Text version
Steam Supply and Condensate Execution and Closeout Requirements Return Piping Replacement 017000 - 1 PGRU, Geneva, NY
SECTION 017000
EXECUTION AND CLOSEOUT REQUIREMENTS
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Closeout procedures.
B. Final cleaning.
C. Starting of systems.
D. Demonstration and instructions.
E. Testing, adjusting and balancing.
F. Protecting installed construction.
G. Project record documents.
H. Operation and maintenance data.
I. Manual for materials and finishes.
J. Manual for equipment and systems.
K. Spare parts and maintenance products.
L. Product warranties and product bonds.
M. Maintenance service.
1.2 CLOSEOUT PROCEDURES
A. Submit written certification that Contract Documents have been reviewed, Work has been inspected, and that Work is complete in accordance with Contract Documents and ready for Architect/Engineer's review.
B. Provide submittals to Architect/Engineer required by authorities having jurisdiction.
C. Submit final Application for Payment identifying total adjusted Contract Sum, previous payments, and sum remaining due.
1.3 FINAL CLEANING
A. Execute final cleaning prior to final project assessment.
Return Piping Replacement 017000 - 2 PGRU, Geneva, NY
B. Clean interior and exterior glass, surfaces exposed to view; remove temporary labels, stains and foreign substances, polish transparent and glossy surfaces, vacuum carpeted and soft surfaces.
C. Clean site; sweep paved areas, rake clean landscaped surfaces.
D. Remove waste and surplus materials, rubbish, and construction facilities from site.
1.4 STARTING OF SYSTEMS
A. Coordinate schedule for start-up of various equipment and systems.
B. Notify Architect/Engineer and Owner seven days prior to start-up of each item.
C. Verify each piece of equipment or system has been checked for proper lubrication, drive rotation, and for conditions which may cause damage.
D. Verify tests and meter readings agree with those required by equipment or system manufacturer.
E. Verify wiring and support components for equipment are complete and tested.
F. Execute start-up under supervision of applicable manufacturer's representative in accordance with manufacturers' instructions.
G. When specified in individual specification Sections, require manufacturer to provide authorized representative to be present at site to inspect, check, and approve equipment or system installation prior to start-up, and to supervise placing equipment or system in operation.
H. Submit a written report in accordance with Section 013300 - Submittal Procedures that equipment or system has been properly installed and is functioning correctly.
1.5 DEMONSTRATION AND INSTRUCTIONS
A. Demonstrate operation and maintenance of products to Owner's personnel two weeks prior to date of final inspection.
B. For equipment or systems requiring seasonal operation, perform demonstration for other season within six months.
C. Utilize operation and maintenance manuals as basis for instruction. Review contents of manual with Owner's personnel in detail to explain all aspects of operation and maintenance.
D. Demonstrate start-up, operation, control, adjustment, trouble-shooting, servicing, maintenance, and shutdown of each item of equipment at agreed time, at equipment designated location.
Return Piping Replacement 017000 - 3 PGRU, Geneva, NY
E. Prepare and insert additional data in operations and maintenance manuals when need for additional data becomes apparent during instruction.
F. Required instruction time for each item of equipment and system is specified in individual sections.
1.6 PROTECTING INSTALLED CONSTRUCTION
A. Protect installed Work and provide special protection where specified in individual specification sections.
B. Provide temporary and removable protection for installed products. Control activity in immediate work area to prevent damage.
C. Prohibit traffic from landscaped areas.
1.7 PROJECT RECORD DOCUMENTS
A. Maintain on site one set of the following record documents; record actual revisions to the Work:
1. Drawings.
2. Specifications.
3. Addenda.
4. Change Orders and other modifications to the Contract.
5. Reviewed Shop Drawings, Product Data, and Samples.
6. Manufacturer's instruction for assembly, installation, and adjusting.
B. Ensure entries are complete and accurate, enabling future reference by Owner.
C. Store record documents separate from documents used for construction.
D. Record information concurrent with construction progress, not less than weekly.
E. Specifications: Legibly mark and record at each product section description of actual products installed, including the following:
1. Manufacturer's name and product model and number.
2. Product substitutions or alternates utilized.
3. Changes made by Addenda and modifications.
F. Record Drawings and Shop Drawings: Legibly mark each item to record actual construction including:
1. Measured depths of foundations in relation to finish first floor datum.
2. Measured horizontal and vertical locations of underground utilities and appurtenances, referenced to permanent surface improvements.
3. Measured locations of internal utilities and appurtenances concealed in construction, referenced to visible and accessible features of the Work.
4. Field changes of dimension and detail.
5. Details not on original Contract drawings.
Return Piping Replacement 017000 - 4 PGRU, Geneva, NY
G. Submit documents to Architect/Engineer with claim for final Application for Payment.
1.8 OPERATION AND MAINTENANCE DATA
A. Submit data bound in 8-1/2 x 11 inch (A4) text pages, three D side ring capacity binders with durable plastic covers.
B. Prepare binder cover with printed title "OPERATION AND MAINTENANCE INSTRUCTIONS", title of project, and subject matter of binder when multiple binders are required.
