872 SIGN MAINTENANCE
872.01 Service Required Furnish, install, and maintain forest entrance, destination, route markers, traffic signs, etc.
872.02 Performance Standard
Sign Maintenance is complete when designated signs meet the quality standards of EM 7100-15 Standards for Forest Service Signs and Posters, and Forest Service Sign Installation Guide 6E62H99 – Sign Installation Field Guide. Both EM 7100-15 and 6E62H99 are available at http://www.fs.fed.us/database/acad/om/.
872.03 Location of Work
As specified on roads listed on the ROAD LISTING, SHOWN ON THE PLANS, or as ordered by the Contracting Officer.
872.04 Measurement
Measurement under this Section will be made by the total number of units for each item listed in the SCHEDULE OF ITEMS completed and accepted.
A. Mile: Work activity will be measured along the centerline of the road regardless of the number of lanes.
872.05 Payment
A. The accepted quantities will be paid at the contract price per unit of measurement for the Section 872 pay items listed in the schedule of items. Payment will be full compensation for the work prescribed in this Section.
Pay Item
Pay Unit
872(1) Clean Sign Face
Each
872(2) Recondition Sign Face
872(3) Install or Replace Single Post and Sign
Each
872(4) Install or Replace Double Post and Sign
Each 872(5) Install or Replace Sign
872(6) Remove Sign
872(7) Remount Sign
872(8) Apply New Sign Face
872(9) Maintain Marker
872(10) Replace Marker
872 (11) Sign, Marker Maintenance
Mile 872.06 Acceptable Quality Levels
| Description |
| Major |
| Minor |
| Allowable Defects |
| Required Action |
| Defect |
| Defect |
| Major |
| Minor |
| Major |
| Minor |
| Materials |
| Signs, posts and other materials do not meet applicable standards |
| N/A |
| 0 |
| N/A |
| Reject and replace |
| N/A |
| Installation |
| Not installed according to applicable standards |
| N/A |
| 0 |
| N/A |
| Reject and replace |
| N/A |
| Maintenance |
| Not maintained according to applicable standards |
| N/A |
| 0 |
| N/A |
| Reject and replace |
| N/A |
| Work Area Management |
| Not following approved safety plan which may include signs, flaggers, and other temporary traffic control measures |
| N/A |
| 0 |
| 0 |
| N/A |
| Suspend work until in compliance |
* Forests have the option to choose a pay reduction in lieu of rework. However, each Forest must establish a threshold where rework is required and define pay reductions for each defect.
Intent and use: User to establish threshold for the acceptable level of quality.
872 - SIGN MAINTENANCE (09/10/04) 1