832 LOAD, HAUL, AND PLACE MATERIALS
832.01 Service Required
Load, haul, and place material at designated sites.
832.02 Performance Standard
Loading, hauling, and placing is complete when no obstruction remains in or adjacent to the roadway or in ditches which would have the potential to interfere with traffic use, block or divert water from structures or channels. This includes relocation, repositioning, stabilization, and revegetation as ordered by the Contracting Officer.
832.03 Location of Work
As specified on roads listed on the ROAD LISTING, SHOWN ON THE PLANS, or as ordered by the Contracting Officer.
832.04 Measurement
Measurement under this Section will be made by the total number of units for each item listed in the SCHEDULE OF ITEMS completed and accepted.
A. Cubic Yard: The quantity will be the number of cubic yards measured in the vehicles.
B. Mile: Work activity will be measured along the centerline of the road regardless of the number of lanes.
832.05 Payment
A. The accepted quantities will be paid at the contract price per unit of measurement for the Section 832 pay items listed in the schedule of items. Payment will be full compensation for the work prescribed in this Section.
Pay Item
Pay Unit
832(1) Load, Haul, and Place Material
Cubic Yard
832(2) Load, Haul, and Place Material
Mile
832(3) Load, Haul, and Place Material
Lump Sum
832.06 Acceptable Quality Levels
| Description |
| Major |
| Minor |
| Allowable Defects |
| Required Action |
| Defect |
| Defect |
| Major |
| Minor |
| Major |
| Minor |
| Slopes |
| Unstable material left on slopes |
| Material left on slopes that can be stabilized and won't block drainages |
| 0 |
| N/A |
| Remove |
| N/A |
| Backslopes |
| Undercut backslope will result in destabilization of slope |
| Undercut backslope will not result in destabilization of slope |
| 0 |
| N/A |
| Repair and Stabilize |
| Revegetate if greater than X minor defects |
| Ditches, inlet/outlet channels, streams and catch basins |
| water will be diverted out of the drainage structure or soil enters system |
| < 20% impeded, but water will stay in the channel. |
| 0 |
| 10% of work ordered |
| Rework |
| Rework if greater than 10% of work ordered |
| Debris on Road (ML 4-5) |
| Any debris in traveled way |
| Debris in traveled way that may slow or impede traffic. |
| 0 |
| 0 |
| Rework |
| Rework |
| Debris on Road (ML 3) |
| Debris in traveled way that may impede traffic. |
| Debris in traveled way that may slow traffic. |
| 0 |
| Greater than 10% of road length treated |
| Rework |
| Rework |
| Debris on Road (ML 2) |
| Objects in traveled way that obstruct high clearance vehicles |
| Debris in traveled way that may impede high clearance vehicles |
| 0 |
| Greater than 10% of road length treated |
| Rework |
| Rework |
Placed Material
(Disposal Sites)
| Unstable material on designated sites. |
| N/A |
| 0 |
| N/A |
| Stabilize |
| N/A |
| Revegetation |
| No revegetation work done |
| Revegetation work incomplete |
| N/A |
| N/A |
| N/A |
| N/A |
| Work Area Management |
| Not following approved safety plan which may include signs, flaggers, and other temporary traffic control measures |
| Not following approved safety plan which may include signs, flaggers, and other temporary traffic control measures |
| 0 |
| 0 |
| Suspend work until in compliance |
| Suspend work until in compliance |
832 – LOAD, HAUL, AND PLACE MATERIALS (09/10/04) 1