013300.pdf
PDF 19 KB Posted
- Attached to
- RECOVERY-- Replace Steam and Condensate Lines at the Plant Genetic Resources Unit (PGRU), Geneva, NY
- Solicitation number
- AG-3615-S-10-0003
About this file
J.1-2 SPECIFICATIONS (FILE 4 OF 22)
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Steam Supply and Condensate Submittal Procedures Return Piping Replacement 013300 - 1 PGRU, Geneva, NY
SECTION 013300
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Submittal procedures.
B. Construction progress schedules.
C. Proposed products list.
D. Product data.
E. Shop drawings.
F. Samples.
G. Design data.
H. Test reports.
I. Certificates.
J. Manufacturer's instructions.
K. Manufacturer's field reports.
L. Erection drawings.
M. Construction photographs.
1.2 SUBMITTAL PROCEDURES
A. Transmit each submittal with Architect/Engineer accepted form.
B. Sequentially number transmittal forms. Mark revised submittals with original number and sequential alphabetic suffix.
C. Identify Project, Contractor, subcontractor and supplier; pertinent drawing and detail number, and specification section number, appropriate to submittal.
D. Apply Contractor's stamp, signed or initialed certifying that review, approval, verification of products required, field dimensions, adjacent construction Work, and coordination of information is in accordance with requirements of the Work and Contract Documents.
Return Piping Replacement 013300 - 2 PGRU, Geneva, NY
E. Schedule submittals to expedite Project, and deliver to Architect/Engineer at business address. Coordinate submission of related items.
F. For each submittal for review, allow 15 days excluding delivery time to and from Contractor.
G. Identify variations from Contract Documents and product or system limitations which may be detrimental to successful performance of completed Work.
H. Allow space on submittals for Contractor and Architect/Engineer review stamps.
I. When revised for resubmission, identify changes made since previous submission.
J. Distribute copies of reviewed submittals as appropriate. Instruct parties to promptly report inability to comply with requirements.
K. Submittals not requested will not be recognized or processed.
1.3 CONSTRUCTION PROGRESS SCHEDULES
A. Submit preliminary outline Schedules within 15days after date of Owner-Contractor Agreement for coordination with work of separate contracts. After review, submit detailed schedules within 15 days modified to accommodate revisions recommended by Architect/Engineer.
B. Submit revised Progress Schedules with every second Application for Payment.
C. Distribute copies of reviewed schedules to Project site file, subcontractors, suppliers, and other concerned parties.
D. Instruct recipients to promptly report, in writing, problems anticipated by projections indicated in schedules.
E. Submit computer generated horizontal bar chart with separate line for each major portion of Work or operation, identifying first work day of each week.
F. Show complete sequence of construction by activity, identifying Work of separate stages and other logically grouped activities. Indicate early and late start, early and late finish, float dates, and duration.
G. Indicate estimated percentage of completion for each item of Work at each submission.
H. Submit separate schedule of submittal dates for shop drawings, product data, and samples, and dates reviewed submittals will be required from Architect/Engineer.
Indicate decision dates for selection of finishes.
I. Revisions To Schedules:
1. Indicate progress of each activity to date of submittal, and projected completion date of each activity.
Return Piping Replacement 013300 - 3 PGRU, Geneva, NY
2. Identify activities modified since previous submittal, major changes in scope, and other identifiable changes.
3. Prepare narrative report to define problem areas, anticipated delays, and impact on Schedule. Report corrective action taken, or proposed, and its effect including effect of changes on schedules of separate contractors.
1.4 PROPOSED PRODUCTS LIST
A. Within 15 days after date of Owner-Contractor Agreement, submit list of major products proposed for use, with name of manufacturer, trade name, and model number of each product.
B. For products specified only by reference standards, give manufacturer, trade name, model or catalog designation, and reference standards.
1.5 PRODUCT DATA
A. Product Data: Submit to Architect/Engineer for review for limited purpose of checking for conformance with information given and design concept expressed in Contract Documents.
B. Submit number of copies Contractor requires, plus two copies Architect/Engineer will retain.
C. Mark each copy to identify applicable products, models, options, and other data.
Supplement manufacturers' standard data to provide information specific to this Project.
D. Indicate product utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances.
E. After review, produce copies and distribute in accordance with SUBMITTAL PROCEDURES article and for record documents described in Section 01 70 00 - Execution and Closeout Requirements.
1.6 SHOP DRAWINGS
A. Shop Drawings: Submit to Architect/Engineer for review for limited purpose of checking for conformance with information given and design concept expressed in Contract Documents.
B. Indicate special utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances.
C. When required by individual specification sections, provide shop drawings signed and sealed by professional engineer responsible for designing components shown on shop drawings.
1. Include signed and sealed calculations to support design.
2. Submit drawings and calculations in form suitable for submission to and approval by authorities having jurisdiction.
Return Piping Replacement 013300 - 4 PGRU, Geneva, NY
3. Make revisions and provide additional information when required by authorities having jurisdiction.
D. Submit number of opaque reproductions Contractor requires, plus two copies Architect/Engineer will retain.
1.7 DESIGN DATA
A. Submit for Architect/Engineer's knowledge as contract administrator or for Owner.
B. Submit for information for limited purpose of assessing conformance with information given and design concept expressed in Contract Documents.
1.8 TEST REPORTS
A. Submit for Architect/Engineer's knowledge as contract administrator or for Owner.
B. Submit test reports for information for limited purpose of assessing conformance with information given and design concept expressed in Contract Documents.
1.9 CERTIFICATES
A. When specified in individual specification sections, submit certification by manufacturer, installation/application subcontractor, or Contractor to Architect/Engineer, in quantities specified for Product Data.
B. Indicate material or product conforms to or exceeds specified requirements. Submit supporting reference data, affidavits, and certifications as appropriate.
C. Certificates may be recent or previous test results on material or Product, but must be acceptable to Architect/Engineer.
1.10 MANUFACTURER'S INSTRUCTIONS
A. When specified in individual specification sections, submit printed instructions for delivery, storage, assembly, installation, start-up, adjusting, and finishing, to Architect/Engineer for delivery to Owner in quantities specified for Product Data.
B. Indicate special procedures, perimeter conditions requiring special attention, and special environmental criteria required for application or installation.
1.11 MANUFACTURER'S FIELD REPORTS
A. Submit reports for Architect/Engineer's benefit as contract administrator or for Owner.
B. Submit report in duplicate within 30 days of observation to Architect/Engineer for information.
Return Piping Replacement 013300 - 5 PGRU, Geneva, NY
C. Submit for information for limited purpose of assessing conformance with information given and design concept expressed in Contract Documents.
1.12 ERECTION DRAWINGS
A. Submit drawings for Architect/Engineer's benefit as contract administrator or for Owner.
B. Submit for information for limited purpose of assessing conformance with information given and design concept expressed in Contract Documents.
C. Data indicating inappropriate or unacceptable Work may be subject to action by Architect/Engineer or Owner.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
Not Used.
END OF SECTION
File details come from the government source that posted it. Updated .