008-RogueRiverSiskiyouStatementOfWorkPackage.pdf

PDF 10 MB Posted

Attached to
Road Maintenance IDIQ Federal contract opportunity
Solicitation number
AG-04R4-S-15-0003
Issued by
Department of Agriculture Forest Service R6-Pacific Northwest Region

About this file

Statement of Work and road maintenance specifications applicable to the Rogue River-Siskiyou National Forest.

View the file

Other files for this federal contract opportunity

Other files attached to Road Maintenance IDIQ, newest first.
File Type Posted
Amendment4.pdf PDF
Amendment3-QuestionsAnswered-AG-04R4-S-15-0003.pdf PDF
Amendment2-ReturnPackage-AG-04R4-S-15-0003.pdf PDF
Amendment2-AG-04R4-S-15-0003.pdf PDF
Amendment1.pdf PDF
RevisedReturnPackage-RoadMaint.pdf PDF
004-BLM-FireProtection.pdf PDF
003-FS-FireProtection-All3.pdf PDF
AG-04R4-S-15-0003ClausesAndProvisions.pdf PDF
007-UmpquaStatmentOfWorkPackage.pdf PDF
005-WD1977-0079.pdf PDF
001-SampleTaskOrder.pdf PDF
002-IllustrationRoadStructureTerms.pdf PDF
006-Willamette-BLM-StatementOfWorkPackage.pdf PDF
009-FremontWinemaStatementOfWorkPackage.pdf PDF
ReturnPackage-RoadMaint.pdf PDF
Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ITEMS 8 - 9: ROGUE RIVER-SISKIYOU DESCRIPTION/SPECIFICATIONS/

STATEMENT OF WORK

SECTION 1—GENERAL

1.1 Scope of contract

The intent of the contract is for the awarded Contractor to provide for yearly road maintenance of forest roads on the Gold Beach Ranger District and the Powers Ranger District (RRS-West and Period of Performance of 01/01/2016 through 12/31/2018) and the High Cascades Ranger District, Siskiyou Mountains Ranger District, and Wild Rivers Ranger District (RRS-East and Period of Performance from date of award through 12/31/2018) of the Rogue River – Siskiyou National Forest. This work includes furnishing labor, equipment, supervision, transportation, operating supplies, and all incidentals necessary to provide maintenance in accordance with drawings and specifications of the contract. Contractor may be required to perform work items simultaneously on all three districts. In addition, the contractor may be required to respond to emergency storm events which may consist of removing trees, debris, slides and slough from drainage structures and/or traveled way to provide access to the forest.

The scope of work is not limited to the payment items identified herein. Other payment items within the overall scope of road maintenance may be added by contract modification if an agreeable price and performance time can be established. In the event requirements for work develop that are not pre-priced, the Government will provide a complete description of the specifications and payment items and request a unit price. If mutual agreement is reached on the pricing of additional payment items, they may be added to the contract at any time. If mutual agreement is not reached on proposed additional payment items, the Government reserves the right to contract for such work with others.

1.2 Location and Description

The location of the worksites, access to the areas, methods of work, size of each sub item, and other information pertinent to this contract are contained in the Vicinity and Project Maps, which shall be considered as part of the technical specifications.

Vicinity Maps are attached to this contract. Specific Project Location Maps shall be issued with each Purchase Order as necessary.

The attached road lists for each district may only be a portion of all the roads on the forest; specific roads requiring work will be listed on each Task Order.

The Typical Drawings included with the specifications are representative of work required.

Road Maintenance IDIQ AG-04R4-S-15-0003 Attachment 8: Rogue River-Siskiyou Package 1 of 162

Road Maintenance IDIQ AG-04R4-S-15-0003 Attachment 8: Rogue River-Siskiyou Package 2 of 162

1.3 Accessibility

1.3.1 Work areas may be reached by Forest roads that are accessible by a standard two-wheel drive pickup equipped with snow tires and chains, if needed, during normal operating seasons, unless otherwise indicated on Project Maps.

Vehicles shall not operate off system roads without prior written approval of the Contracting Officer.

1.3.2 Inaccessibility due to snow, fallen trees, slides or washouts on roads may or may not be corrected at the option of the Government. If road access is blocked, the Government may: (1) provide an alternate access route; (2) delete the inaccessible sub items (s) or; (3) substitute similar sub item(s).

1.3.3 Roads shown on unit maps indicate access to units and are not to suggest the roads are open within units or for any further travel.

1.3.4 Use of motorized equipment other than hand held equipment such as power saws and brush cutters will not be permitted off designated roads in the project area without approval of the Contracting Officer or as hereinafter provided.

1.3.5 No vehicle shall by-pass any officially blocked road (barriers, locked gates, posted signs, rock/log/dirt, etc.) without approval of the Contracting Officer.

SECTION 2--DEFINITIONS

Wherever in these specifications, or in other contract documents, the following terms, or pronouns in place of them, are used, the intent and meaning shall be interpreted as follows:

1. Agreed or Approved - Official agreement or approval by use of a written document issued by the Government. Agreements also require signature of Contractor's Representative and are dated.

2. Base Course – The layer or layers of specified or selected material of designed thickness placed on a subbase or a subgrade to support a surface course. (See Illustration of Road Maintenance Terms.)

3. Berm –A curb or dike that controls roadway runoff water, or delineates traffic direction.

4. Channel - A natural waterway leading into or away from a culvert or bridge.

5. Contract Amendment - A bilateral written supplemental agreement between the Government and the Contractor, documenting a modification outside the scope of the contract and establishing an equitable adjustment therefore.

Road Maintenance IDIQ AG-04R4-S-15-0003 Attachment 8: Rogue River-Siskiyou Package 3 of 162

6. Contractor - The individual, partnership, joint venture, or corporation undertaking the execution of the work under the terms of the contract.

5. Culvert - Any structure that provides a passageway, drain, or waterway under a road or embankment.

6. Cross ditch – A shallow ditch placed across the roadbed to remove water from the roadbed surface that can be driven across by full-size pickups or other high clearance vehicles; usually placed diagonal to the centerline.

