AF 66 Submittal Register.pdf

PDF 467 KB Posted

Attached to
Repair Water Tower B738
Solicitation number
FA303026Q0013
Issued by

About this file

This is an AF Form 66 Submittal Register for a construction project to repair Water Tower B738 (West) at Goodfellow Air Force Base, Texas. The document serves as a schedule of material submittals organized by submission type and categorized by submittal designation (SD-01 through SD-12), establishing requirements for contractor compliance throughout the project lifecycle.

The register identifies 65 line items requiring government approval across multiple submittal categories including pre-construction documents, shop drawings, product data, test reports, certifications, manufacturer's instructions and data, and closeout submittals. Key pre-construction submittals include work clearance requests, crane lift plans, contractor inventory records, baseline design schedules, accident prevention plans, and fall protection plans. Construction-phase submittals encompass quality control plans, environmental management systems, hazardous material safety data sheets, and progress documentation. Specialized submittals address lead-based paint removal procedures, metal fabrications for riser access components and safety grating, and elevated water storage tank repainting qualifications requiring documentation of painting contractor experience on at least five similar projects within the past five years and key personnel apprenticeship training. Closeout submittals include as-built drawings, operation and maintenance manuals, warranty management documentation, and final construction waste diversion reports. The register documents required submission dates, receipt dates, civil engineering review dates, return suspense dates, submittal numbers, contractor notification dates, and approval/disapproval determinations, establishing a comprehensive tracking mechanism for contractor deliverables throughout project execution.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

JCGU 26-7001 Repair Water Tower B738 (West)

Goodfellow AFB, TX AF Form 66 Submittal Register 3/10/2026

PROJECT NUMBER : SOLICITATION/CONTRACT NO.:

SCHEDULE OF MATERIAL SUBMITTALS

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

Use Electronic Delivery

LI

N

E N

U M

B

ER

ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL

All SUBMITTALS LISTED ON THIS SUBMITTAL REGISTER ARE FOR

GOVERNMENT APPROVAL; G

R

EQ

U

IR

ED

S

U B

M

IS

SI

O

N D

A

TE

D A

TE

R

EC

EI

V

ED

IN

C

O N

TR

A

C

TI

N G

D A

TE

T

O C

IV

IL

E N

G

IN

EE

R

IN

G

R

ET

U R

N S

U

SP

EN

SE

D A

TE

SU

B

M

IT

TA

L

N U

M B

ER

S

DATE CONTRACTOR NOTIFIED

C O

N

TR

A C

TO

R

R

ES

U B

M

IT

TA

L

FI

N

A L

A P

P R

O V

A L

REMARKS

APPROVED

DIS-

APPROVED

Section 01 00 00 Para 1.24, AF Form 103 and Section 01 18 00

Para 2.1 (Work Clearance Request) X

Section 01 00 00 Para 1.31 Crane EM 385-1-1 Form 16-2

(Standard Lift Plan) X

Section 01 00 00 Para 1.34, Contractor Inventory (Sustainment

Management System).

X

4 Section 01 00 00 Para 1.35 (A) As-Built Drawings X

Section 01 12 17 Para 1.2 (C) Bi-Weekly 3-Week Short Interval

Production Schedule (SIPS).

