About this file

J.1-2 SPECIFICATIONS (FILE 8 OF 22)

View the file

Other files

File Type Posted
SF30.pdf PDF
Revised Schedule of Items.docx DOCX document
Bidders SignIn Sheet.pdf PDF
SF-30.Amendment01.pdf PDF
OF 17.pdf PDF
SF-LLL FORM.pdf PDF
2003.162.034-Spec Cover.pdf PDF
312323-Backfill.pdf PDF
034100-Plant-Precast Structural Concrete.pdf PDF
NY34.dvb DVB file
230700-HVAC Insulation.pdf PDF
017000.pdf PDF
013300.pdf PDF
016000.pdf PDF
311000-Site Clearing.pdf PDF
000101-Table of Contents.pdf PDF
013000.pdf PDF
230523-General Duty Valves for HVAC PipingA.pdf PDF
230529-Hangers Supports for HVAC Piping and Equipment.pdf PDF
310516-Aggregate.pdf PDF
ag-3615-s-10-0003 geneva steam line - drawings.zip ZIP file
230553-Identification for HVAC Piping and Equipment.pdf PDF
321216 Bituminous Concrete Pavement.pdf PDF
071700-Bentonite Waterproofing.pdf PDF
329219-Seeding and Soil Supplements.pdf PDF
230500_Common work for HVAC.pdf PDF
014000.pdf PDF
232213-Steam and Condensate Heating Piping.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Steam Supply and Condensate Cast-In-Place Concrete Return Piping Replacement 033000-1 PGRU, Geneva, NY

SECTION 033000

CAST-IN-PLACE CONCRETE

PART 1 GENERAL

1.1 SUMMARY

A. Section includes cast-in-place concrete for MTW tunnel base slab.

1.2 REFERENCES

A. American Concrete Institute:

1. ACI 301 - Specifications for Structural Concrete.

2. ACI 305 - Hot Weather Concreting.

3. ACI 306.1 - Standard Specification for Cold Weather Concreting.

4. ACI 318 - Building Code Requirements for Structural Concrete.

B. American Society for Testing and Materials:

1. ASTM B221 - Standard Specification for Aluminum and Aluminum-Alloy

Extruded Bars, Rods, Wire, Profiles, and Tubes.

2. ASTM C33 - Standard Specification for Concrete Aggregates.

3. ASTM C94 - Standard Specification for Ready-Mixed Concrete.

4. ASTM C150 - Standard Specification for Portland Cement.

5. ASTM C260 - Standard Specification for Air-Entraining Admixtures for

Concrete.

6. ASTM C494 - Standard Specification for Chemical Admixtures for Concrete.

7. ASTM C618 - Standard Specification for Coal Fly Ash and Raw or Calcined

Natural Pozzolan for Use as a Mineral Admixture in Portland Cement Concrete.

8. ASTM C1017 - Standard Specification for Chemical Admixtures for Use in

Producing Flowing Concrete.

9. ASTM C1116 - Standard Specification for Fiber-Reinforced Concrete and

Shotcrete.

1.3 SUBMITTALS

A. Design Data:

1. Submit concrete mix design for each concrete strength. Submit separate mix designs when admixtures are required for the following:

a. Hot and cold weather concrete work.

b. Air entrained concrete work.

2. Identify mix ingredients and proportions, including admixtures.

1.4 QUALITY ASSURANCE

A. Perform Work in accordance with ACI 301.

B. Acquire cement and aggregate from one source for Work.

Return Piping Replacement 033000-2

C. Conform to ACI 305 when concreting during hot weather.

D. Conform to ACI 306.1 when concreting during cold weather.

1.5 COORDINATION

A. Coordinate placement of joint devices with erection of concrete formwork and placement of form accessories.

PART 2 PRODUCTS

2.1 CONCRETE MATERIALS

A. Cement: ASTM C150, Type I - Normal.

B. Fine and Coarse Aggregates: ASTM C33.

C. Water: Clean and not detrimental to concrete.

2.2 ADMIXTURES

A. Air Entrainment: ASTM C260.

B. Chemical: ASTM C494 Type A - Water Reducing and Type F - Water Reducing, Mid- Range.

C. Fly Ash: ASTM C618 Class F or C.

2.3 ACCESSORIES

A. Bonding Agent: Latex emulsion.

B. Non-Shrink Grout: Premixed compound consisting of non-metallic aggregate, cement, water reducing and plasticizing agents; capable of developing minimum compressive strength of 2,400 psi in 48 hours and 7,000 psi in 28 days manufactured by Sonneborn or equivalent.