7. Ditch – A relatively long narrow excavation placed to collect or disperse water.

8. Drainage dip – A drainage structure that was previously constructed within the roadbed surface to form a uniform depression that allows routine passage of vehicles while diverting water from the traveled way.

9. Drainage ditch – A ditch located parallel to and abutting the roadbed.

10. Drainage structure – A term identifying manufactured devices placed to control water movements.

11. Drawings – Illustrations showing detailed maintenance required.

12. Equipment – All machinery, operating supplies and tools necessary for the proper performance and acceptable completion of the work.

13. Excess Material – Material from the roadway in excess to that needed for maintenance of roadway.

14. Foreslope – The slope of the ditch section nearest to the traveled way.

15. Grade – The vertical alignment of the top surface of the road.

16. High Clearance Vehicles – Vehicles such as, pickups, 4x4s, and log trucks.

17. Highway Vehicles – Vehicles such as, passenger cars, High and low high clearance vehicles.

18. Hydrologic Function – Physical properties of the occurrence and movement of water on the earth’s surface and in particular that part which crosses transportation systems.

19. Inspector - The Government's authorized representative designated in writing, assigned to make detailed inspections of contract performance, but not to sign orders to the Contractor.

Road Maintenance IDIQ AG-04R4-S-15-0003 Attachment 8: Rogue River-Siskiyou Package 4 of 162

20. Lead-off ditch – A ditch used to remove water from roadside drainage ditches, the roadway, cattleguards, or drainage structures such as culverts and drainage dips.

21. Low Clearance Vehicles – Vehicles such as passenger cars, non 4x4 pickups, vans and other highway vehicles.

22. Materials – Any substances specified for use in the performance of the work.

23. Measurement – Method of determining and expressing the quantities of work.

24. Nominal Dimensions or Weights – The numerical values shown on the drawings or in the specifications as measurements for the work.

25. Order - A written order by the Government directing fulfillment of work requirements under the terms of the contract.

26. Original Contract Quantities - Those estimated quantities shown in the Schedule of Items as awarded.

27. Patching – Minor repairs.

28. Paved Surface or Pavement - Denotes asphalt, concrete, or other stabilized materials excluding natural aggregates. Dust palliative treatments are not considered as pavement.

29. Reasonably Close Conformity - Means compliance with customary maintenance tolerances where working tolerances are not specified.

30. Right-of-Way - A general term denoting land, property, or interest therein acquired for or devoted to a road.

31. Roadbed – The portion of a road between the intersection of the subgrade and side slopes, excluding that portion of the ditch below the subgrade.

32. Road Listing – A preliminary listing of road locations and any established work priorities.

33. Schedule of Items - Schedule containing a listing and description of maintenance items, quantities, units of measure, methods of measurement, unit price, and amount.

34. Shoulder – The portion of the roadway continuous to the traveled way for accommodation of stopped vehicles, emergency use, and lateral support of travel way structure.

Road Maintenance IDIQ AG-04R4-S-15-0003 Attachment 8: Rogue River-Siskiyou Package 5 of 162

35. Slough or Slide – Material deposited on the roadway that may need to be repositioned or removed.

36. Slump – A localized portion of the roadbed that has slipped, or otherwise become lower than the adjacent roadbed, and constitutes a hazard to traffic.

37. Supplemental Specifications - Specifications that detail conditions and requirements peculiar to the individual project.

38. Standard Specifications - Specifications for all divisions of work.

39. Subgrade – Top surface of roadbed upon which subbase, base course, or surface course was constructed.

40. Traveled Way – The portion of the roadway for the movement of vehicles. For purpose of this contract, traveled way includes turnouts and curve widening.

41. Turnouts - A short auxiliary lane on a one-lane road provided for passage of meeting vehicles.

42. Unit of Measure - The unit and fractions of units shown in the Schedule of Items.

43. Unsuitable Material - Material removed during maintenance which must be disposed of in designated locations. Includes material with substantial amounts of vegetation or other objectionable material.

44. Waterbar - A deeper type of cross ditch which is not intended for passage of low clearance passenger vehicles.

45. Work Schedule - The Contractor's current schedule for work progression.

Quantity Measurement Terms

1. U.S. Customary Units of measure are used in conjunction with these specifications.

2. The methods of measurement and computation will be those necessary to accurately determine the quantities of materials furnished and work performed.

3. All items, which are measured by the feet, will be measured parallel to its longitudinal centerline, unless otherwise shown on the drawings.

4. A station when used as a definition of term or measurement will be one hundred feet, or a precise location along a survey line.

Road Maintenance IDIQ AG-04R4-S-15-0003 Attachment 8: Rogue River-Siskiyou Package 6 of 162

5. Miles will, in the absence of known distances from existing plans or surveys, be determined by the Government using a calibrated survey odometer or equal substitute operated on the traveled way at or parallel to road centerline.

6. The term "ton" means 2000 pounds. Trucks used to haul material measured by truck weight shall be weighed empty at least once daily, and each truck shall bear a plainly legible identification mark. Weigh tickets furnished by the Contractor from certified scales will be used to determine weight measurements.

7. Materials measured by the cubic yard in the hauling vehicle shall be measured therein at the point of delivery. Vehicles may be of any size or type, provided that the box is of such shape that the actual volume may be readily and accurately determined.

8. Measurement by the acre will use the length and width treated. Measurement of width will approximate significant slope breaks, but will not include minor deviations along the slopes. The measured slope distance for the length will multiply width treated and converted to a standard 10,000 square yard or acreage value of the surface area treated.

9. Measure square yard with horizontal longitudinal and traverse measurements.

10. The term "lump sum" when used in the Schedule of Items means the complete unit as required by or described in the contract.

11. Measurement will be made of each item or unit of work, as shown in the Schedule of Items, completed and accepted in accordance with the contract provisions, specifications, and drawings.