C. Internally subdivide binder contents with permanent page dividers, logically organized as described below; with tab titling clearly printed under reinforced laminated plastic tabs.
D. Drawings: Provide with reinforced punched binder tab. Bind in with text; fold larger drawings to size of text pages.
E. Contents: Prepare Table of Contents for each volume, with each product or system description identified, typed on white paper, in three parts as follows:
1. Part 1: Directory, listing names, addresses, and telephone numbers of
Architect/Engineer, Contractor, Subcontractors, and major equipment suppliers.
2. Part 2: Operation and maintenance instructions, arranged by system and subdivided by specification section. For each category, identify names, addresses, and telephone numbers of Subcontractors and suppliers. Identify the following:
a. Significant design criteria.
b. List of equipment.
c. Parts list for each component.
d. Operating instructions.
e. Maintenance instructions for equipment and systems.
f. Maintenance instructions for special finishes, including recommended cleaning methods and materials, and special precautions identifying detrimental agents.
3. Part 3: Project documents and certificates, including the following:
a. Shop drawings and product data.
b. Air and water balance reports.
c. Certificates.
d. Originals of warranties.
1.9 MANUAL FOR MATERIALS AND FINISHES
A. Submit two copies of preliminary draft or proposed formats and outlines of contents before start of Work. Architect/Engineer will review draft and return one copy with comments.
B. For equipment, or component parts of equipment put into service during construction and operated by Owner, submit documents within ten days after acceptance.
Return Piping Replacement 017000 - 5 PGRU, Geneva, NY
C. Submit one copy of completed volumes 15 days prior to final inspection. Draft copy be reviewed and returned after final inspection, with Architect/Engineer comments. Revise content of document sets as required prior to final submission.
D. Submit three sets of revised final volumes in final form within 10 days after final inspection.
E. Building Products, Applied Materials, and Finishes: Include product data, with catalog number, size, composition, and color and texture designations. Include information for re-ordering custom manufactured products.
F. Instructions for Care and Maintenance: Include manufacturer's recommendations for cleaning agents and methods, precautions against detrimental agents and methods, and recommended schedule for cleaning and maintenance.
G. Moisture Protection and Weather Exposed Products: Include product data listing applicable reference standards, chemical composition, and details of installation. Include recommendations for inspections, maintenance, and repair.
H. Additional Requirements: As specified in individual product specification sections.
I. Include listing in Table of Contents for design data, with tabbed fly sheet and space for insertion of data.
1.10 MANUAL FOR EQUIPMENT AND SYSTEMS
A. Submit two copies of preliminary draft or proposed formats and outlines of contents before start of Work. Architect/Engineer will review draft and return one copy with comments.
B. For equipment, or component parts of equipment put into service during construction and operated by Owner, submit documents within ten days after acceptance.
C. Submit one copy of completed volumes 15 days prior to final inspection. Draft copy be reviewed and returned after final inspection, with Architect/Engineer comments. Revise content of document sets as required prior to final submission.
D. Submit three sets of revised final volumes in final form within 10 days after final inspection.
E. Each Item of Equipment and Each System: Include description of unit or system, and component parts. Identify function, normal operating characteristics, and limiting conditions. Include performance curves, with engineering data and tests, and complete nomenclature and model number of replaceable parts.
F. Include manufacturer's printed operation and maintenance instructions.
G. Include original manufacturer's parts list, illustrations, assembly drawings, and diagrams required for maintenance.
Return Piping Replacement 017000 - 6 PGRU, Geneva, NY
H. Include charts of valve tag numbers, with location and function of each valve, keyed to flow and control diagrams.
I. Include list of original manufacturer's spare parts, current prices, and recommended quantities to be maintained in storage.
J. Additional Requirements: As specified in individual product specification sections.
K. Include listing in Table of Contents for design data, with tabbed dividers and space for insertion of data.
1.11 SPARE PARTS AND MAINTENANCE PRODUCTS
A. Furnish spare parts, maintenance, and extra products in quantities specified in individual specification sections.
B. Deliver to Project site and place in location as directed by Owner; obtain receipt prior to final payment.
1.12 PRODUCT WARRANTIES AND PRODUCT BONDS
A. Obtain warranties executed by responsible subcontractors, suppliers, and manufacturers, within ten days after completion of applicable item of work.
B. Execute and assemble transferable warranty documents and bonds from subcontractors, suppliers, and manufacturers.
C. Verify documents are in proper form, contain full information, and are notarized.
D. Co-execute submittals when required.
E. Include Table of Contents and assemble in three D side ring binder with durable plastic cover.
F. Submit prior to final Application for Payment.
G. Time Of Submittals:
1. For equipment or component parts of equipment put into service during construction with Owner's permission, submit documents within ten days after acceptance.
2. Make other submittals within ten days after final inspection, prior to final Application for Payment.
3. For items of Work for which acceptance is delayed beyond Date of final acceptance, submit within ten days after acceptance, listing date of acceptance as beginning of warranty or bond period.
Return Piping Replacement 017000 - 7 PGRU, Geneva, NY
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
Not Used.
END OF SECTION