X

Section 01 18 00 Para 5 AF Form 3000 (GAFB Fire Hydrant Use

Request) X

7 Section 01 30 00 Para 1.3 Progress and Completion Pictures X

8 Section 01 30 00 Para 1.5.1 Superintendent Qualifications X X

Section 01 30 00 Para 1.5.1 Superintendent OSHA 30-Hour

Training Certificate X X

10 Section 01 30 00 Para 1.6 Pre-Construction Meeting Agenda X

Section 01 32 16.00 20 Para 1.1, Para 1.2 and Para 1.4 SD-01

Baseline Design Schedule and Monthly Updates X

Section 01 35 26 Para 1.3 and Para 1.7 SD-01 Accident

Prevention Plan (APP) - Site Specific X

13 Section 01 35 26 Para 1.3 SD-06 Notifications and Reports X

14 Section 01 35 26 Para 1.3 SD-06 Accident Reports X

15 Section 01 35 26 Para 1.3 SD-06 Activity Hazard Reports (AHA) X

16 Section 01 35 26 Para 1.3 SD-07 Certificate of Compliance X

Section 01 35 26 Para 1.3 and Para 1.7.3.2 SD-07 Standard Lift

Plan (SLP) X

Section 01 35 26 Para 1.3 and Para 1.17 SD-07 Severe Storm

Plan X

Section 01 35 26 Para 1.3 and Para 3.8.3 SD-07 Machinery and

Mechanized Equipment Certification X

20 Section 01 35 26 Para 1.4 SD-06 Monthly Exposure Reports X

Section 01 35 26 Para 1.6.1.2.3 Competent Person for Fall

Protection X

Section 01 35 26 Para 1.7.3.4 Fall Protection and Prevention

Plan (FP&P) Plan X

23 Section 01 35 26 Para 1.13.3 Inspection Reports X

JCGU 26-7001 Repair Water Tower B738 (West)

PROJECT TITLE:

P R

E- C

O N

ST

R

U C

TI

O

N

SD

-0

SH

O

P D

R A

W

IN

G S

(S D

-0

P R

O D

U C

T D

A

TA

SD

-0

SA

M

P

LE

S (S

D -0

D

ES

IG

N

D A

TA

SD

-0

TE

ST

R

EP

O R

TS

SD

-0

C

ER

TI

FI

C A

TI

O

N S

(S D

-0

M A

N U

FA

C

TU

R

E' S

IN

ST

R U

C

TI

O N

SD

-0

M A

N U

FA

C

TU

R

E' S

FI

EL

D R

EP

O

R

TS

SD

-0

O

TH

ER

SD

-1

M A

N U

FA

C

TU

R

E' S

M A

IN

TE

N A

N C

E D

A

TA

SD

-1

C

LO

SE

O

U T

SU

B

M

IT

TA

LS

SD

-1

AF Form 66 Submittal Register 3/10/2026

PROJECT NUMBER : SOLICITATION/CONTRACT NO.:

SCHEDULE OF MATERIAL SUBMITTALS

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

Use Electronic Delivery

LI

N

E N

U M

B

ER

ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL

All SUBMITTALS LISTED ON THIS SUBMITTAL REGISTER ARE FOR

GOVERNMENT APPROVAL; G

R

EQ

U

IR

ED

S

U B

M

IS

SI

O

N D

A

TE

D A

TE

R

EC

EI

V

ED

IN

C

O N

TR

A

C

TI

N G

D A

TE

T

O C

IV

IL

E N

G

IN

EE

R

IN

G

R

ET

U R

N S

U

SP

EN

SE

D A

TE

SU

B

M

IT

TA

L

N U

M B

ER

S

DATE CONTRACTOR NOTIFIED

C O

N

TR

A C

TO

R

R

ES

U B

M

IT

TA

L

FI

N

A L

A P

P R

O V

A L

REMARKS

APPROVED

DIS-

APPROVED

JCGU 26-7001 Repair Water Tower B738 (West)

PROJECT TITLE:

P R

E- C

O N

ST

R

U C

TI

O

N

SD

-0

SH

O

P D

R A

W

IN

G S

(S D

-0

P R

O D

U C

T D

A

TA

SD

-0

SA

M

P

LE

S (S

D -0

D

ES

IG

N

D A

TA

SD

-0

TE

ST

R

EP

O R

TS

SD

-0

C

ER

TI

FI

C A

TI

O

N S

(S D

-0

M A

N U

FA

C

TU

R

E' S

IN

ST

R U

C

TI

O N

SD

-0

M A

N U

FA

C

TU

R

E' S

FI

EL

D R

EP

O

R

TS

SD

-0

O

TH

ER

SD

-1

M A

N U

FA

C

TU

R

E' S

M A

IN

TE

N A

N C

E D

A

TA

SD

-1

C

LO

SE

O

U T

SU

B

M

IT

TA

LS

SD

-1

24 Section 01 35 26 Para 1.13.4 SD-07 Licenses and Certificates X X

25 Section 01 35 26 Para 1.14 SD-07 Hot Work Permit X

26 Section 01 35 26 Para 1.16 SD-07 Confined Space Entry Permit X

Section 01 45 00.00 10, Para 1.3 and Para 3.8.1 SD-06 Punch-

Out Inspection X

Section 01 45 00.00 10, Para 1.3 and Para 3.9.1 SD-06

Verification Statement X

Section 01 45 00.00 10, Para 3.2 SD-01 Contractor Quality

Control (CQC) Plan X

Section 01 56 00 SD-01, Para 18 Environmental Management

System (EMS) X

Section 01 56 00 SD-01, Para 3.8 Hazardous Material Safety

Data Sheet (SDS) X

Section 01 56 00 SD-01 Para 4.3 Contractor Hazardous Material

Authorization Inventory X

33 Section 01 56 00 SD-02 Para 15 Air Emission Source Reporting

34 Section 01 56 00 SD-02 Para 16 Construction and Debris

35 Section 01 56 00 SD-03 Para 11.4 Asbestos Free Certification

Section 01 56 00 SD-11 Para 4.4 Contractor Hazardous Material

Authorization Final Report (AF Form 3952) X

37 Section 01 57 19 Para 1.4 Environmental Protection Plan (EPP) X

Section 01 74 19 SD-01 Para 1.7 Construction Waste

Management Plan X

39 Section 01 74 19 SD-06 Quarterly Reports X

Section 01 74 19 SD-11 Para 1.10 Final Construction Waste

Diversion Plan X

41 Section 01 78 00 SD-03 Para 1.6.5 Warranty Management Plan

42 Section 01 78 00 SD-03 Para 1.6.5 Warranty Tags X

43 Section 01 78 00 SD-03 Para 3.5 Final Cleaning X

44 Section 01 78 00 SD-03 Para 3.5 Spare Parts Data

45 Section 01 78 00 SD-08 Posted Instructions

AF Form 66 Submittal Register 3/10/2026

PROJECT NUMBER : SOLICITATION/CONTRACT NO.:

SCHEDULE OF MATERIAL SUBMITTALS

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

Use Electronic Delivery

LI

N

E N

U M

B

ER

ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL

All SUBMITTALS LISTED ON THIS SUBMITTAL REGISTER ARE FOR

GOVERNMENT APPROVAL; G

R

EQ

U

IR

ED

S

U B

M

IS

SI

O

N D

A

TE

D A

TE

R

EC

EI

V

ED

IN

C

O N

TR

A

C

TI

N G

D A

TE

T

O C

IV

IL

E N

G

IN

EE

R

IN

G

R

ET

U R

N S

U

SP

EN

SE

D A

TE

SU

B

M

IT

TA

L

N U

M B

ER

S

DATE CONTRACTOR NOTIFIED

C O

N

TR

A C

TO

R

R

ES

U B

M

IT

TA

L

FI

N

A L

A P

P R

O V

A L

REMARKS

APPROVED

DIS-

APPROVED

JCGU 26-7001 Repair Water Tower B738 (West)

PROJECT TITLE:

P R

E- C

O N

ST

R

U C

TI

O

N

SD

-0

SH

O

P D

R A

W

IN

G S

(S D

-0

P R

O D

U C

T D

A

TA

SD

-0

SA

M

P

LE

S (S

D -0

D

ES

IG

N

D A

TA

SD

-0

TE

ST

R

EP

O R

TS

SD

-0

C

ER

TI

FI

C A

TI

O

N S

(S D

-0

M A

N U

FA

C

TU

R

E' S

IN

ST

R U

C

TI

O N

SD

-0

M A

N U

FA

C

TU

R

E' S

FI

EL

D R

EP

O

R

TS

SD

-0

O

TH

ER

SD

-1

M A

N U

FA

C

TU

R

E' S

M A

IN

TE

N A

N C

E D

A

TA

SD

-1

C

LO

SE

O

U T

SU

B

M

IT

TA

LS

SD

-1

46 Section 01 78 00 SD-10 Operation and Maintenance Manuals

47 Section 01 78 00 SD-11 Para 3.1.2 As-Built Drawings X

Section 01 78 00 SD-11 As-Built Record of Equip and Materials, Final Approved Shop Dwgs

49 Section 01 78 00 SD-11 Para 3.9.1 Interim DD Form 1354 X

50 Section 01 78 00 SD-11 Para 3.9.1 Checklist for DD Form 1354 X

51 Section 02 83 33.13 Para 1.5 Pre-Removal Meeting Agenda X

Section 02 83 33.13 Para 1.6, B, Manufacturers Literature and

Data X

Section 02 83 33.13 Para 1.6, B, 2 Safety Data Sheets for Each

Paint Removal Product X

Section 02 83 33.13 Para 1.6, B, 3 Installation Instructions, a.