SECTION 3--GOVERNMENT FURNISHED PROPERTY, MATERIALS, SERVICES

Specifications governing road maintenance work include Pacific Northwest (Region 6) Standard Specifications (2005 Performance Based Service Contract (PBSC)), and may include Rogue River-Siskiyou National Forest Standard Specifications for Maintenance of Roads and Special Project Specifications which refine, revise, and add to the Standard Specifications. The 2005 PBSC specifications are included in their entirety, but may reference the Standard Specifications for Constructions of Roads and Bridges on Federal Highway Projects FP-03. The Special Project Specifications and Standard Specifications must be read as a whole to gain a full understanding of the work required. In case of discrepancies, however, between these specifications, the Special Project Specifications will take precedence over the Standard Specifications.

Standard Specifications are numbered with three digits and may have an alpha character added. Special Project Specifications are numbered with the corresponding Standard Specification number followed by –1, -2 or other numbering suffix.

Road Maintenance IDIQ AG-04R4-S-15-0003 Attachment 8: Rogue River-Siskiyou Package 7 of 162

SECTION 4--CONTRACTOR FURNISHED CRITICAL ITEMS/SERVICES

Equipment as required to complete the work according to the attached specifications.

Furnishing Of Material

Unless otherwise stated in the Supplemental Specifications, the Contractor shall furnish all material required for performance of the contract. All material shall comply with the specifications. The Contractor shall verify the kind and amount of work that may be necessary in furnishing the material.

The Contractor shall furnish and deliver the material to the site of the work in such a manner that their quality and fitness for the work is preserved.

Measurement and payment for contract work will be made only for “work ordered under” those pay items included in the Schedule of Items. Measurement and payment for work or materials required to complete the project “in accordance with” the drawings and specifications and which are not included as pay items in the Schedule of Items will be considered as incidental to and included in the payment for other pay items shown and separate measurement and payment will not be made.

The Contractor shall be responsible for furnishing warning devices and complying with the safety standards and traffic management procedures as specified in this contract.

SECTION 5--PERFORMANCE WORK STATEMENT TASKS AND CRITICAL

SUBTASKS

All work will be performed in accordance with the attached specifications.

Manage all work areas in accordance with other clauses and specifications in this contract including documents incorporated by reference.

Water sources for Contractor use will be noted on individual task orders as needed.

640 Road Opening and Closure Devices

• Mobilization and equipment move-in included in Section 640(1).

811 Blading & Compaction --

• Grade sags and/or drainage dips shall be maintained in accordance with Section 811 and incidental to Payment Item 811.

Road Maintenance IDIQ AG-04R4-S-15-0003 Attachment 8: Rogue River-Siskiyou Package 8 of 162

813 Spot Surfacing --

• For all Districts location for placement of spot surfacing and source designations will be identified on task orders.

832 Load, Haul, and Place Materials

• Material will be placed at sites designated by the Contracting Officer.

834 Roadway Drainage System Maintenance

• When ordered by the Contracting Officer, excess material generated from ditch and culvert cleaning shall be removed and disposed of in accordance with Section 832. There shall be no side-casting or end dumping. Roads with POC concerns shall be worked in dry weather.

872 Sign Installation and Maintenance --

• Minor vegetation clearing to ensure visibility of the sign or marker is considered incidental to the sign work itself, and shall be treated in accordance with Section 842.

Special Requirements For Water Drafting Equipment Water drafting equipment may be used only at water sources designated on the Vicinity Map, task order, or provided by the Contracting Officer. Such equipment shall include a screen around the intake (foot valve) with openings no larger than 3/32 - inch. An air gap or positive antisiphon device shall be provided between the water source and the vehicle being loaded if the vehicle has been used for other than water haul, if the source is a domestic potable water supply, or the water is used for tank mixing with any other materials. Materials must be readily available and appropriate measures taken to prevent petroleum products from entering the water source.

861 Maintenance of Cattleguards, Traffic Gates and Barriers, Guardrails and Retaining Walls

• Maintain cattle guards at locations as directed by the Contracting Officer.

• Material will be placed at sites designated by the Contracting Officer.

Noxious Weed Mitigation Requirements.

Forest Service will flag and/or stake all known locations of noxious weeds prior to work commencing. Infested sites to be avoided will be marked with florescent orange flagging and labeled “NOXIOUS WEEDS” with black lettering. Forest Service will provide the contractor with a map indicating where the known infestations are located. Contractor will avoid performing road maintenance in the flagged and/or staked areas unless otherwise directed by the COR. If directed to work in an infested area and perform maintenance such as road grading, brushing and ditch maintenance contractor will be required to prevent spreading the infestation into uninfested areas. Contractor will be required to immediately clean vehicles and equipment after working in an invested area.

Road Maintenance IDIQ AG-04R4-S-15-0003 Attachment 8: Rogue River-Siskiyou Package 9 of 162

Special Equipment Cleaning Requirements Port Orford-Cedar Root Disease Port Orford-cedar Root Disease Control - Contractor vehicles and equipment shall be washed by high-pressure washer to remove all loose or dried soil, or mud from surface and underside of vehicles before entering contract area to prevent the spread of Port Orford-cedar root disease. Washing shall also be done any time Contractor equipment, or vehicles that have been operated outside the road travel way, are moved from an infected area, or if removed from the contract area and returned. The CO will inspect equipment prior to its transportation to the Forest. Work shall progress from uninfected sites to infected sites, as shown on the road listings or directed by the CO.

If water is drafted from sources possibly infested with phytophthora lateralis spores (Port Orford - cedar root disease), then Clorox (TM) must be added:

Rate: 1 Liter of Ultra Clorox Bleach in 1000 Liters of water (52.5 ppm sodium hypochlorite).

Treatment Site: Treatment of water to occur only in truck tanks, tankers, trailers, fold-a-tank, water buckets, or other similar water carrying equipment. No treatment to occur in natural or man-made sources, such as streams, lakes, ponds, rivers, sumps or reservoirs. Treated water must be used in forested areas: Water should be used for fire fighting purposes, dust abatement, equipment cleaning and road work.

Restrictions: No direct application of treated water to streams or other bodies of water.

