Schedule of Items

View the file

Other files

File Type Posted
wen riv.pdf PDF
Naches_District roads.pdf PDF
CleElum_D_Map.pdf PDF
chelan.pdf PDF
833 3 culvert.pdf PDF
841_pbsc.doc DOC document
833 2 drain dip.pdf PDF
index of attachments.doc DOC document
entiat.pdf PDF
vicinity map.pdf PDF
Amendment 1.pdf PDF
SPS 842-1 Cutting Roadway Vegetation.doc DOC document
Tonasket Vicinity Map 11by17.doc DOC document
SPS 881-1 Mobilization-Equipment moving.doc DOC document
813_Spot_Surfacing_perf_based.doc DOC document
834_Roadway_Drainage_System_Maintenance_pbsc.doc DOC document
832_Load_Haul_and_Place_Materials_perf_based.doc DOC document
811_Surface Maintenance_perf_based.doc DOC document
807_Equipment_Rental_Perf_based.doc DOC document
872_sign_maintenance_pbsc.doc DOC document
834-1_Catch_Basin_Cleaning_Illustration.pdf PDF
833-1_X-Ditching_Illustration.pdf PDF
861_Guardrail_Traffic_Gates_and_Cattleguard_Maint_pbsc.doc DOC document
801-1_Illustration_of_Road_Structure_Terms.pdf PDF
RFQ AG-05GG-S-09-0057.doc DOC document
851-1_Hazard_Removal_Illustration.pdf PDF
881_Mob_Equip_Moving_pbsc.doc DOC document
842_Roadway_Veg_Maint_pbsc.doc DOC document
Methow Valley Vicinity map 8by11.doc DOC document
851_Hazard_Removal_pbsc.doc DOC document
Vicinity Map_WA_State.doc DOC document
851-2_Hazard_Removal_Illustration.pdf PDF
SPS811.02C.doc DOC document
Abbrev_MLs_Rd_Structure_details.doc DOC document
808_work area management.doc DOC document
814_Asphalt_Surface_Maintenance_perf_based.doc DOC document
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Amendment No. 1 RFQ AG-05GG-S-09-0057 August 4, 2009 Okanogan & Wenatchee NF

Forest-Wide Road Maintenance

Remove existing pages 3 - 7 and replace with the following: Page 3 of 52

SCHEDULE OF ITEMS

Item No.
Description
Pay Unit
Est Quant.
Unit Price
Total Price
811(3)
Surface Maintenance Level 3 roads
Single Lane Mile
250
$__________
$__________
811(3)(b)
Surface Maintenance Level 3 roads with water
Single Lane Mile
250
$__________
$__________
811(4)
Surface Maintenance Level 3 roads
Double Lane Mile
10
$__________
$__________
811(4)(b)
Surface Maintenance Level 3 roads with water
Double Lane Mile
10
$__________
$__________
811(5)
Surface Maintenance Level 2 roads
Single Lane Mile
125
$__________
$__________
811(5)(b)
Surface Maintenance Level 2 roads with water
Single Lane Mile
150
$__________
$__________
811(7)
Shoulder Maintenance
Road Mile
100
$__________
$__________
813(1)
Spot Surfacing, Gradation C
Cubic Yard
1000
$__________
$__________
813(3)
Spot Surfacing, Gradation C
Ton
500
$__________
$__________
814(1)
Pothole Patching
Ton
100
$__________
$__________
814(2)
Skin Patching
Ton
500
$__________
$__________
814(5)
Paved Surface Cleaning (Single Lane)
Mile
100
$__________
$__________
814(6)
Paved Surface Cleaning (Double Lane)
Mile
100
$__________
$__________
832(1)
Load, Haul, and Place Material
Cubic Yard
350
$__________
$__________
832(2)
Load, Haul, and Place Material
Mile
200
$__________
$__________
833(1)
ACTUAL PRODUCT TO BE INCLUDED IN INDIVIDUAL TASK ORDER

________Inch corrugated metal pipe

________Inch thickness for steel, ________Inch thickness for aluminum or

________Inch thickness for Plastic

Linear Foot
300
$PER T.O.
$PER T.O.
833(2)
Culvert Removal
Each
10
$__________
$__________
833(3)
Water-bar Installation
Each
30
$__________
$__________
833(4)
Water-bar Installation
Mile
20
$__________
$__________
833(5)
Water-bar Removal
Each
20
$__________
$__________
833(6)
Water-bar Removal
Mile
10
$__________
$__________
833(7)
Cross Ditch Installation
Each
30
$__________
$__________
833(8)
Cross Ditch Installation
Mile
20
$__________
$__________
Item No.
Description
Pay Unit
Est Quant.
Unit Price
Total Price
833(9)
Cross Ditch Removal
Each
10
$__________
$__________
833(10)
Cross Ditch Removal
Mile
10
$__________
$__________
833(11)
Driveable Drain Dip Installation
Each
20
$__________
$__________
833(12)
Driveable Drain Dip Installation
Mile
10
$__________
$__________
834(1)
Clean and Recondition Culverts
Each
50