Paint Removal Products X

Section 02 83 33.13 Para 1.6 Qualifications, C 1-4 (Paint

Removal Contractor, Testing Laboratory, Industrial Hygienist, Paint Disposal Facility)

X

Section 02 83 33.13 Para 1.6 Record Documents D, 1-4

(Hazardous Waste Manifest from Transporter, Paint Disposal

Facility Receipts, Certification of Medical Examination, and

Employee Training Certifications)

X

Section 02 83 33.13 Para 1.7, B, Paint Removal Contractor

Certification X

Section 02 83 33.13 Para 1.7, C, Paint Disposal Facility

Certification X

Section 02 83 33.13 Para 1.7, D 1-4 Lead-Based Paint Removal

Plan X

Section 02 83 33.13 Para 1.7, G 1-8 Hazardous Waste

Management Plan X

Section 05 50 00 Metal Fabrications, Para 1.3 Submittals and

Shop Drawings as specified in Drawings Sheets G-003 for Task 3 -

Riser Access Manway, Task 4 - Internal Riser Access Ladder, and

Task 5 - Steel Bar safety Grating.

X

Section 09 91 01 Para 1.3 (B) Elevated Water Storage Tank

Repainting, Para 1.3 Documentation of Painting Contractor

Qualifications and Experience. List of elevated water tower painting projects completed in past five (5) years.

X

AF Form 66 Submittal Register 3/10/2026

PROJECT NUMBER : SOLICITATION/CONTRACT NO.:

SCHEDULE OF MATERIAL SUBMITTALS

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

Use Electronic Delivery

LI

N

E N

U M

B

ER

ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL

All SUBMITTALS LISTED ON THIS SUBMITTAL REGISTER ARE FOR

GOVERNMENT APPROVAL; G

R

EQ

U

IR

ED

S

U B

M

IS

SI

O

N D

A

TE

D A

TE

R

EC

EI

V

ED

IN

C

O N

TR

A

C

TI

N G

D A

TE

T

O C

IV

IL

E N

G

IN

EE

R

IN

G

R

ET

U R

N S

U

SP

EN

SE

D A

TE

SU

B

M

IT

TA

L

N U

M B

ER

S

DATE CONTRACTOR NOTIFIED

C O

N

TR

A C

TO

R

R

ES

U B

M

IT

TA

L

FI

N

A L

A P

P R

O V

A L

REMARKS

APPROVED

DIS-

APPROVED

JCGU 26-7001 Repair Water Tower B738 (West)

PROJECT TITLE:

P R

E- C

O N

ST

R

U C

TI

O

N

SD

-0

SH

O

P D

R A

W

IN

G S

(S D

-0

P R

O D

U C

T D

A

TA

SD

-0

SA

M

P

LE

S (S

D -0

D

ES

IG

N

D A

TA

SD

-0

TE

ST

R

EP

O R

TS

SD

-0

C

ER

TI

FI

C A

TI

O

N S

(S D

-0

M A

N U

FA

C

TU

R

E' S

IN

ST

R U

C

TI

O N

SD

-0

M A

N U

FA

C

TU

R

E' S

FI

EL

D R

EP

O

R

TS

SD

-0

O

TH

ER

SD

-1

M A

N U

FA

C

TU

R

E' S

M A

IN

TE

N A

N C

E D

A

TA

SD

-1

C

LO

SE

O

U T

SU

B

M

IT

TA

LS

SD

-1

Section 09 91 01 Para 1.3 (C) Elevated Water Storage Tank

Repainting, Para 1.3 Documentation of Painting Contractor

Qualifications. Evidence of key personnel have successfully performed surface preparation and application of coating system on a minimum of five (5) similar projects in the past five

(5) years.

X

Section 09 91 01 Para 1.3 (D) Elevated Water Storage Tank

Repainting, Para 1.3 Documentation of Painting Contractor

Qualifications. Evidence of key personnel have successfully participated in apprenticeship and training programs approved and registered with the US DOL Bureau of Apprenticeship and

Training.

X

Section 09 91 01 Para 1.3 (E) Manufacture Literature and Data

(NSF Certification and Quality of Paint) X

File details come from the government source that posted it. Updated .