SECTION 01110
SUMMARY OF WORK/BID SCHEDULE
PART 1
GENERAL
1 .1 DESCRIPTION
A. The work of this contract consists of the general grading of existing aggregate road surface, compaction of graded surface, pavement replacement, asphalt pavement, asphalt sealing/chipping, traffic control marking and associated work.
B. All work will be performed under a single contract.
1 .2 LOCATION
A. The road improvement work is located at varies site in the following Ohio counties: Athens, Lawrence, Hocking, Monroe, Perry and Washington.
1 .3 CONTRACTOR'S USE OF PREMISES
A. Construction Camp: Establishment of a camp within the project site will not be permitted.
B. The facility will be closed to the public during construction. However, maintain access for USFS staff for construction administration inspections, administrative, and other official business throughout the construction phase.
C. Confine storage of materials to the location(s) identified on the construction drawings.
D. Preservation of Natural Features: Confine all operations to limits shown for the project. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
1. Provide temporary barriers to protect existing trees and plants and root zones.
2. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer and remove agreed‑on roots and branches that interfere with construction.
3. Do not fasten ropes, cables, or guys to existing trees.
4. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
E. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.
1. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
2. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
3. Interruption of Existing Utility Service: Contractor to coordinate with local utility companies to minimize any potential delays and interruptions to existing utility services.
F. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on USDA Forest Service roads are identical to the state load restrictions with such additional regulations as may be imposed by the Contracting Officer. Information regarding rules and regulations for vehicular traffic on USDA Forest Service roads may be obtained from the Contracting Officer. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
1 .4 SPECIAL CONSTRUCTION REQUIREMENTS
A.
There are no limited access, seasonal shutdown, or limited access periods anticipated.
1.5
FIELD VERIFICATION
A. Field verify all new and existing dimensions affecting the work of this contract before ordering products.
1.6
CONSTRUCTION MATERIALS
A.
All materials, including borrow and aggregates, shall be Contractor‑furnished from outside the site.
1.7
SALVAGED MATERIALS
A.
In addition to materials specified in other sections, the following will remain the property of the Government: Contractor shall strip and salvage existing topsoil as identified within the construction drawings.
B. Stockpile material in the location(s) identified within the construction drawings & C.O.R.
1.8 DISPOSAL OF MATERIAL
A. The Contractor may dispose of material at a site they choose off USDA Forest Service property, as long as all laws are followed.
PART 2
PRODUCTS
Not used.
PART 3
EXECUTION
Not used.
PART 4 BID SCHEDULE
A.
Attached to these section is the bid schedule for these construction projects. All cost shall be included in the price so as to have a complete and functional project.
WAYNE NATIONAL FOREST,
01110-2
ROAD IMPROVEMENT PROJECTS, PROJECT NO.
SUMMARY OF WORK