Do not apply treated water in such a manner that allows run-off into bodies of waters such as creeks, streams, ponds, water-containing ditches, etc. Do not use as an irrigation source for plants. Do not use for drinking water.

It is a violation of Federal and State law to use this product inconsistent with it's labeling.Follow all directions, restrictions and precautions on the product label. The below label must be in possession of the user at the time of application.

Provide the Ultra Clorox Bleach Use Report to the CO within 15 days after each use period and at the close of the contract.

Restrict operations in affected areas to dry season. Waivers, at the discreation of the CO, may be issued in the event of extended dry weather.

Contractor shall clean all heavy equipment and vehicles prior to traveling or working in an Unifested area from an Infested area. Equipment and vehicles shall be cleaned and inspected at sites agreed to by the Forest Service. As much as practicable, work in uninfested areas first, then move to infested areas last.

Dispose of fill and debris from potentially infested sites in an approved area.

Roads in infected areas will be identified in the task orders.

Road Maintenance IDIQ AG-04R4-S-15-0003 Attachment 8: Rogue River-Siskiyou Package 10 of 162

SECTION 6--GOVERNMENT STANDARDS/STATE STANDARDS/TECHNICAL

EXHIBITS

001 Rogue River-Siskiyou National Forest Road Maintenance Specification

List and Acceptable Quality Levels RRS-East RRS-West 002 Rogue River-Siskiyou National Forest Road Lists RRS-East RRS-West 003 Vicinity Maps RRS-East RRS-West 004 RRS-West Quarantine Maps 005 Special Equipment Cleaning Requirements Port Orford Cedar

SECTION 7--QUALITY/PERFORMANCE REQUIREMENTS SUMMARY

All work shall be in compliance with the attached Acceptable Quality Levels included with each section of the road maintenance specifications.

Road Maintenance IDIQ AG-04R4-S-15-0003 Attachment 8: Rogue River-Siskiyou Package 11 of 162

Specification List

LISTING OF PERFORMANCE BASED SERVICE CONTRACT

SPECIFICATIONS

PBSC

Specification

DESCRIPTION

640F1 Road Opening and Closure Devices

807 Equipment Rental

811F1 SURFACE MAINTENANCE

813 Spot Surfacing

814 Asphalt Surface Maintenance Pothole Patching

832 LOAD, HAUL, AND PLACE MATERIALS

833 DRAINAGE STRUCTURE INSTALLATION OR REPLACEMENT

834 ROADWAY DRAINAGE SYSTEM MAINTENANCE

842F1 ROADWAY VEGETATION MAINTENANCE

851 HAZARD REMOVAL

MAINTENANCE of CATTLEGUARDS, TRAFFIC GATES, BARRIERS, GUARDRAILS, and RETAINING WALLS.

881 MOBILIZATION / EQUIPMENT MOVING

Road Maintenance IDIQ AG-04R4-S-15-0003 Attachment 8: Rogue River-Siskiyou Package 12 of 162

SECTION 640F1 – ROAD OPENING AND CLOSURE DEVICES

640.01

SERVICE REQUIRED:

Remove existing road closure devices and or install road closure devices using Jersey barriers, earth, earth-log, boulders, and or stumps as SHOWN ON THE DRAWING.

640.02

PERFORMANCE STANDARD:

Work is complete when road closure barriers have been removed and material has been conserved and re-positioned at designated locations for re-use as SHOWN ON THE

DRAWING.

Work is complete when road closure barriers have been constructed as SHOWN ON THE DRAWING and the road is not accessible to motorized vehicles.

640.03

LOCATION OF WORK:

As specified on roads listed on the ROAD LISTING, SHOWN ON THE PLANS or as ordered by the Contracting Officer.

640.04

MEASUREMENT:

Measurement under this Section will be made by the total number of units for each item in the SCHEDULE OF ITEMS completed and accepted.

640.05

PAYMENT:

The accepted quantities will be paid at the contract price per unit of measurement for the Section 640 pay items listed in the schedule of items. Payment will be full compensation for the work prescribed in this section.

Pay Item Description Pay Unit

640(1) Earthen Berm Repair Each 640(2) Remove Road Closure Device Each

Road Maintenance IDIQ AG-04R4-S-15-0003 Attachment 8: Rogue River-Siskiyou Package 13 of 162

640.06

ACCEPTABLE QUALITY LEVELS

Description Major Defect Minor Defect Allowable Defects

Required Action

Major Minor Major Minor

Remove Road Closure Device

Device not removed according to drawings and entrance not accessible

Some material remains but entrance is accessible.

0 per pay unit

1 per pay unit

Rework

Rework if greater than 1 minor defect

A loss of more than 10% of material

A loss of less material

0 per pay unit

0 per pay unit

Replace or recover lost material

Accept the loss of material

Install Road

Improper device installed or not installed according to drawings

Less than 10% deviation from lines and grades on drawings

0 per unit

0 per

Remove and install correct device according to drawings.

Road Maintenance IDIQ AG-04R4-S-15-0003 Attachment 8: Rogue River-Siskiyou Package 14 of 162

Road Maintenance IDIQ AG-04R4-S-15-0003 Attachment 8: Rogue River-Siskiyou Package 15 of 162

807 EQUIPMENT RENTAL

807.01 Service Required

Furnishing and operating equipment.

807.02 Performance Standards

A. Equipment will be weed free before it used on National Forest System lands.

B. Make equipment available for inspection and approval before use. Furnish the equipment specified in the table below:

807.03 Location of Work

Location of work is as specified on roads listed on the ROAD LISTING, SHOWN ON THE PLANS, or as ordered by the Contracting Officer.

807.04 Measurement

A. The accepted quantities will be paid at the established hourly rate, rounded to the nearest half (1/2) hour, that the equipment is in operation.

B. Non-operable equipment or equipment dependent on another piece of non-operable equipment will not be paid for.

C. Hours of operation shall be the same as for the Service Provider’s regular work shift, unless otherwise directed in writing by the Contracting Officer.

