
ELECTRICITY AND LIGHTING
A.
Make arrangements with utility company for metered connection to existing utility and pay all costs. If contractor requires such service.
B.
When temporary connections are removed, restore existing utility services to their original condition.
3.2
TELEPHONE
A.
No telephone service is available on site for Contractor's use. Make arrangements with Telephone Company and pay all costs.
3.3
WATER
A.
Water for construction is not available. The Contractor shall furnish water from a source outside of the project boundary
B.
Furnish cool, potable water for construction personnel in locations convenient to work stations.
3.4
SANITARY FACILITIES
A.
Place in approved locations secluded from public observation and convenient to work stations. Relocate as work progress requires.
B. Maintain and clean toilet facilities at least weekly.
C.
Completely remove sanitary facilities on completion of work.
3.5
FIRE PREVENTION AND PROTECTION
A.
Responsible Person: A capable and qualified person shall be placed in charge of fire protection. The responsibilities shall include locating and maintaining fire protective equipment and establishing and maintaining safe torch cutting and welding procedures.
B.
Hazard Control: Take all necessary precautions to prevent fire during construction. Do not store flammable or combustible liquids on-site. Provide adequate ventilation during use of volatile or noxious substances.
C.
Spark Arresters:
1. Written determinations of periods and areas of potential fire hazard will be issued by Contracting Officer.
2. Equip all gasoline or diesel powered equipment used during periods of potential fire hazards or in potential forest and grass fire locations with spark arresters approved by the USDA Forest Service. Equipment with turbo charged engines do not require spark arresters.
D.
Service and Refueling Areas: Locate areas a minimum of 50 feet from buildings. Shut down equipment before refueling. No refueling will be allowed within 50 feet of any open water.
C. Smoking: Smoking within buildings or temporary storage sheds is prohibited.
D. Welding: Cutting by torch or welding shall be performed only when adequate fire protection is provided. Check with Contracting Officer for welding ‘Burn Permit’ requirements.
3.6
PROTECTION EQUIPMENT REQUIRED
A.
Buildings:
1. Furnish a minimum of one extinguisher for each 1,500 square feet of area or major fraction thereof.
2. Travel distance from any work station to the nearest extinguisher shall not exceed 75 feet.
B. Vehicles and Equipment: Provide one extinguisher on each vehicle or piece of equipment.
3.7
CLEANING OF EQUIPMENT
A.
Clean all earth moving equipment prior to mobilization to the site. All equipment shall be free of soil to prevent the spread of Non-Native Invasive Species (NNIS) prior to entry to National Forest land. When demobilized from site, equipment will again be washed to prevent spread to next site as Non-Native Invasive Species (NNIS) is present at construction site. Failure to wash prior to arrival will result in that equipment being rejected at the site and removal will be required within 8 hours of notice by C.O.R.
END OF SECTION