24 inch Diameter and under

834(2)
Clean and Recondition Culverts
Each
10

Over 24 inch through 48 inch Dia

834(3)
Clean and Recondition Culverts
Each
10

Over 48 inch Diameter

834(4)
Clean Ditches
Mile
100
$__________
$__________
834(5)
Clean Ditches and Drainage Structures
Mile
50
$__________
$__________
834(6)
Clean Drainage Structures
Mile
10
$__________
$__________
841(1)
Establish Vegetation
Acres
30
$__________
$__________
841(2)
Establish Vegetation
Mile
20
$__________
$__________
841(3)
Establish Vegetation
Lump sum
10
$__________
$__________
842(1)
Vegetation Maintenance Level 4&5 roads
Mile
20
$__________
$__________
842(2)
Vegetation Maintenance Level 3 roads
Mile
80
$__________
$__________
842(3)
Vegetation Maintenance Level 2 roads
Mile
80
$__________
$__________
861(1)
Recondition/clean one-lane cattleguard
Each
10
$__________
$__________
861(2)
Recondition/clean two-lane cattleguard
Each
10
$__________
$__________
861(4)
Recondition/clean traffic gate
Each
20
$__________
$__________
872(3)
Install or Replace Single Post and Sign
Each
20
$__________
$__________
872(4)
Install or Replace Doulbe Post and Sign
Each
10
$__________
$__________
872(5)
Install or Replace Sign
Each
50
$__________
$__________
881(3)
Equipment Moving
Mile
150
$__________
$__________
881(4)
Equipment Moving
Hour
30
$__________
$__________

Total

SCHEDULE OF ITEMS - EQUIPMENT RENTAL

Item No.
Description
Pay Unit
Est. Quant.
Unit Price
Total Price
807(1)(a)
Grader Rental. 145-220 HP. Examples: Cat 120H, 12H, John Deere 670CH, Case 865D, New Holland RG. Minimum blade length: 14 feet.
Hour
400
$__________
$__________
807(1)(b)
Grader Rental. 115-145 HP. Examples: Cat 12H (Global), Case 845. Minimum blade length 12 feet.
Hour
150
$__________
$__________
807(2)
Backhoe Rental. 75 HP minimum. Front loader bucket capacity: 1 cubic yard minimum.
Hour
45
$__________
$__________
807(3)
Wheeled Front End Loader. 3-5 cubic yard rated bucket capacity. Minimum 140 HP.
Hour
40
$__________
$__________
807(4)
Tractor Mounted Rotary, Cylinder, or Flail roadside brush cutter Rental
Hour
160
$__________
$__________
807(5)(a)
Dumptruck Rental. 10 cubic yard bed capacity minimum.
Hour
60
$__________
$__________
807(5)(b)
Dumptruck w/ Pup trailer Rental. 20 cubic yard total bed capacity.
Hour
40
$__________
$__________
807(5)(c)
Belly Dump Truck Rental. 20 cubic yard minimum capacity.
Hour
30
$__________
$__________
807(6)
Rock Truck, articulated. 30 ton 6x6 wheel drive.
Hour
80
$__________
$__________
807(7)(a)
Dozer Rental. (Track-type). 70-120 HP. 5-way articulating blade. With Rippers. Example: Cat D4G XL, D5G XL.
Hour
60
$__________
$__________
807(7)(b)
Dozer Rental. (Track-type). 5-way articulating blade. With Rippers. 120-160 HP Example: Cat D5N XL, John Deere 750.
Hour
60
$__________
$__________
807(7)(c)
Dozer Rental. (Track-type).120-160 HP, with tow behind 15-20 ton grid roller. Example: Cat D5N XL, John Deere 750.
Hour
60
$__________
$__________
807(7)(d)
Dozer Rental. (Track-type). 5-way articulating blade. With Rippers. 200-285 HP. Example: Cat D7R.
Hour
40
$__________
$__________
807(7)(e)
Dozer Rental. (Track-type). 5-way articulating blade. With Rippers. 285 HP and above. Example: Cat D8.
Hour
40
$__________
$__________
807(8)(a)
Finn or equivalent Hydroseeder, 1700 gallon capacity. Includes two operators
Hour
80
$__________
$__________
Item No.
Description
Pay Unit
Est. Quant.
Unit Price
Total Price
807(8)(b)
Finn or equivalent Hydroseeder, 3300 gallon capacity. Includes two operators.
Hour
80
$__________
$__________
807(9)(a)
Hydraulic Excavator Rental. 90-110 HP. Thumb attachment on bucket. Examples: Cat 312C, Hitachi 120
Hour
60
$__________
$__________
807(9)(b)
Hydraulic Excavator Rental. 111-140 HP. Thumb attachment on bucket. Examples: Cat 320C, Hitachi 200LC, EX200LC.
Hour
60
$__________
$__________
807(9)(c)
Hydraulic Excavator Rental 141-180 HP. Thumb attachment on bucket. Example: Cat 322C
Hour
60
$__________
$__________
807(9)(d)
Hydraulic Excavator Rental 141-180 HP. Hydraulic Rock Breaker attachment. Example: Cat 322C.
Hour
60
$__________
$__________
807(9)(e)
Hydraulic Excavator Rental 181-260 HP. Thumb attachment on bucket. Example: Cat 330C, Hitachi 230CL.
Hour
30
$__________
$__________
807(10)(a)
Water Truck with spreader bar Rental. 1000-2500 gallon capacity.
Hour
250
$__________
$__________
807(10)(b)
Water Truck with spreader bar Rental. 2500-5000 gallon capacity.
Hour
250
$__________
$__________
807(11)
Smooth Steel Drum, Tandem or Single, Roller Rental. Riding. Minimum HP: 75. Minimum Drum Width: 4 feet. 7-11 ton.
Hour
200
$__________
$__________
807(12)
Materials Transport-Tractor Trailer combination rental; 40 foot trailer.
Hour
40
$__________
$__________
807(13)(a)(1)
Equipment Transport Rental- 0-20 ton.
Hour
40
$__________
$__________
807(13)(a)(2)
Equipment Transport Rental- 0-20 ton. Daily rate staged w/out operator.
Daily
40
$__________
$__________
807(13)(b)(1)
Equipment Transport Rental- 20-40 ton.
Hour
40
$__________
$__________
807(13)(b)(2)
Equipment Transport Rental- 20-40 ton. Daily rate staged w/out operator.
Daily
40
$__________
$__________
807(13)(c)(1)
Equipment Transport Rental- 40+ ton.
Hour
40
$__________
$__________
807(13)(c)(2)
Equipment Transport Rental- 40+ ton. Daily rate staged w/out operator.
Daily
40
$__________
$__________
807(14)
Vibratory Plate Compactor, Hand operated, Rental.
Hour
80
$__________
$__________
807(15)
Cut Off Saw, gasoline or electric Rental. Capable of cutting 12 gauge galvanized corrugated steel culvert.
Hour
40
$__________
$__________
807(16)
Volume Pump Rental. Minimum capacity 250 gallons per minute.
Hour
200
$__________
$__________

