This document is Addendum 2 for Invitation to Bid (ITB) #4264 for the Boiler Systems Replacement project at the Oregon Department of Forestry (ODF) Tillamook Forest Center. The addendum modifies the bid documents to update the HVAC control system specifications and drawings. It requires bidders to acknowledge receipt of the addendum by signing and returning it prior to the bid closing date. The contract opportunity involves replacing the boiler systems at the Tillamook Forest Center, which is located in Marion County and the City of Salem, Oregon.

The addendum eliminates a contractor qualification requirement related to the manufacturer's certification. It also provides updated technical specifications and drawings that bidders must use. Pricing terms, set asides, funding sources, and other contractual details are not included in this addendum, as it is focused on modifying the technical requirements of the solicitation.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ITB #4264

Boiler Systems Replacement – ODF Tillamook Forest Center Solicitation Addendum #2

This Solicitation Addendum #2 modifies the Bid Document(s) only to the extent indicated herein. All other areas not specifically mentioned or affected by this Solicitation Addendum #2 shall remain in full force and effect. This Solicitation Addendum #2 shall be added as a part of the original Solicitation Document, ITB #4264.

This Solicitation Addendum #2 must be acknowledged by inserting its number on the appropriate blank lines in Section H of the Invitation to Bid and by providing all required signatures prior to Bid Closing. Failure to do so may result in rejection of Bid.

A. Refer to Attachment A, SPECIFICATIONS

1. Delete Section 23 09 23, DIRECT-DIGITAL CONTROL SYSTEM FOR HVAC, in its entirety and replace with the eleven page Section 23 09 23, DIRECT-DIGITAL CONTROL SYSTEM FOR HVAC, dated November 10, 2022, attached to this Solicitation Addendum #2.

2. Delete Section 23 09 93, SEQUENCES OF OPERATION FOR DDC CONTROLS, in its entirety.

B. Refer to Attachment B, DRAWINGS

1. Delete the following four sheets in their entirety and replace with the sheets attached to this Solicitation Addendum #2:

a. M-501

b. M-502

c. M-601

d. M-701

C. Delete the second required qualification in Subsection 3, CONTRACTOR QUALIFICATIONS, of Section I, RESPONSIBILITY INQUIRY/CONTRACTOR REFERENCES/ESB UTILIZATION, in its entirety as follows:

Contractor has a minimum of 5 years experience installing the manufacturer’s product being bid and shall provide a manufacturer’s letter certifying that the contractor is certified to install, maintain and work on the vendor’s equipment. (Contractor must submit supporting documentation with Bid) This Solicitation Addendum #2 constitutes a MATERIAL CHANGE to ITB #4264. IT MUST BE SIGNED AND RETURNED PRIOR TO THE BID CLOSING DATE AND TIME. ITS RECEIPT MUST ALSO BE ACKNOWLEDGED BY INSERTING ITS NUMBER ON THE APPROPRIATE BLANK LINES IN SECTION H OF THE BID DOCUMENT.

Signature: _____________________________________ Date: ____________________

Bidder Name: ____________________________________________________________

(Please Print) ITB # 4264 Addendum #2