001-SampleTaskOrder.pdf

PDF 477 KB Posted

Attached to
Road Maintenance IDIQ Federal contract opportunity
Solicitation number
AG-04R4-S-15-0003
Issued by
Department of Agriculture Forest Service R6-Pacific Northwest Region

About this file

A sample of what a task order may look like.

View the file

Other files for this federal contract opportunity

Other files attached to Road Maintenance IDIQ, newest first.
File Type Posted
Amendment4.pdf PDF
Amendment3-QuestionsAnswered-AG-04R4-S-15-0003.pdf PDF
Amendment2-ReturnPackage-AG-04R4-S-15-0003.pdf PDF
Amendment2-AG-04R4-S-15-0003.pdf PDF
Amendment1.pdf PDF
RevisedReturnPackage-RoadMaint.pdf PDF
004-BLM-FireProtection.pdf PDF
003-FS-FireProtection-All3.pdf PDF
AG-04R4-S-15-0003ClausesAndProvisions.pdf PDF
007-UmpquaStatmentOfWorkPackage.pdf PDF
005-WD1977-0079.pdf PDF
008-RogueRiverSiskiyouStatementOfWorkPackage.pdf PDF
002-IllustrationRoadStructureTerms.pdf PDF
006-Willamette-BLM-StatementOfWorkPackage.pdf PDF
009-FremontWinemaStatementOfWorkPackage.pdf PDF
ReturnPackage-RoadMaint.pdf PDF
Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Contractor: From:

Name:

Email:

Phone:

Contract Number: District TO #:

Item #: Requisition #:

Ranger District:

Pay Item Description Unit Est Qty Unit Price Amount

807(1) Equipment Rental, Excavator Hour 807(2) Equipment Rental, Backhoe Hour 807(3) Equipment Rental, Dozer Hour 807(4) Equipment Rental, Grader Hour 807(5) Equipment Rental, Compactor Hour 807(6) Equipment Rental, Dump Truck Hour 808(1) Single Flagger Operation Hour 808(2) Dual Flagger Operation Hour 811(1) Surface Maintenance Level 2 Roads MI 811(2) Surface Maintenance Level 2 Roads with Roller Compaction MI 811(3) Surface Maintenance Level 3 & 4 Roads with Roller Compaction MI 813(1) Spot Surfacing, Gradation _____ CY 813(2) Spot Surfacing, Gradation _____ Ton 813(3) Government Furnished Spot Surfacing, Less Than 10 Miles One Way Haul CY 813(4) Government Furnished Spot Surfacing, 10 - 20 Miles One Way Haul CY 814(1) Pothole Patching Ton 814(2) Skin Patching Ton 832(1) Load, Haul, and Place Materials, Less Than 5 Miles One Way Haul CY 832(2) Load, Haul, and Place Materials, 5 - 10 Miles One Way Haul CY 833(1) Culvert Removal EA 833(2) Water-bar Installation EA 833(3) Rolling Dip Installation EA 834(1) Clean and Recondition Culverts MI 834(2) Clean and Recondition Culverts EA 834(3) Clean Ditches MI 841(1) Hay Bail EA 842(1) Vegetation Maintenance Level 2 Roads MI 842(2) Vegetation Maintenance Level 3-5 Roads MI 851(1) Logging Out Maintenance Level 2 Roads MI 851(2) Logging Out Maintenance Level 3-5 Roads MI 851(3) Danger Tree Removal EA 851(4) Minimal Hazard or Obstruction Removal EA 851(5) Moderate Hazard or Obstruction Removal EA 861(1) Guardrail Replacement LF 861(2) Guardrail Post Replacement EA 861(3) Steel End Section Component and Fastener Replacement EA 872(1) Install or Replace Sign EA 881(1) Mobilization, < $10,000 Total Task Order Award Amount LS 881(2) Mobilization, $10,000 - $20,000 Total Task Order Award Amount LS 881(3) Mobilization, $20,001 - $50,000 Total Task Order Award Amount LS 881(4) Mobilization, > $50,000 Total Task Order Award Amount LS 881(5) Additional Equipment Washing EA 881(6) Equipment Moving MI

Total $ - Fixed price on parent IDIQ is the Unit Price for all sub items.

Project Specific Information:

See attached specifications and description of work.

Attachments:

Maps Project specific road list Project specific plans

Est. Start Date:

Performance Time:

(Each Forest will have a task order built from their unique Schedule of Items)

SAMPLE TASK ORDER

Willamette National Forest 3106 Pierce Parkway, Suite D Springfield, Oregon 97477

Road Maintenance IDIQ AG-04R4-S-15-0003 Attachment 1: Sample Task Order 1 of 1

Task Order