Description Max Age Min

HP

Min Reach Weight Capacity Attachments Remarks

Excavator 10 years Backhoe 75 14’ >13,000 Extendahoe Grader 10 years

Crawler Tractor

70 N/A

16,000 to 30,000

Six way blade, rippers

Dump Truck

220 N/A

10 CY

min.

Road Maintenance IDIQ AG-04R4-S-15-0003 Attachment 8: Rogue River-Siskiyou Package 16 of 162

D. Moving of equipment will be paid at the established hourly rate.

807.05 Payment

The accepted quantities will be paid at the contract price per unit of measurement for the Section 807 pay items listed in the schedule of items. Payment will be full compensation for the work prescribed in this Section.

PAY ITEM PAY UNIT

807(1) Backhoe Hour 807(2) Crawler Tractor - Dozer Hour 807(3) Dump Truck Hour

Road Maintenance IDIQ AG-04R4-S-15-0003 Attachment 8: Rogue River-Siskiyou Package 17 of 162

807.06 Acceptable Quality Levels

Description Major Minor Allowable

Defects Required Action Defect Defect Major Minor Major Minor

Weed free equipment Equipment not weed free. N/A 0 N/A Equipment rejected until it can be made weed free N/A

Maintenance of Equipment

Equipment not capable of operating at least 90% of the time N/A 0 N/A Replace defective equipment N/A

Equipment meets all state and federal regulations

Does not meet state and federal regulations N/A 0 N/A

Bring equipment up to state and federal regulations or replace equipment

N/A

Equipment leaks Equipment leaks in sensitive areas or leaks that are large and not typically inherent in the specific equipment

Small leaks inherent in the specific type equipment 0 N/A

Replace equipment and restore affected site as directed by the Contracting Officer

Place absorbent pads under equipment when not operating.

Equipment will be operated by a fully trained, qualified, and competent operator at all times.

Operator not fully trained, qualified, and competent. N/A 0 N/A

Stop equipment operation until a fully trained, qualified, and competent operator is available. Repair any damage done by incompetent operator as directed by the Contracting Officer

N/A

* Forests have the option to choose a pay reduction in lieu of rework. However, each Forest must establish a threshold where rework is required and define pay reductions for each defect.

Intent and use: User to establish threshold for the acceptable level of quality.

Road Maintenance IDIQ AG-04R4-S-15-0003 Attachment 8: Rogue River-Siskiyou Package 18 of 162

811F1 SURFACE MAINTENANCE

811.01

A. Smooth and shape native or aggregate surfaced roads including traveled way, shoulders, turnouts, and intersections. Reshape or recondition ditches, water bars, and drain dips. Water shall be applied as necessary to prevent segregation and facilitate compaction. When ordered by the Contracting Officer to work in a weed infested area the contractor will be required to prevent spreading the infestation into un-infested areas by cleaning vehicles and equipment. The contractor will use wash stations approved by the Contracting Officer.

B. When roller compaction is required, an 8-10 ton vibratory roller will be operated over the full width of the roadway for a minimum of 3 complete passes and until there is no visible evidence of consolidation. One pass is defined as operating the vibratory roller from the point where blading begins to the point where blading ends.

811.02 Performance Standards

Level 2-4 Roads

A road surface is maintained to standard when: The travel way is logged out, free of washboards, potholes, or other irregularities.

The surface is smooth, compact, crowned or sloped to drain, without segregation of the surfacing materials. Suitable materials have been recovered and incorporated. Unsuitable materials have been removed. Ditches and road surface drainage structures function efficiently. Unpaved shoulders are shaped to provide a smooth transition from the paved surface and drain efficiently.

811.03

As specified on roads listed on the road listing, shown on the plans or task orders, marked on the ground, or as ordered by the Contracting Officer. Locations of weed-infested areas are marked on the ground. Do not operate in the weed-infested areas unless ordered to do so by the Contracting Officer.

811.04 Measurement

Measurement under this Section will be made by the total number of units for each item listed in the SCHEDULE OF ITEMS completed and accepted.

Road Maintenance IDIQ AG-04R4-S-15-0003 Attachment 8: Rogue River-Siskiyou Package 19 of 162

A. Single Lane Roads: Surface maintenance will be measured along the centerline of the roadway. Turnouts are incidental. Measurement will be to the nearest one-tenth (0.1) mile.

B. Double Lane Roads: Surface maintenance will be measured along the centerline of the roadway. Measurement will be to the nearest one-tenth (0.1) mile.

C. Road Mile: Work activity will be measured along the centerline of the road regardless of the number of lanes, to the nearest one-tenth (0.1) mile.

811.05

The accepted quantities will be paid at the contract price per unit of measurement for the Section 811 pay items listed in the schedule of items. Payment will be full compensation for the work prescribed in this Section.

851(1) and 851(2) Log Out (Typical: LOGOUT) is incidental to the pay item.

Pay Item Pay Unit

811(1) Single Lane Roads Center Line Road Mile 811(2) Double Lane Roads Center Line Road Mile 811(3) Single Lane Roads with Roller Compaction Center Line Road Mile 811(4) Double Lane Roads with Roller Compaction Center Line Road Mile

811.06 Acceptable Quality Levels

Acceptance will be determined by visual inspection. If visual inspection finds that all work conforms to performance standards (811.02) the work will be acceptable. If visual inspection finds that occasional work elements do not completely conform to performance standards but non-conforming work elements are not representative of an overall quality of work problem the work will be acceptable. If visual inspection finds that non-conforming work is representative of an overall quality of work problem, rework will be required.