SCHEDULE OF ITEMS - EQUIPMENT RENTAL

Item No.
Description
Pay Unit
Est. Quant.
Unit Price
Total Price
807(17)
Timber Falling. (Includes vehicle, all equipment and supplies).
Hour
120
$__________
$__________
807(18)
General Labor. (Includes vehicle, incidental equipment and supplies).
Hour
120
$__________
$__________

807 Items Total:

B.1 EXECUTIVE SUMMARY: Contractor shall provide repair and maintenance services of Forest Service roads within and adjacent to the Okanogan and Wenatchee National Forest. Work may include, but not be limited to, the routine blading of aggregate and native surfaced single lane roads, ditch cleaning, dust abatement and road brushing. Other work that may be ordered includes culvert cleaning, culvert replacement, minor paving, and aggregate surfacing.

Contractor shall furnish all supervision, labor, materials, equipment, tools, transportation, and supplies, and perform all work required to maintain the facilities in accordance with drawings and specifications of the contract. Contractor will be paid for actual work performed. Items of work not listed herein that are considered within the general scope of the contract shall be negotiated on a lump sum basis based on material and equipment rental unit prices established in the contract. This is an indefinite delivery, indefinite quantity firm fixed priced multiple year contract. Task orders may be placed against this contract until September 30, 2013.

Minimum and Maximum Contract Amounts: As referred to in paragraph (b) of clause 52.216-22, entitled "Indefinite Quantity," the minimum quantity and contract guarantee for this contract is $5,000 with a maximum of $100,000 per task order not to be exceeded without the contractor's approval. (see clauses in section I).

Solicitation submittals: The primary performance time is estimated to be from May 15th to October 30th of each calendar year, starting in 2009 (see Section F). Contractor shall submit a signed SF-1449 and pricing information using the schedule of items. Other required submittals include an experience questionnaire with past experience, past projects and references (attached), a listing of make and type of equipment being offered, and Certifications and Representations (ensure your ORCA is up to date) (following the schedule of items pricing page).

Ordering: Task orders may be issued/signed only by a warranted Contracting Officer/Purchasing Agent with the requisite warrant authority to sign an individual task order. Orders placed will contain the following information: task order number and date, units to be worked, performance period, and accounting data.

The Task Order award document will be on any of the following:

a. OF-347 – Order for Supplies or Services

b. SF-1449

File details come from the government source that posted it. Updated .