2.4 CONCRETE MIX

A. Mix and deliver concrete in accordance with ASTM C94, Alternative Procedure 1.

B. Provide concrete to the following mix design:

Unit Measurement

Compressive Strength (28 day) 3500 psi (Reference) Cement 490 pounds Fiber Reinforcement 1 ½ lbs per cubic yard

Return Piping Replacement 033000-3

Water/Cement Ratio (maximum) .47 by weight (mass) Aggregate Size (maximum) 1 1/2 inch Air Entrained 6 percent plus/minus 1 percent Admixture Water Reducer, Type F Admixture Mid Range Plasticizer, Type F Fly Ash Pozzolan Content: Maximum 15 percent of cement content.

Slump - Plus or minus 1 inch 6 inches.

C. Admixtures: Include admixture types and quantities indicated in concrete mix designs approved through submittal process.

1. Use accelerating admixtures in cold weather. Use of admixtures will not relax cold weather placement requirements.

2. Use calcium chloride only when approved by the structural engineer.

3. Use set retarding admixtures during hot weather.

4. Add air entraining agent to normal weight concrete mix for work exposed to exterior.

2.5 STEEL REINFORCEMENT

A. Reinforcing Bars: ASTM A 615/A 615M, Grade 60 (Grade 420), deformed.

B. Plain-Steel Wire: ASTM A 82, as drawn.

2.6 CURING MATERIALS

A. Absorptive Cover: AASHTO M 182, Class 2, burlap cloth made from jute or kenaf, weighing approximately 9 oz./sq. yd. (305 g/sq. m) dry.

B. Moisture-Retaining Cover: ASTM C 171, polyethylene film or white burlap-polyethylene sheet.

C. Water: Potable.

PART 3 EXECUTION

3.1 EXAMINATION

A. Verify requirements for concrete cover over reinforcement. All reinforcing steel shall have a minimum of 4 inches of concrete cover measured from the bottom and sides of the tunnel base slab.

B. Verify anchors, seats, plates, reinforcement and other items to be cast into concrete are accurately placed, positioned securely, and will not interfere with placing concrete.

Return Piping Replacement 033000-4

3.2 PREPARATION

A. Prepare previously placed concrete by cleaning with steel brush and applying bonding agent.

B. In locations where new concrete is doweled to existing work, drill holes in existing concrete, insert steel dowels and fill holes around dowels with epoxy grout.

3.3 PLACING CONCRETE

A. Place concrete in accordance with ACI 301.

B. Notify Architect/Engineer minimum 24 hours prior to commencement of operations.

C. Ensure reinforcement, inserts and embedded parts are not disturbed during concrete placement.

D. Place concrete continuously. Do not interrupt successive placement; do not permit cold joints to occur.

3.4 CURING AND PROTECTION

A. Immediately after placement, protect concrete from premature drying, excessively hot or cold temperatures, and mechanical injury.

B. Maintain concrete with minimal moisture loss at relatively constant temperature for period necessary for hydration of cement and hardening of concrete.

C. Wet cure concrete tunnel base slab for a period of at least 7 days.

3.5 FIELD QUALITY CONTROL

A. Field inspection and testing will be performed in accordance with ACI 301.

B. Provide free access to Work and cooperate with appointed firm.

C. Submit proposed mix design of each class of concrete to inspection and testing firm for review prior to commencement of Work.

D. Three concrete test cylinders will be taken for every 50 or less cu yds of each class of concrete placed.

E. One additional test cylinder will be taken during cold weather concreting, cured on job site under same conditions as concrete it represents.

F. One slump test will be taken for each set of test cylinders taken.

G. One air content test will be made for each set of test cylinders taken.

Return Piping Replacement 033000-5

H. Maintain records of concrete placement. Record date, location, quantity, air temperature and test samples taken.

3.6 PATCHING

A. Allow Architect/Engineer to inspect concrete surfaces immediately upon removal of forms.

B. Excessive honeycomb or embedded debris in concrete is not acceptable. Notify Architect/Engineer upon discovery.

C. Patch imperfections or remove concrete and replace as directed by Architect/Engineer.

3.7 DEFECTIVE CONCRETE

A. Defective Concrete: Concrete not conforming to required lines, details, dimensions, tolerances or specified requirements.

B. Repair or replacement of defective concrete will be determined by Architect/Engineer.

C. Do not patch, fill, touch-up, repair, or replace exposed concrete except upon express direction of Architect/Engineer for each individual area.

END OF SECTION