Road Maintenance IDIQ AG-04R4-S-15-0003 Attachment 8: Rogue River-Siskiyou Package 20 of 162

811.06 Acceptable Quality Levels Rogue River - Siskiyou NF FY 2015 - 2018 Road Maintenance Contract

Major Minor Allowable Defects Required Action Defect Defect Major Minor Major Minor

Surface Irregularitie s (Level 4&5)

Potholes greater than 2" deep and wider than 1 foot

Potholes 2" or less deep and 1 foot or less wide

0 per unit

2 per unit Rework

Rework if greater than 2 minor defects

Washboards greater than

1" deep

1” or less deep and not exceeding 20 feet long

0 per unit

2 per unit Rework

Rework if greater than 2

Surface Irregularitie s (Level 3)

Potholes greater than 2" deep and wider than 1 foot

Potholes 2” or less deep and 1 foot or less wide

1 per unit

2 per unit Rework if greater than 1 major defect

Rework if greater than 3

1" deep less than 1" deep and not exceeding 20 feet long

1 per unit

2 per unit Rework if greater than 1 major defect

Rework if greater than 3

Road Cross

Section (Level 4&5)

Crown or Cross Slope is not uniform and does not drain as specified on more than 250' of surface per mile

Crown or Cross Slope is not uniform and does not drain as specified on less than 250' of surface per mile

0 1 per unit Rework

Rework if greater than 1 minor defect

Road Maintenance IDIQ AG-04R4-S-15-0003 Attachment 8: Rogue River-Siskiyou Package 21 of 162

Defect Defect Major Minor Major Minor

Road Cross

Section (Level 3)

Crown or Cross Slope is not uniform and does not drain as specified on more than 250' of surface per mile

Crown or Cross Slope is not uniform and does not drain as specified on less than 250' of surface per mile

0 1 per unit Rework

Rework if greater than 1 minor defect

Road Cross

Section (Level 2)

Road surface does not drain properly and causes erosion, or obstructs high clearance vehicles

Road surface does not drain properly, but does not cause erosion

0 2 per unit Rework

Rework if greater than 2

Oversized Material

(Level 3&4 aggregate surfaced roads)

Material greater than 3" diameter remaining on the road surface

Material less than 3" diameter remaining on the road surface and traffic safety is not compromise d

0 2 per unit Rework

Rework if greater than 2

Oversized

(Level 2)

Objects in traveled way that obstruct high clearance vehicles

Debris in traveled way that may impede high clearance vehicles

0 2 per unit Rework

Rework if greater than 2 minor defects

Aggregate Surface Quality

Gradation of surface aggregate is degraded by

Gradation of surface aggregate is degraded by

0 1 per unit Rework

Rework if greater than 2

Road Maintenance IDIQ AG-04R4-S-15-0003 Attachment 8: Rogue River-Siskiyou Package 22 of 162

Defect Defect Major Minor Major Minor more than 10 % less than 10 defects

A loss of more than 10 CY/mile

A loss of less than 10 CY/mile 0 1 per unit Replace or recover lost material Accept the loss of material

Surfacing is segregated over more than a 100 square yard area per 1000 linear feet of road and traffic safety is compromise d

Surfacing is segregated over less than a 100 square yard area per 1000 linear feet of road and traffic safety is not compromise d

0 2 per unit Rework

Accept the loss of surface quality

Backslope s

Undercut backslope will result in destabilizatio n of slope

Undercut backslope will not result in destabilizatio n of slope

0 1 per unit Repair and Stabilize

Revegetat e if greater than 3 minor defects

Compactio n

Visible displacement occurs under hauling or spreading equipment

N/A 0 0 per unit Rework N/A

Ditches and Road Drainage

Structures

Impeded flow or water diverted out of drainage structures

< 20% impeded, but water will stay in the channel

0 1 per unit Rework

Rework if greater than 2 minor

Road Maintenance IDIQ AG-04R4-S-15-0003 Attachment 8: Rogue River-Siskiyou Package 23 of 162

Defect Defect Major Minor Major Minor

Unpaved Shoulders (Level 3, 4, & 5)

Elevation difference between pavement and shoulder is greater than 1"

Elevation difference between pavement and shoulder is less than

1"

0 2 per unit Rework

Rework if greater than 2

1/4" diameter remaining on the road surface

Material 1/4" diameter or less remaining on the road surface and traffic safety is not compromise d

0 3 per unit Rework

Rework if greater than 2

Working outside of project limits

Area contains invasive weeds

N/A 0 N/A Repair and treat affected areas as directed by the Contracting Officer N/A

Road Maintenance IDIQ AG-04R4-S-15-0003 Attachment 8: Rogue River-Siskiyou Package 24 of 162

813 SPOT SURFACING

813.01

Load, haul, and place surface material to repair or stabilize road surfaces.

813.02 Performance Standard

A. Spot surfacing is complete when the designated quantity of the ordered material has been placed and tailgate spread in a manner that will not impede traffic.

B. All materials transported onto National Forest System land will be weed-free. Written documentation of methods used to determine the weed-free status of any and all materials furnished by the contractor will be furnished to the Contracting Officer before transport of any materials onto National Forest System land.

813.03

As specified on roads listed on the ROAD LISTING, SHOWN ON THE PLANS, or as ordered by the Contracting Officer.

813.04

Measurement under this Section will be made by the total number of units for each item listed

A. The quantity will be the number of cubic yards measured in the vehicles, or square yards of aggregate placed.

B. Material measured by the ton shall be verified by certified weight tickets.

813.05

The accepted quantities will be paid at the contract price per unit of measurement for the Section 813 pay items listed in the schedule of items. Payment will be full compensation for the work prescribed in this Section.

Pay Item Pay Unit

813(1) Spot Surfacing, Gradation _____ Cubic Yard (less than 10 miles one way haul) 813(2) Spot Surfacing, Gradation _____ Cubic Yard (10 miles - 20 miles one way haul)

Road Maintenance IDIQ AG-04R4-S-15-0003 Attachment 8: Rogue River-Siskiyou Package 25 of 162

814 ASPHALT SURFACE MAINTENANCE

814.01

Repair and cleaning of pavement surfaces.

814.02

This work is complete when the pavement is clean and free of cracks, potholes, and surface irregularities.

Follow industry standards as outlined in the Asphalt Institute Manual Series Number 16.

814.03

As specified on roads listed on the ROAD LISTING, SHOWN ON THE PLANS, or as ordered by the Contracting Officer.

814.04

Measurement under this Section will be made by the total number of units for each item listed in the SCHEDULE OF ITEMS completed and accepted.

A. Single Lane Roads: The work activity will be measured along the centerline of the roadway. Turnouts are incidental. Measurement will be to the nearest one-tenth (0.1) mile.

