About this file

J.1-2 SPECIFICATIONS (FILE 3 OF 22)

View the file

Other files

File Type Posted
SF30.pdf PDF
Revised Schedule of Items.docx DOCX document
Bidders SignIn Sheet.pdf PDF
SF-30.Amendment01.pdf PDF
OF 17.pdf PDF
SF-LLL FORM.pdf PDF
2003.162.034-Spec Cover.pdf PDF
312323-Backfill.pdf PDF
034100-Plant-Precast Structural Concrete.pdf PDF
NY34.dvb DVB file
230700-HVAC Insulation.pdf PDF
017000.pdf PDF
013300.pdf PDF
016000.pdf PDF
311000-Site Clearing.pdf PDF
000101-Table of Contents.pdf PDF
230523-General Duty Valves for HVAC PipingA.pdf PDF
033000-Cast in Place Concrete.pdf PDF
230529-Hangers Supports for HVAC Piping and Equipment.pdf PDF
310516-Aggregate.pdf PDF
ag-3615-s-10-0003 geneva steam line - drawings.zip ZIP file
230553-Identification for HVAC Piping and Equipment.pdf PDF
321216 Bituminous Concrete Pavement.pdf PDF
071700-Bentonite Waterproofing.pdf PDF
329219-Seeding and Soil Supplements.pdf PDF
230500_Common work for HVAC.pdf PDF
014000.pdf PDF
232213-Steam and Condensate Heating Piping.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Steam Supply and Condensate Administrative Requirements Return Piping Replacement 013000 - 1 PGRU, Geneva, NY

SECTION 013000

ADMINISTRATIVE REQUIREMENTS

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Coordination and project conditions.

B. Preconstruction meeting.

C. Site mobilization meeting.

D. Progress meetings.

E. Cutting and patching.

F. Special procedures.

1.2 COORDINATION AND PROJECT CONDITIONS

A. Coordinate scheduling, submittals, and Work of various sections of Project Manual to ensure efficient and orderly sequence of installation of interdependent construction elements.

B. Verify utility requirements and characteristics of operating equipment are compatible with building utilities. Coordinate work of various sections having interdependent responsibilities for installing, connecting to, and placing in service, operating equipment.

C. Coordinate space requirements, supports, and installation of mechanical Work indicated diagrammatically on Drawings. Follow routing shown for pipes as closely as practicable;

place runs parallel with lines of building. Utilize spaces efficiently to maximize accessibility for other installations, for maintenance, and for repairs.

D. Coordinate completion and clean-up of Work of separate sections in preparation for Substantial Completion.

E. After Owner occupancy of premises, coordinate access to site for correction of defective Work and Work not in accordance with Contract Documents, to minimize disruption of Owner's activities.

1.3 PRECONSTRUCTION MEETING

A. Owner and Architect/Engineer will schedule meeting after Notice of Award.

B. Attendance Required: Owner, Architect/Engineer, and Contractor.

Return Piping Replacement 013000 - 2 PGRU, Geneva, NY

C. Record minutes and distribute copies within five days after meeting to participants, with a copy to the Architect/Engineer, Owner, and those affected by decisions made.

1.4 SITE MOBILIZATION MEETING

A. Architect/Engineer will schedule meeting at Project site prior to Contractor occupancy.

B. Attendance Required: Owner, Architect/Engineer, Contractor, Contractor's Superintendent, and major Subcontractors.

C. Record minutes and distribute copies within five days after meeting to participants, with a copies to the Architect/Engineer, Owner, and those affected by decisions made.

1.5 PROGRESS MEETINGS

A. Schedule and administer meetings throughout progress of the Work at maximum bi-monthly intervals.

B. Architect/Engineer will make arrangements for meetings, prepare agenda with copies for participants, preside at meetings.

C. Attendance Required: Job superintendent, major subcontractors and suppliers, Owner, Architect/Engineer, as appropriate to agenda topics for each meeting.

D. Record minutes and distribute copies within five days after meeting to participants, with a copy to the Architect/Engineer, Owner, and those affected by decisions made.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.1 CUTTING AND PATCHING

A. Employ skilled and experienced installer to perform cutting and patching.

B. Submit written request in advance of cutting or altering elements affecting:

1. Structural integrity of element.

2. Integrity of weather-exposed or moisture-resistant elements.

3. Efficiency, maintenance, or safety of element.

4. Visual qualities of sight exposed elements.

5. Work of Owner or separate contractor.

C. Execute cutting, fitting, and patching [including excavation and fill,] to complete Work, and to:

1. Fit the several parts together, to integrate with other Work.

Return Piping Replacement 013000 - 3 PGRU, Geneva, NY

2. Uncover Work to install or correct ill-timed Work.

3. Remove and replace defective and non-conforming Work.

4. Remove samples of installed Work for testing.

5. Provide openings in elements of Work for penetrations of mechanical and electrical Work.

D. Execute work by methods to avoid damage to other Work, and to provide proper surfaces to receive patching and finishing.

E. Cut masonry and concrete materials using masonry saw or core drill.

F. Restore Work with new products in accordance with requirements of Contract Documents.

G. Fit Work tight to pipes, sleeves, ducts, conduit, and other penetrations through surfaces.

H. Maintain integrity of wall, ceiling, or floor construction; completely seal voids.

I. Refinish surfaces to match adjacent finishes. For continuous surfaces, refinish to nearest intersection; for assembly, refinish entire unit.

J. Identify hazardous substances or conditions exposed during the Work to Architect/Engineer for decision or remedy.

3.2 SPECIAL PROCEDURES

A. Materials: As specified in product sections; match existing with new products and salvaged products for patching and extending work.

B. Employ skilled and experienced installer to perform alteration work.

C. Cut, move, or remove items as necessary for access to alterations and renovation Work.

Replace and restore at completion.

D. Remove unsuitable material not marked for salvage, including rotted wood, corroded metals, and deteriorated masonry and concrete. Replace materials as specified for finished Work.

E. Remove debris and abandoned items from area and from concealed spaces.

F. Prepare surface and remove surface finishes to permit installation of new work and finishes.

G. Close openings in exterior surfaces to protect existing work from weather and extremes of temperature and humidity.

H. Remove, cut, and patch Work in manner to minimize damage and to permit restoring products and finishes to specified condition.

Return Piping Replacement 013000 - 4 PGRU, Geneva, NY

I. Refinish existing visible surfaces to remain in renovated rooms and spaces, to renewed condition for each material, with neat transition to adjacent finishes.

J. Where new Work abuts or aligns with existing, provide smooth and even transition. Patch Work to match existing adjacent Work in texture and appearance.

K. When finished surfaces are cut so that smooth transition with new Work is not possible, terminate existing surface along straight line at natural line of division and submit recommendation to Architect/Engineer for review.

L. Where change of plane of 1/4 inch or more occurs, submit recommendation for providing smooth transition; to Architect/Engineer for review.

M. Patch or replace portions of existing surfaces which are damaged, lifted, discolored, or showing other imperfections.

N. Finish surfaces as specified in individual product sections.

END OF SECTION