B. Double Lane Roads: The work activity will be measured along the centerline of the roadway. Measurement will be to the nearest one-tenth (0.1) mile.

C. Road Mile: Work activity will be measured along the centerline of the road regardless of the number of lanes.

D. Ton: Material measured by the ton shall be verified by certified weight tickets.

E. Linear Foot: Work activity by the linear foot will be measured using standard survey methods rounded to the nearest one (1) foot.

Road Maintenance IDIQ AG-04R4-S-15-0003 Attachment 8: Rogue River-Siskiyou Package 26 of 162

814.05

A. The accepted quantities will be paid at the contract price per unit of measurement for the Section 814 pay items listed in the schedule of items. Payment will be full compensation for

814(1) Pothole Patching Ton 814(2) Skin Patching Ton 814(3) Crack Sealing Linear Foot 814(4) Crack Sealing Mile 814(5) Paved Surface Cleaning (Single Lane) Mile 814(6) Paved Surface Cleaning (Double Lane) Mile 814(7) Paved Surface Cleaning Each

Road Maintenance IDIQ AG-04R4-S-15-0003 Attachment 8: Rogue River-Siskiyou Package 27 of 162

Description Major Minor Allowable Defects Required Action Defect Defect Major Minor Major Minor

Pothole Patching

Finished elevation does not match adjoining segments by more than 1/4 inch

N/A 0 N/A Rework N/A

Patched material does not properly adhere to adjacent surfaces

N/A 0 N/A Rework N/A

Area to be patched is not properly prepared

N/A 0 N/A Rework N/A

Skin Patching

Finished skin patch does not make smooth transition with adjoining pavement.

N/A 0 N/A Rework N/A

Patched material does not properly adhere to adjacent surfaces

N/A 0 N/A Rework N/A

Area to be patched is not properly prepared

N/A 0 N/A Rework N/A

Crack Sealing

Crack Sealant does not completely fill the cracks greater than 1/4 inch

Crack Sealant does not completely fill the cracks 1/4 inch or less

0 1 per unit Rework Accept

Crack sealant does not properly adhere to adjacent surfaces

N/A 0 N/A Rework N/A

Area to be sealed is not properly prepared

N/A 0 N/A Rework N/A

Surface Cleaning

More than 5% of surface is not cleaned as specified

Less than 5% of surface is not cleaned as specified

0 1 per unit Rework Accept

Road Maintenance IDIQ AG-04R4-S-15-0003 Attachment 8: Rogue River-Siskiyou Package 28 of 162

Defect Defect Major Minor Major Minor

Asphalt Quality

Product and gradation does not meet Specifications and is not suitable for job.

Product and gradation does not meet Specifications but is otherwise suitable for job.

0 1 per unit Reject and replace Accept

Work Area Management

Not following approved safety plan which may include signs, flaggers, and other temporary traffic control measures

Not following approved safety plan which may include signs, flaggers, and other temporary traffic control measures

0 0 Suspend work until in compliance

Suspend work until in compliance

Road Maintenance IDIQ AG-04R4-S-15-0003 Attachment 8: Rogue River-Siskiyou Package 29 of 162

SECTION 832 – LOAD, HAUL AND PLACE MATERIALS

832.01

Load, haul, and place material at designated sites.

832.02

Loading, hauling, and placing is complete when no obstruction remains in or adjacent to the roadway or in ditches which would have the potential to interfere with traffic use, block or divert water from structures or channels. This includes relocation, repositioning, stabilization, shaping to drain, leaving accessible for future disposal needs, and revegetation as ordered by the Contracting Officer.

832.03

LOCATION OF WORK:

directed by the Contracting Officer.

832.04

MEASUREMENT:

Measurement under this Section will be made by the total number of units for each item listed in the SCHEDULE OF ITEMS completed and accepted.

A. Cubic Yard: The quantity will be the number of cubic yards measured in the vehicles.

B. Mile: Work activity will measured along the centerline of the road regardless of the number of lanes.

832.05

PAYMENT:

A. The accepted quantities will be paid at the contract price per unit of measurement for the Section 832 pay item listed in the schedule of items. Payment will be full compensation for the work prescribed in this Section.

832(1) Load, Haul and Place Material Cubic Yard (less than 10 miles one way haul)

832(2) Load, Haul and Place Material Cubic Yard (10 - 20 miles one way haul)

Road Maintenance IDIQ AG-04R4-S-15-0003 Attachment 8: Rogue River-Siskiyou Package 30 of 162

832.06

Major Defect Minor Defect Allowable Defects Required Action Major Minor Major Minor

Slopes

Unstable material left on slopes

Material left on slopes that can be stabilized and won’t block drainages

0 per pay

Remove Remove or stabilize in place

Backslopes

Undercut backslope will result in destabilization of slope

Undercut backslope will not result in destabilization of slope

Repair and Stabilize

Revegetate if greater than 2 minor defects

Ditches, inlet/outlet channels, streams and catch basins

Water will be diverted out of the drainage structure or soil enters system

<20% impeded, but water will stay in the channel

0 1 per pay

Rework if greater than 3 minor

Debris on Road (ML4- 5)

Any debris in traveled way

Debris in traveled way that may slow or impede traffic

0 2 per pay unit

Rework Rework if greater than 3 minor defects

Debris on Road (ML3)

Debris in traveled way that may impede traffic

Debris in traveled way that may slow traffic

0 3 per pay unit

Rework Rework if greater than 5 minor defects

Debris on Road (ML2)

Objects in traveled way that obstruct high clearance vehicles

Debris in traveled way that may impede high clearance vehicles

0 5 per pay unit

Rework Rework if greater than 5 minor defects

Placed material (Disposal Sites)

Unstable material on designated sites

N/A N/A Stabilize N/A

Work Area Management

Not following approved safety plan which may include signs, flaggers, and other temporary traffic control measures

Not following approved safety plan which may include signs, flaggers, and other temporary traffic control measures

0 0 Suspend work until in compliance

Suspend work until in compliance

Road Maintenance IDIQ AG-04R4-S-15-0003 Attachment 8: Rogue River-Siskiyou Package 31 of 162

SECTION 833 – DRAINAGE STRUCTURE INSTALLATION

OR REPLACEMENT

833.01

Install or remove drainage structures including culverts, water-bars and cross ditches.

(Culverts will be government furnished) 833.02

Drainage structure installation or replacement is complete when designated culverts, water-bars, or cross ditches have been installed to the lines and grades specified, and removed culverts have been properly disposed.

833.03

833.04

A. Mile: Work activity will be measured along the centerline of the road

B. Linear Foot: Work activities by the linear foot will be measured using standard survey methods rounded to the nearest one (1) foot. Culvert bands are incidental to the installation.

C. Each: Measured by the total number of units for each item in the schedule of items completed and accepted.

Road Maintenance IDIQ AG-04R4-S-15-0003 Attachment 8: Rogue River-Siskiyou Package 32 of 162

833.05

PAYMENT:

A. The accepted quantities will be paid at the contract price per unit of measurement for the Section 833 pay item listed in the schedule of items. Payment will be full compensation for the work prescribed in this Section.

Pay Item Description Pay Unit 833(1) less than or equal to 24 inch corrugated metal pipe Linear Foot 833(2) Culvert Removal Each 833(3) Water-bar Installation Each 833(4) Water-bar Installation Mile 833(5) Water-bar Removal Each 833(6) Cross Ditch Installation Mile 833(7) Cross Ditch Installation Each 833(8) Cross Ditch Removal Each

Road Maintenance IDIQ AG-04R4-S-15-0003 Attachment 8: Rogue River-Siskiyou Package 33 of 162

Road Maintenance IDIQ AG-04R4-S-15-0003 Attachment 8: Rogue River-Siskiyou Package 34 of 162

Road Maintenance IDIQ AG-04R4-S-15-0003 Attachment 8: Rogue River-Siskiyou Package 35 of 162

833.06

ACCEPTABLE QUALITY LEVEL

Description Major Defect Minor Defect Allowable Defects Required Action

Culvert size

Culvert is smaller than the designated diameter shown on the drawings

Culvert is larger than the designated diameter shown on the drawings

0 per unit

N/A

Remove culvert and replace with designated size

Accept if culvert fits the geometry of the road but pay at designated size, otherwise replace.

Culvert is shorter than the designated length shown on the drawings

Culvert is longer than the designated length shown on the drawings

0 per unit 0 per

Replace or add section to fit geometry of road.

Remove excess culvert and treat cut end, or harden fill slope to prevent erosion and pay for ordered length

Grade and alignment of culvert

More than 10% deviation from original lines and grades

10% or less deviation from original lines and grades

0 per unit 1 per

Remove and replace culvert

Repair if greater than 1 minor defects.

Sag or depression in road after placement of culvert and backfill material

Greater than 2 inch depression in traveled way

2 inch or less depression in traveled way on

0 per unit

1 per

Furnish, place and compact designated material to repair depression.

Repair if greater than 1 minor defects.

Removed culvert or pieces left on National Forest System Lands

Culvert or pieces of culverts left on National Forest System Lands

N/A 0 per unit N/A Remove from National Forest System Lands

N/A

Water-bars and cross ditches

More than 10% deviation from original lines and grades

10% or less deviation from original lines and grades

0 per unit 2 per unit

Rework Rework if greater than 2 minor defects

Road Maintenance IDIQ AG-04R4-S-15-0003 Attachment 8: Rogue River-Siskiyou Package 36 of 162

ACCEPTABLE QUALITY LEVELS:

Sedimentation

Operations cause or allow sediment to leave site.

N/A 0 per unit

N/A Cease operations until sediment is controlled

N/A

Work Area Management

Not following approved safety plan which may include signs, flaggers, and other temporary traffic control measures

Not following approved safety plan which may include signs, flaggers, and other temporary traffic control measures

0 0 Suspend work until in compliance

Suspend work until in compliance

Road Maintenance IDIQ AG-04R4-S-15-0003 Attachment 8: Rogue River-Siskiyou Package 37 of 162

SECTION 834 – ROADWAY DRAINAGE SYSTEM MAINTENANCE

834.01

Clean, recondition, and repair roadway drainage systems including culverts, downspouts, ditches, inlet and outlet channels, catch basins, and appurtenances.

834.02

Drainage system maintenance is complete when no obstruction remains in the defined area adjacent to the structure or in ditches which would have the potential to block water from entering the structure, back water into the structure (except for structures designed to function in a back-flooded manner), or divert water outside the defined channel. Equipment operation in live streams or hydraulic flushing of drainage structures is not permitted.

When ordered by the Contracting Officer to work in a weed infested area the contractor will be required to prevent spreading the infestation into un-infested areas by cleaning vehicles and equipment. The contractor will use wash stations approved by the Contracting Officer.

834.03

As specified on roads listed on the road listing, shown on the plans, marked on the ground and/or ordered by the Contracting Officer and;

1. Drainage structures including inlet structures, culverts, catch basins, inlet/outlet channels, and ditches within the area shown on the plans or in the supplemental specifications.

2. Culverts –. A minimum external horizontal distance of 10 feet in any direction from the inlet and outlet end and a minimum internal distance of 3 feet from the inlet and outlet ends. Culverts that need to be cleaned are those that have 20% or more of their end area blocked.

3. Ditches adjacent to the roadbed.

4. This work does not include bridges, cattleguards, drain dips or water bars.

5. Do not operate in the weed infested areas marked on the ground unless ordered to do so by the Contracting Officer.

Road Maintenance IDIQ AG-04R4-S-15-0003 Attachment 8: Rogue River-Siskiyou Package 38 of 162

834.04

Mile: Work activity will be measured along the centerline of the road regardless of the number of lanes.

834.05

A. The accepted quantities will be paid at the contract price per unit of measurement for the Section 834 pay items listed in the schedule of items. Payment will be full

834(1) Clean and Recondition Culverts Mile 834(2) Clean and…